Overview of material price adjustment in construction works: applicable conditions, base price (reference price for adjustment), risk band, and calculation methods (GB/T 50500-2024 Sections 3.3/8.7 and Appendices A, G)
Four indispensable elements of material price adjustment: ① adjustable scope (only labour cost, principal material cost, and construction machinery fuel and power cost, listed per Appendix G.2 Tables G.2.1-1/2 as a contract annex); ② base price (reference price for adjustment) C₀ (the market price level 28 days before the tender deadline (= FIDIC Base Date), or for non-tendered works 28 days before contract signing); ③ risk band r (contractual agreement takes precedence, in practice 3%–5%; where absent or unclear, a cost fluctuation beyond 5% triggers); ④ quantities subject to price adjustment Q (per the contract's agreed rules). Trigger |Ci−C₀|/C₀>r; upward unit price for the excess beyond the band = Ci−C₀(1+r), downward = C₀(1−r)−Ci; price difference = Σ unit price for the excess beyond the band × Q, carrying value added tax (VAT) only, with no management fee or profit.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- T/ZBD 100.5-2023 建设工程结算审核作业指引
- 建设部令第107号 建筑工程施工发包与承包计价管理办法
Topic Positioning
The master card of material price adjustment: per GB/T 50500-2024 Sections 3.3, 8.7 and Appendices A, G, it sorts out the four elements — applicable conditions, base price (reference price for adjustment), risk band, calculation methods — and the accompanying iron rules; details are in the cited sub-cards.
Core Conclusions
All four elements are indispensable: ① scope — only labour cost, principal material cost, and construction machinery fuel and power cost are adjustable; principal materials fill Appendix G.2 Tables G.2.1-1/2 as a contract annex; ② base price (reference price for adjustment) C₀ — the market price level 28 days before the tender deadline (= FIDIC Base Date), or for non-tendered works, 28 days before contract signing; ③ risk band r — contractual agreement takes precedence (in practice 3%–5%); where absent or unclear, a cost fluctuation beyond 5% triggers (8.7.2); ④ quantities subject to price adjustment Q — per the contract's agreed rules. Trigger |Ci−C₀|/C₀>r; upward unit price for the excess beyond the band = Ci−C₀(1+r), downward = C₀(1−r)−Ci; price difference = Σ unit price for the excess beyond the band × Q, carrying value added tax (VAT) only, with no management fee or profit (3.3.5). On schedule delays, prices follow responsibility (employer-caused takes the higher, contractor-caused the lower, 8.7.4); construction consumables, preliminaries, and management fee and profit are not adjusted (8.7.6).
Applicable Boundaries
Statute first, agreed terms prevail: where there is an agreement, follow the contract; the standard applies only as the fallback where there is none; agreements imposing an uncapped risk allocation to one party or 'all risks' are prohibited (3.3.1); lump-sum contracts are in principle not adjusted for cost fluctuation; the base price (reference price for adjustment) and construction-period price must share the same basis and source. This card is the master outline; sub-topics are in the cited cards.
Further Reading
GB/T 50500-2024: Appendix A.2.1 formula, A.2.4 the tender-vs-base price relation, A.2.3 multi-price averaging, A.2.5 the purchase price method, Appendix A.1 the index method, Appendix G.2, Clauses 8.7.1–8.7.6, 3.3.1–3.3.5, terminology 2.0.21; with T/ZBD 100.5-2023 Clause 3.1.7 and Construction Ministry Order No. 107, Article 12.
Keywords
Related Cards
- →
GB/T 50500-2024 rules for adjusting price differences, management fee, and tax after the actual price of provisionally priced materials/equipment is determined (Section 8.4)
Per GB/T 50500-2024 Section 8.4, once the actual price of provisionally priced materials (including engineering equipment) is determined, only the material provisional-price item in the all-in unit rate is adjusted (pre-tax difference = confirmed actual pre-tax unit price − provisional pre-tax unit price, times quantity); labor, machinery, management fee, profit and other costs are not adjusted; VAT is charged additionally on the difference and the contract price is adjusted. Replacement price: for items subject to mandatory tendering by law, the pre-tax winning purchase price replaces it; otherwise, the pre-tax inquiry/own-quote price confirmed by the employer. Specialist-work provisional prices are VAT-inclusive, replaced wholesale by the winning VAT-inclusive subcontract price — a different rule.
- →
Priority of price bases for construction payment settlement: contract agreement > price confirmed by both parties > published price information > market price enquiry (purchase contract / invoice prices require the employer's approval of material prices)
Bases for settlement by priority: ① contract-agreed price (fundamental basis); ② price confirmed by the employer and contractor (certified record of agreed material prices — report quantity and unit price to the employer for verification before purchase; deemed approval upon lapse of the response period); ③ published price information (base price for adjustment / dispute fallback); ④ market price enquiry (for provisional sums and materials without published prices). Purchase contract prices and invoice prices only prove actual cost and become a basis for settlement only after the employer's approval of material prices.
- →
Steel price adjustment calculation: price-information adjustment formula, per-specification per-period threshold checks with adjustment on actual basis, and tax treatment (GB/T 50500-2024 Appendix A.2)
Steel price adjustment uses the price-information adjustment method (GB/T 50500-2024 Appendix A.2): △P = Σ[(Ci − C0·(1±r)) × Q] × (1 + VAT rate), adjusting only the portion beyond the risk band on an actual basis; the agreed risk band prevails, with the beyond-5% fallback where not agreed or unclear (8.7.2). Each specification must be checked independently each period for exceeding the risk band (base prices, published price information, and increase rates differ; specifications within the risk band are not adjusted for the period); the price difference carries VAT only, no management fee or profit (3.3.5); when checking adjustment tables, first look at whether the bid price is above or below the base price (A.2.4 determines the excess-calculation base).
