Rules for determining the material adjustment base price (C0): base date, one-of-three sources and the adjustment computation base (GB/T 50500-2024)
The base price C0 = the market price level 28 days before the bid closing date (for non-tendered works, 28 days before contract signing); that instant is the contract base date (term 2.0.21). The source is one of: (1) the market price used in the maximum bid price; (2) the current quarter's (month's) guidance price of the cost management agency; (3) the winning-bid price of analogous works under the same conditions published by the local trading center — all must represent the base-date price level, and the tender documents must state the source, publishing agency and specific quarter (month). Where the guidance price is the base, whether the bid is below/above/equal to the base decides the computation base of the excess portion (appendix A.2.4, preventing high/low-bid arbitrage); the price-index method corresponds to the basic price index F0.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.1
- GB/T 50500-2024 术语2.0.21
- GB/T 50500-2024 App. A.2.4
- GB/T 50500-2024 第8.7.2条
- GB/T 50500-2024 第3.3.5条
- GB/T 50500-2024 App. G.2.1
Topic Positioning
This card explains determining the material adjustment base price (C0) under GB/T 50500-2024: base-date locking, one-of-three sources, the tender-document disclosure duty, and the adjustment computation base under the bid-vs-base relations (appendix A.2.1, A.2.4, term 2.0.21).
Core Conclusions
Base price = the market price level 28 days before the bid closing date (for non-tendered works, 28 days before contract signing); that instant is the contract base date, serving as the base for both price-change and regulation/policy adjustments. Source, one of three: (1) the market price used in the maximum bid price; (2) the cost management agency's guidance price for the quarter (month); (3) the winning-bid price of analogous works of the same period (within the prior month) and conditions published by the trading center at the project location — all must represent the base-date price level; the tender documents must state the source, publishing agency and specific quarter (month). With the guidance price as base (A.2.4): where the bid is below the base, upward excess is computed on the base and downward excess on the bid; above, the reverse; equal, both on the base — preventing high/low-bid arbitrage. The index method corresponds to the basic price index F0, its source agreed by the parties in the contract. A contractor with objections should request clarification within the time fixed before bidding.
Applicable Boundaries
Applies only to contract-price adjustment caused by price changes (appendix G.2.1 tables are exclusive to this class). Source and band follow the contract first; this card is the statutory fallback caliber; absent an agreed band, fluctuation beyond 5% triggers adjustment (clause 8.7.2); the difference carries VAT only, no management fee or profit (clause 3.3.5). Determining the current price Ci of the measurement period is outside this card.
Further Reading
See GB/T 50500-2024: term 2.0.21 (contract base date), appendix A.2.1 (difference formula and three sources), appendix A.2.4 (adjustment bases under three bid relations), appendix A.1.6 (F0), appendix G.2.1, clauses 3.3.5 and 8.7.2.