- →
Material price adjustment channels under fixed lump-sum contracts: no adjustment within the agreed risk band, adjustment beyond the risk band, mandatory adjustment for statutory causes
Under a fixed lump-sum contract, cost fluctuations within the agreed risk band are not adjusted, but "fixed" ≠ an uncapped lump sum: ① contract-agreed price adjustment clauses are applied as agreed; ② where no risk band is agreed or the agreement is unclear, the portion of labour cost, principal material cost and construction machinery fuel and power cost fluctuating beyond 5% may be adjusted per Appendix A (8.7.2 fallback); the standard prohibits uncapped risk allocation to one party / "all risks" lump-sum wording (3.3.1), and cost movements beyond the agreed risk band are borne by the employer (3.3.2); ③ materials under government pricing/guidance pricing follow the new prices; ④ policy-driven adjustments to labour cost; ⑤ abnormal large fluctuations may be negotiated under the change of circumstances doctrine (8.7.3). Price adjustment claims under lump-sum contracts are procedurally handled as claims (T/ZBD 100.5-2023 3.1.7); price differences carry value added tax (VAT) only, no management fee or profit (3.3.5).
Cited By
- ←
Differences in final account adjustment between lump-sum contracts (fixed total price) and unit-rate contracts (fixed unit rates): treatment rules for quantity changes, BOQ errors, design changes and cost fluctuation, mapped to GB/T 50500-2024 clause numbers
GB/T 50500-2024 uses 'lump-sum contract / unit-rate contract' rather than 'fixed total price / fixed unit rate'; the substantive difference lies in the allocation of quantity and price risk. A lump-sum contract wraps up both quantities and prices - the measured-works BOQ items need not be re-measured, and price changes arising from BOQ errors are deemed included in the contract total and are not adjusted during performance (clauses 4.1.6, 7.2.2, 8.2.3); only 'provisional quantity' unit-rate-priced items and variations may be adjusted. A unit-rate contract fixes the rates and re-measures the quantities - all BOQ items and quantities of the measured works must be re-measured, BOQ errors fall on the employer, and quantity changes are priced under clause 8.9.1 or clause 8.9.2 depending on the 15% (inclusive / exclusive) boundary (clauses 2.0.6, 4.1.4, 8.2.1). The adjustment rules for cost fluctuation (where no band is agreed, adjustment under Annex A is allowed once the movement exceeds 5%, the differential bearing VAT only, with no overheads or profit) and for changes in laws and regulations and policy are identical for both contract types.
- ←
Splitting the remedy paths and procedural requisites when material prices rise: whether to go first for contract price adjustment (price adjustment for cost fluctuation) or for a works claim; the time limits, written requisites and negotiation sequence of each path; and the consequences of a missed or wrong procedure (GB/T 50500-2024 cl. 8.7, cl. 8.11 and Annex A; Civil Code art. 533; Fa Shi [2026] No. 12 art. 9)
The first path for a material price rise is contract price adjustment, not a claim: GB/T 50500-2024 cl. 8.11.2 states that where an event has already had its price adjustment calculated under the contract price adjustment provisions (excluding claims), no further works claim shall be calculated - duplicate claims will be disallowed. The adjustment path runs: report quantities and unit prices before procurement -> employer checks and confirms (no reply within the agreed period is deemed approval; GF-2017-0201 general conditions 11.1 gives 5 days) -> adjust under cl. 8.7.2 (fluctuation beyond 5% where the contract sets no band) per Annex A -> submit the price adjustment report, employer verifies and confirms (cl. 8.1.3) -> confirm, sign and pay together with the progress payments / interim settlement by construction stage payments (cl. 8.1.6). Only where the contract provides no adjustable price, for abnormal fluctuation of non-adjustable materials (cl. 8.7.3), or where the rise intertwines with delay losses does the claim path open: Notice of Claim (within the contract-agreed period after the event, 28 days where unspecified) -> claim report (28 days after the notice) -> employer 14 days to request further particulars, 28 days to reply -> confirm, sign and pay; a late notice 'may be treated as waived', and the other party's late reply 'may be deemed accepted'. For fixed-price settlement, requests to adjust solely for major changes in labour cost or key material prices within the construction period are not supported by the courts (Fa Shi [2026] No. 12 art. 9), unless otherwise agreed or qualifying as change of circumstances under Civil Code art. 533.
- ←
Valuation rules for the four variables of material price adjustment (adjustment based on published price information) and the step-by-step calculation flow: base price C0, risk band r, measurement-period market price Ci and adjustable quantity Q (GB/T 50500-2024 Annex A.2)
The published-price-information method takes its values in five steps. (1) C0 = the market price level 28 days before the tender submission deadline (for non-tendered works, 28 days before the contract signing date), one source chosen from three (the market price used in setting the tender price ceiling / the quarterly (monthly) published price information of the cost administration body / award prices of comparable projects published for the same period by the trading centre); the tender documents must state the source, the issuing body and the specific quarter (month). (2) r: the contractual agreement prevails; where none exists or it is unclear, adjustment is allowed once the movement exceeds 5% (clause 8.7.2), the sign of r following the sign of dC (positive on increase, negative on decrease). (3) Ci takes the current price of the measurement period; with multiple prices, use the arithmetic mean / the weighted mean against executed quantities / the price over the main-consumption construction period; where a price is missing or disputed, published price information may be used provisionally and trued up later; purchase prices must be submitted to the employer for verification before purchase, silence within the time limit being deemed approval. (4) Q is calculated under the contractual quantity calculation rules. (5) Adjustment only where |Ci - C0| / C0 > r; on increase the excess unit differential = Ci - C0(1+r), on decrease = C0(1-r) - Ci; multiplied by Q it bears VAT only, with no overheads or profit.
- ←
Main-material price surge beyond the risk band: sequencing between GB/T 50500-2024 Section 8.7/Appendix A price adjustment and Civil Code Article 533 change of circumstances
When main-material prices surge far beyond the contractual risk band, first complete price adjustment per GB/T 50500-2024 Section 8.7 and Appendix A (agreed risk band first; 5% fallback when unspecified/unclear; portions beyond the risk band at actual values, differences carrying VAT only, no management fee/profit); only the residual loss still grossly unfair after adjustment proceeds to 8.7.3 negotiation, and failing negotiation to Civil Code Article 533 modification or termination — a "contract first, statutory fallback" progression, not either-or. Judicial appraisal per GB/T 51262-2017 5.6.2: as agreed if agreed; adjustable but without an agreed risk band — the appointing party decides judicial appraisal per the national standard (unless already index-adjusted); agreed non-adjustable — government-priced/guided materials appraised per old Contract Law Article 63 (now Civil Code Article 513).
- ←
Hierarchy of effect and order of interpretation when tender documents, bid documents and the awarded contract conflict over material price adjustment (adjustment of the works price): substantive content follows the tendering and bidding documents; conflicts that are not substantive follow the priority order of contract documents (particular conditions first; later signing of the same class first) and the limits of those rules
A price-adjustment clause is part of the pricing and adjustment method of the 'works price' and so falls within the reach of substantive content: where the awarded contract differs from the tender documents, bid documents or letter of acceptance, those documents govern settlement of the works price (Bidding Law Art. 46; Implementation Regulations Art. 57; Fa Shi [2020] No. 25 Arts. 2 and 22). Internal conflicts not amounting to substantive departure are construed by the priority order of contract documents (GF-2017-0201 Clause 1.5: contract agreement > letter of acceptance > letter of tender with appendices > particular conditions > general conditions > technical standards > drawings > priced BOQ > other documents; for documents of the same class the latest signing prevails), that is 'particular over general, later over earlier within the same class'; but 'later over earlier' is a rule of interpretation, not a power of variation, and cannot give variation effect to a later agreement that departs from substantive content (Civil Code Art. 544: a variation whose content is unclear is deemed not varied). Where the position still cannot be fixed, construe comprehensively under Civil Code Arts. 142 and 466 and Fa Shi [2023] No. 13 Art. 1.
- ←
Allocating the works cost saved through design optimisation in EPC (engineering, procurement and construction) contracting between employer and contractor: the Particular Conditions entry on 'value engineering benefit sharing' is the sole basis of a claim, and no statutory sharing ratio exists absent agreement; the saving must be verified through valuation of variations and stripped of price differentials and similar factors on a like-for-like basis, and under a fixed lump-sum contract the saving usually settles directly as the contractor's cost surplus
No statutory sharing - only contractual sharing: General Conditions of GF-2020-0216, Sub-Clause 13.2.3, reads 'Where a value engineering proposal reduces the contract price, shortens the time for completion or improves the economic benefit of the works, the parties may share the benefit as agreed in the Particular Conditions' - 'may' plus 'as agreed in the Particular Conditions' means there is no sharing claim without agreement; a blank, a slash, or 'to be negotiated separately' in that Particular Conditions entry is presumed to be no variation under Civil Code, Article 544. Sharing amount S = (C0 - C1) x r x k, where r is the contractually agreed ratio (r = 0 if not agreed; the industry '30/70 or 50/50' splits are negotiating convention, not a standard), C0 and C1 must share the same scope, VAT status and base period, and C1 is determined under the variation valuation rules of Sub-Clause 13.3.3.1. Under a fixed lump-sum contract (the default form under Sub-Clause 14.1.1) the contract price is not reduced for optimisation, the saving settles as the contractor's surplus, and no 'allocation' generally arises.
- ←
Construction Interpretation II, Article 9: where the contract stipulates settlement of the project price at fixed prices, a request to adjust the price on the ground of material changes in labour costs or the prices of key building materials within the construction period is not supported, leaving only two exits: 'the parties have otherwise agreed' and 'change of circumstances under Article 533 of the Civil Code'
In principle, not supported. Under Fa Shi [2026] No. 12 Article 9, where a construction contract stipulates settlement of the project price at fixed prices and a party requests adjustment on the ground of material changes in labour costs or the prices of key building materials within the agreed construction period, the people's court shall not support the request, unless the parties have otherwise agreed or the case satisfies Article 533 of the Civil Code on change of circumstances. Three points of distinction: (1) the rule negates 'adjustment requests premised on material price changes'; it does not invalidate the fixed-price clause; (2) 'the parties have otherwise agreed' is the most-used channel - where the contract lists adjustable materials, agrees a base price and a risk band, an adjustment formula or a source of published price information, adjustment follows the agreement and is not blocked by this Article; (3) only one judicial channel remains, change of circumstances, with a high threshold (unforeseeable at contract formation, a material change outside commercial risk, and manifest unfairness on continued performance) and prior negotiation required.
- ←
Whether a supplier may seek a price adjustment when building material prices rise sharply during a fixed-price procurement (sales) contract: routing by contract type (procurement contracts via sales contract rules plus change of circumstances; construction contracts via Interpretation II Article 9; government pricing via Civil Code Article 513), a comparison of three adjustable exceptions and five unsupported scenarios, a legal basis list, and points on evidence, time limits and jurisdiction
As a rule, no. A supplier who has signed a fixed-price procurement contract cannot request an increase merely because building material prices have risen sharply: a fixed price is itself the allocation of price risk, and rises and falls are commercial risks the supplier should bear at the time of contracting. Only three exceptions allow an adjustment: (1) the contract provides otherwise for price adjustment / price fluctuation adjustment (including provisional prices, market-following pricing, or settlement at published price information), adjusted within the agreed band; (2) the subject matter is under government pricing or government guidance pricing and the government adjusts the price within the delivery period, in which case the price at the time of delivery applies (Civil Code Article 513); (3) the case satisfies change of circumstances under Civil Code Article 533 (unforeseeable at contracting, not a commercial risk, continued performance manifestly unfair, and renegotiation required first), and the subject matter is not a bulk commodity of active market attributes with large long-term price fluctuations -- steel, cement and other principal building materials fall squarely within the exclusion proviso of Article 32(1) of Fa Shi [2023] No. 13, so this route usually fails. Fixed prices in construction contracts are governed separately by Article 9 of Fa Shi [2026] No. 12, which leaves only two exits: contrary agreement or change of circumstances.
- ←
Rules for handling contract price adjustment for cost fluctuation in final account review and construction cost expert assessment: routing by contract type, price-dating principles for delay periods, the exception for government-priced materials, and the eight categories of costs not adjusted for changes in costs listed in GB/T 50500-2024 clause 8.7.6
Final account review and expert assessment proceed on two levels. (i) Routing by contract type: for lump-sum contracts, unless otherwise agreed, cost fluctuation is generally not adjusted, and a contractor claiming adjustment for change of circumstances or prolonged duration must proceed by claim; for unit-rate contracts the agreement prevails, and absent or unclear agreement the matter is resolved by reference to national, local or sector provisions, with labour, materials and plant outside the contractually adjustable scope not adjustable. Price-dating during delay: where the delay is not attributable to the contractor, the higher of the prices at the planned and actual progress dates applies; where attributable to the contractor, the lower applies; concurrent delay is shared by sequence and responsibility. (ii) Hard constraint on the scope of adjustment: GB/T 50500-2024 clause 8.7.6 lists eight categories of costs not adjusted for changes in costs (construction consumables, small and medium tools, preliminaries, plant and small tools costs other than fuel and power, material costs of items outside the agreed adjustable list, changes beyond the agreed scope or band, overheads and profit, and costs arising from the contractor's own causes); where the contract sets no band or sets it unclearly, fluctuation beyond 5% may be adjusted per Annex A (8.7.2), and abnormal movements of other materials outside the agreed adjustable scope may be handled by equitable risk allocation, by negotiation or by adjustment to actual costs (8.7.3, 3.3.6).
- ←
Dividing price and quantity gaps of employer-supplied (free-issue) materials: price gaps to the employer and outside the contractor's adjustment scope, quantity gaps bounded by the effective wastage rate, custody and freight splitting at the delivery point with unloading (GB/T 50500-2024 clauses 3.6.1, 3.2.4, 3.6.3, 6.2.4, 8.7.5; against GB 50500-2013 clause 3.2.1)
Price gaps are the employer's and never enter the contractor's adjustment: 3.6.1 - 'at bidding, the prices of employer-supplied materials do not enter the all-in unit rates'; 3.2.4 - 'the material cost of employer-supplied materials does not enter the work-item list'; 8.7.5 - 'the material adjustments of 8.7.2~8.7.4 are not suited to employer-supplied items... adjustable by the employer on actual changes but not listed in the contract total' - the gap between actual purchase and contracted prices is the employer's own, forming no contractor adjustment income and no downward contract revision. Quantity gaps split at the effective wastage rate: contractor-caused over-draws are borne by the contractor per 3.6.3, clawed back at supply-contract prices from interim or final payments; within the rate, and employer-caused excesses (specification mismatch pushing wastage beyond the rate; employer-caused over-draws), fall on the employer. Custody and freight split at 'delivered to the delivery point and unloaded': before, the employer's (6.2.4 - bid rates exclude those costs); after, site custody, double handling and own installation wastage are the contractor's, coordination and custody services charged to the employer in attendance provisions (3.6.4).
- ←
Choosing among the three bases of material price adjustment (bid price / base-period published information / jointly confirmed price): statutory sources, defaults, difference-rate versus risk-band linkage and item-by-item locking (GB/T 50500-2024 term 2.0.21, Appendix A.2, G.2.1)
Per GB/T 50500-2024 Appendix A.2.1, the base price C0 is 'the market price level at the base date (28 days before the tender deadline; non-tendered, 28 days before contract signature)' with only three statutory sources: the market prices used for the tender price ceiling, the cost authority's current-quarter (month) published information, and award prices of like works from the trading centre of the same period and conditions - the tenderer must state the source, publisher and specific quarter (month). The bid price is thus not a statutory C0 source (Table G.2.1-1: base price and risk band by the tenderer, bid price by the bidder), and the confirmed price corresponds in A.2.1 to a source of the current period price Ci - both rise to C0 only by express contract. Difference rate = (Ci - C0) / C0 x 100%; against the risk band r only the excess adjusts: rising, unit difference = Ci - C0 x (1 + r); falling, = C0 x (1 - r) - Ci; the amount x Q carries VAT only, never overheads or profit (3.3.5); absent an agreed band, swings beyond 5% adjust (8.7.2).
- ←
The step chain of adjusting on published price information: fix the adjustable list -> lock base price C0 -> take period prices Ci -> difference x adjustable quantity Q -> adjust the excess over the risk band -> book into progress and settlement, with fallbacks for missing periods and items and the Q test (GB/T 50500-2024 Appendix A.2; against superseded GB 50500-2013 Appendix A.2)
Six steps: (1) fix the adjustable material / labour list (2024: 3.3.5 item 2 + Appendix G Tables G.2.1-1/-2; 2013: 9.8.2 agreed scope, else over 5% adjusts the excess) -> (2) lock C0 = the market price 28 days before the tender deadline (non-tendered: signature), source, publisher and quarter (month) stated (A.2.1; 2013 A.2.3) -> (3) take Ci per measurement period; several prices within a period take the arithmetic mean, the quantity-weighted mean or the main-consumption-period price (A.2.1, A.2.3) -> (4) difference x Q (2024 A.2.1 formula; 2013 has only the 'excess on actuals' principle, no explicit formula) -> (5) adjust only beyond the agreed band r (rising Ci - C0(1+r), falling C0(1-r) - Ci; absent a band, over 5% - 8.7.2 / 2013 9.8.2) -> (6) book into cumulative progress and pay with progress and interim settlements (9.4.6, 8.1.6). Missing periods fall back in order: contract rule -> same-period alternative source -> in-period averaging -> provisional posting on current information with later truing (A.2.2) -> employer-recognised purchase price (A.2.5; 2013 A.2.3 item 4: 3 working days' silence deems approval; unreported self-purchase refused by the employer never adjusts) -> market enquiry by three parties; 'carry the last period forward' has no national-text basis outside the index method (2013 A.1.2). Q follows the contractual quantity rule; the default is the consumption of measured completed work - never signed list quantities or purchase / invoice totals; differences carry VAT only (3.3.5 item 4).
- ←
Defining the scope of adjustable (price-adjustable) materials: locked by contract annex tables, not share thresholds; auxiliary and low-value materials outside adjustment (neither coefficient-merged nor overheads-lumped); the negotiation channel for unlisted materials' abnormal swings (GB/T 50500-2024 clauses 3.3.1, 3.3.5, 8.7.3, 8.7.5, 8.7.6; Appendix G.2, A.2.1)
GB/T 50500-2024 sets no material-cost share threshold: the adjustable scope locks item by item in annex Tables G.2.1-1 / G.2.1-2 (Appendix G.2) - tenderer filling name, specification, unit, base price and risk band, bidder the price, quantities per the contractual rule (3.3.5, G.2.1). Auxiliary and low-value materials (consumables, small tools, preliminaries, non-agreed materials) plus overheads and profit never adjust for price moves (8.7.6) - there is no national channel 'merging auxiliaries by coefficient', nor are they an overheads lump: their price risk sits inside the material cost of the all-in rate. Unlisted materials adjust in principle never; only on abnormal, unforeseeable-at-contracting moves making performance plainly inequitable may the parties negotiate band or sharing per equitable allocation (8.7.3). Free-issue and provisionally priced items sit outside 8.7.2~8.7.4 (8.7.5). Local share-threshold practices are local documents - verify current numbers.
- ←
Fee boundary for material price adjustment: the price difference carries VAT only, with no management fee or profit; the eight cost categories under Clause 8.7.6 are not adjusted (GB/T 50500-2024)
Per GB/T 50500-2024 Clause 3.3.5 item 4, price differences of labor, materials, and machinery fuel/power carry VAT only — no management fee or profit; Clause 8.7.6 lists eight categories not adjusted for price changes (construction consumables, small tool usage, preliminaries, other machinery usage beyond fuel/power, materials outside agreed adjustable items, changes beyond the agreed scope and band, management fee and profit, contractor's own-cause costs); Clause 8.7.3 opens a negotiation exception for abnormal, unforeseeable fluctuations.
- ←
The direction of price adjustment for legal and policy changes during delay (extension) periods: contractor-caused delay takes no rises but all falls; employer-caused the reverse; neither-party delay adjusts on actuals (GB/T 50500-2024 clauses 8.8.1~8.8.4)
Direction follows fault: for contractor-caused extension, policy changes in the extension window bring no upward adjustment and all downward adjustments; for employer-caused extension, no downward and all upward; neither-party extension adjusts on actuals (save contract or other provision). Events are limited to legal and policy changes after the contract base date (enactment / amendment / repeal / changed government interpretation). Basis: GB/T 50500-2024 clauses 8.8.1~8.8.4; the model contract parallels GF-2017-0201 clause 11.2.
- ←
Contract price adjustment for changes in laws, regulations and policies: the base date (28 days before the tender deadline / 28 days before contract signature) and the rule for contractor-caused delay that 'upward adjustments are denied, downward adjustments are granted' (GB 50500-2013 Section 9.2; GB/T 50500-2024 Section 8.8)
GB 50500-2013 Clause 9.2.1: for tendered works the base date is 28 days before the tender submission deadline, and for non-tendered works 28 days before contract signature; where changes in State laws, regulations, rules and policies afterwards increase or decrease the construction cost, the contract price is adjusted per the provisions issued accordingly by the provincial or sectoral construction authority or its authorised construction cost administration. Clause 9.2.2: where the time is delayed for reasons attributable to the contractor, upward adjustment of the contract price after the originally scheduled completion time is denied and downward adjustment is granted. Changes in laws and policies are a risk borne by the employer (Clause 3.4.2 item 1). GB/T 50500-2024 carries this forward in Clause 8.8.1 (four categories: newly added, amended, repealed, re-interpreted) and Clause 8.8.2 (during delay, increases denied, decreases granted).
- ←
Direction-specific base rules in the price adjustment method based on published price information when the contractor's tender price deviates from the base price (GB/T 50500-2024 Annex A.2.4, corresponding to Section 9.7 of the superseded GB 50500-2013): rises judge on the higher of the two prices, falls on the lower, a two-way disadvantage that blocks arbitrage, with the selection boundary against the Annex A.1 index method
Under GB/T 50500-2024 Annex A.2.4, the published-price-information adjustment applies a direction-specific base: the base for upward adjustment (price rise) is the higher of the base price C0 and the tender price P, and the base for downward adjustment (price fall) is the lower of the two. Hence when the contractor's price is below the base price (P < C0), rises are judged on the base price C0 and falls on the tender price P; when the price is above the base price (P > C0) the reverse applies; when the price equals the base price, both directions are judged on C0. Only the portion crossing the risk band threshold is adjusted as actually incurred; below the threshold nothing is adjusted; and the price differential carries VAT only, with no overheads or profit (3.3.5).
- ←
Determining plant and small tools cost within the all-in unit rate: consumption × plant rate per machine-shift, 7-item/4-item composition of the plant rate per machine-shift, and adjustment for price differentials
Plant and small tools cost = construction machinery usage cost + construction instrument and meter usage cost, both determined as machine-shift consumption under quota norms (prescribed resource consumption standards) × plant rate per machine-shift (GB/T 51095-2015 Clause 5.3.9; TB 10801-2024 Section 3.3). The plant rate per machine-shift for construction machinery has 7 items = depreciation + overhaul + maintenance + assembly and disassembly + labour + power + other costs; the plant rate per machine-shift for instrument and meter has 4 items = depreciation + maintenance + verification + power; both are computed on an 8-hour working shift. Where machine-shift cost quota norms exist, take the price per the quota norms (railway TB/T 10814-2024, base-period price excluding deductible input value added tax (VAT)); the difference between base period and compilation period is listed as an adjustment for price differentials of plant and small tools cost. When fuel and power prices fluctuate beyond the agreed risk band (no-adjustment tolerance, e.g. ±5%; where not agreed, 5%), price adjustment (for fluctuation) applies; the price difference carries VAT only, with no management fee or profit (GB/T 50500-2024 Clauses 8.7.2, 3.3.5).
- ←
The relationship between the risk allowance inside the all-in unit rate and contractual price adjustment for fluctuation: within the band the risk allowance absorbs the movement, beyond the band only the excess is adjusted, and the two are never counted twice
The risk allowance and contractual price adjustment are a two-stage allocation of the same pricing risk against the risk band r agreed in the contract: within r, the movement is absorbed by the risk allowance implied in the all-in unit rate (not billed as a separate item, not repaid at settlement); when the movement exceeds r, the adjustment rules adjust only the excess. The exclusion of double counting runs both ways - GB 50500-2013 Clause 6.2.2 states that 'when the risk content and its scope (band) that arises falls within the range agreed in the contract, the contract price shall not be adjusted'; GB/T 50500-2024 Clause 3.3.5 states that the price differential adjustment 'shall carry VAT but shall not carry management fee or profit', and Clause 8.7.6 states that management fee and profit, preliminaries and other plant and small tools costs shall not be adjusted for changes in costs, that is, an above-band adjustment may not be stacked with risk allowance / management fee / profit. Clause numbers must not be mixed across editions: in the 2013 edition the all-in unit rate is Clause 2.0.8 and the risk allowance is Clause 2.0.9; in the 2024 edition the all-in unit rate is Clause 2.0.9 (excluding VAT).
- ←
Provisional prices (materials / specialist works): the settlement adjustment procedure of replacing the provisional price with the actual confirmed price - legal position, the submission-checking-review-re-examination-confirmation chain and deemed approval on expiry, the two confirmation routes (compulsory tendering and otherwise), adjusting only the pre-tax material price, the deduction direction when the confirmed price is lower, the boundary against material price adjustment, and the clause mapping of GB/T 50500-2024 against GB 50500-2013
The final account replaces the provisional price with the 'confirmed price' (the tender-winning pre-tax price, or the tax-inclusive tender-winning specialist subcontract price, for items that must be tendered by law; or the pre-tax price from market enquiry or the contractor's own quotation confirmed by the employer for items outside compulsory tendering); published price information is not a basis for settlement adjustment (it only guides the provisional unit rate when compiling the tender price ceiling, or serves as the adjustment baseline where the contract makes that material price-adjustable); the procedure runs under GB/T 50500-2024 clauses 8.1.2 to 8.1.6 - submission, checking, review, re-examination and confirmation - and failure to confirm or comment within the time limit is deemed approval; the adjustment replaces only the material provisional price inside the all-in unit rate (pre-tax); labour, plant, overheads and profit do not move (clause 8.4.6), VAT being charged on the difference; where the confirmed price is below the provisional price the adjustment runs the same way down, deducted from the current progress payment or interim settlement by construction stage, and the final account lists 'provisional price adjustment amounts' separately; BOQ items carrying material provisional prices are outside the material cost adjustment of clauses 8.7.2 to 8.7.4 (clause 8.7.5). The 2013 counterparts are clauses 9.9.1 to 9.9.4.
- ←
Selecting between the two methods of contract price adjustment for changes in costs: comparison of applicable conditions, clause-by-clause contrast and same-contract mixing boundaries of the Appendix A.1 index-based adjustment and the Appendix A.2 adjustment based on published price information under GB/T 50500-2024
The two methods share an identical adjustable scope, base time point and trigger threshold (only labour cost, key material cost and the fuel and power cost of construction plant are adjustable; the base time point is 28 days before the tender deadline; where the contract sets no band or sets it unclearly, fluctuations beyond 5% are adjustable; the differential carries VAT only, never overheads or profit). The difference lies only in the price variable. A.1, index-based (formula) adjustment, takes the VAT-exclusive contract price P0 as the base and weights the fixed weight A and the variable weights B1...Bn of each adjustable factor by the ratio 'current index / base index' - the index source is agreed in the contract, the agreed fluctuation band is folded into the base price index, and where an index is missing the previous measurement period's index may be used provisionally. A.2, adjustment based on published price information, takes the adjustable factor quantity Q as the base and computes the money price differential between the base price C0 and the measurement-period market price Ci less the risk band coefficient r; the base price and the market price are each chosen from three sources (market price used in setting the tender price ceiling / published price information of the cost management agency / tender-winning prices published by the trading centre), whether the band is exceeded is determined by scenarios of the tender price against the base price, and under the purchase-price route the contractor must submit quantity and unit price to the employer for checking before purchase (no reply in time is deemed approval). The standard itself has no dedicated 'applicable conditions' clause, only 'one of the methods of Appendix A'; the choice is first a matter for the contract; where one contract assigns different methods to different adjustable factors, they must be entered separately in Table G.2.1-1 (published price information method) / Table G.2.1-2 (index method), without double counting the same differential.
- ←
The index-based adjustment method (GB/T 50500-2024 Appendix A.1): the adjustment formula, fixing the fixed weight A and variable weights Bi, and the sources and timing of price indices (factors)
The index method computes dP = P0 x [A + sum Bi x (Fti/F0i) - 1]: P0 the net-of-VAT contract price of the measurement period; A the fixed weight and Bi the weights of adjustable factors on the net-of-VAT contract price, with A + sum Bi = 1; weights and base indices are ranged by the employer and fixed in the tenderer's price-index and weight schedule of the tender-letter appendix, absent which the tender price ceiling's weights may be used (A.1.4); base indices at the contract base date (28 days before the tender deadline for tendered works), current indices per period, the previous period's usable provisionally (A.1.2/A.1.5/A.1.6); the index source is contractual (2024 no longer mandates authority indices first); adjustments carry VAT only, never overheads or profit.
- ←
Settlement pricing when the confirmed price of a provisionally priced material differs from published price information: the procedurally formed confirmed price (net award price, or employer-confirmed enquiry price) replaces the provisional sum, published prices serving only as the contractually agreed base or a provisional fallback in disputes
Settlement follows the confirmed price formed under the contractual procedure - for mandatory-tender items, the net-of-VAT material award price replaces the provisional price; otherwise the employer-confirmed (or jointly enquired) net price does (GB/T 50500-2024 clauses 8.4.1, 8.4.5); published price information neither replaces the confirmed price nor caps or floors it - it applies only where the contract makes it the base, or where a period market price is missing or the dispute is large, provisionally, 'to be trued up in later payments against actual market prices' (Appendix A clause A.2.2). The difference adjusts only the material provisional price (net) within the all-in unit rate, other cost heads unchanged, carrying VAT but never overheads or profit (clauses 8.4.6, 3.3.5 item 4).
- ←
GB/T 50500-2024 clause set 8.8: adjustments of contract price and duration for changes in laws, regulations and policies - scope, the one-way adjustment rule during extended durations, and no adjustment of overheads and profit
GB/T 50500-2024 clause 8.8: for laws, regulations, policy provisions or government interpretations newly enacted, amended or repealed after the contract base date, price and/or duration adjust per the contract and the rules published by the authorities; policy changes during contractor-caused extension adjust downward only (8.8.2), during employer-caused extension upward only (8.8.3); where policy change causes material extension and subsequent abnormal market price moves, the price-fluctuation rules apply (8.8.1/8.8.2/8.8.3); overheads and profit inside the total and unit prices never adjust for policy changes (8.8.5).
- ←
The non-adjustment boundary of material price adjustment: the eight cost classes never adjusted for price moves, the BOQ items outside routine adjustment, and the negotiated handling of abnormal fluctuation (GB/T 50500-2024 clauses 8.7.3 / 8.7.5 / 8.7.6)
GB/T 50500-2024 clause 8.7.6 lists eight classes never adjusted for price moves: construction consumables, small tools, preliminaries, other plant costs, materials outside the agreed adjustable items, price moves beyond the agreed scope and band, overheads and profit, and contractor-cause costs; clause 8.7.5 keeps the adjustment away from employer-supplied material items and provisionally priced material items; clauses 8.7.3 and 3.3.6 are the negotiated channels for abnormal fluctuation or missing agreement. Differences carry VAT only, never overheads or profit.
- ←
Charging boundary of material price differentials (construction-period adjustment): VAT only - no overheads or profit, and no participation in the charging bases of total-price preliminaries or statutory levies (GB/T 50500-2024 Article 3.3.5 paragraph 4, Article 8.7.6)
Differentials formed by construction-period material price settlement adjustments carry VAT only - no overheads or profit, and they do not join the charging bases of total-price preliminaries or statutory levies. Basis: GB/T 50500-2024 Article 3.3.5 paragraph 4 - differentials of labour, materials and the fuel-power element of plant within all-in unit rates carry VAT but not overheads or profit; Article 8.7.6 items 3 (preliminaries) and 7 (overheads and profit) are listed among fees not adjusted for cost fluctuation; and since total-price preliminaries charge on labour plus plant, and statutory levies on quota labour, material differentials - being material in nature - fall outside both bases anyway. Express contract terms prevail.
- ←
The mechanism for determining the scope of price-adjustable materials and typical categories (GB/T 50500-2024 appendix G.2)
GB/T 50500-2024 sets no statutory "list of price-adjustable materials": the employer and contractor define the scope of adjustable main materials and lock it in as a contract annex by completing table G.2.1-1 (price-information adjustment method) or G.2.1-2 (price-index adjustment method) of appendix G.2; the statutory adjustable factors are only three classes — labor cost, main material cost, and fuel/power cost of construction plant; price differences carry VAT only, with no management fee or profit.
- ←
Rules for determining the material adjustment base price (C0): base date, one-of-three sources and the adjustment computation base (GB/T 50500-2024)
The base price C0 = the market price level 28 days before the bid closing date (for non-tendered works, 28 days before contract signing); that instant is the contract base date (term 2.0.21). The source is one of: (1) the market price used in the maximum bid price; (2) the current quarter's (month's) guidance price of the cost management agency; (3) the winning-bid price of analogous works under the same conditions published by the local trading center — all must represent the base-date price level, and the tender documents must state the source, publishing agency and specific quarter (month). Where the guidance price is the base, whether the bid is below/above/equal to the base decides the computation base of the excess portion (appendix A.2.4, preventing high/low-bid arbitrage); the price-index method corresponds to the basic price index F0.
- ←
Composition of multi-month construction material published price information (government guidance prices): three methods for determining multiple market prices within a measurement period (GB/T 50500-2024 Appendix A.2.3 — arithmetic mean / quantity-weighted / price for the main consumption period)
Multi-month construction does not automatically mean weighting: when measuring monthly (or per agreed measurement period), each period takes its own market price Ci, differences computed and accumulated period by period — no prior weighting needed; only when one measurement period spans multiple price issues (e.g., quarterly measurement, monthly published price information (government guidance prices)) is Ci composed per A.2.3's three methods: (1) arithmetic mean, (2) weighted average with completed quantities, (3) price during the main-consumption construction period — method and priority order must be contractually agreed. Method choice directly flips threshold triggering — the same data can show +8.75% (arithmetic, exceeds the 5% risk band, adjustable) vs +4.13% (weighted, within the risk band, no adjustment); the composed Ci enters dP = sum[(Ci - C0(1 +/- r)) x Q] x (1 + VAT rate), with price differences subject to value added tax (VAT) only, not management fee or profit (3.3.5).
- ←
Adjustment of the contract price (GB/T 50500-2024 Chapter 8): eleven triggering events, mechanism by section, and FIDIC mapping
Adjustment of the contract price is the mechanism for changing the contract price during performance. GB/T 50500-2024 Cl. 8.1.1 lists eleven triggering events: BOQ errors, provisional sums, PC sums (provisional estimates), contractor's services, dayworks, changes in costs, changes in laws and policies, variations, additional works, claims, and other events agreed by the parties; the procedure runs submit, check, re-check, review and confirm (8.1.2). Key mechanics: BOQ errors and variations share one re-rating ladder (identical items at contract rates; analogous items converted; different items negotiated), with a 15% quantity boundary for re-rating (8.2/8.9); provisional sums are controlled by the employer and any unused balance reverts at final account (8.3); PC-sum items are replaced by tender prices — materials pre-VAT, specialist works VAT-inclusive (8.4); dayworks are measured under 7.5 (certified dayworks records) and priced at the BOQ daywork rates (8.6, with deemed approval if verification is overdue, 7.5.5); changes in costs are adjusted beyond the agreed band — 5% by default — by index-based (formula) adjustment or adjustment based on published price information (8.7 + Annex A), the differential carrying VAT only; changes in laws pivot on the base date, adjusting price and/or time for enactments, amendments, repeals or new interpretations after it, with no upward adjustment during contractor-caused delay (8.8); additional works may follow contract rates or freshly negotiated rules under a supplementary agreement (8.10); claims cover events outside 8.2-8.10 — compensatory, not punitive, and mutual, with profit added for eight categories of employer-risk events (8.11). FIDIC counterparts sit scattered across Clause 13 (variation valuation 13.3, provisional sums 13.4, changes in laws 13.6, changes in cost 13.7 — 2017 numbering) and Clause 20 claims (28-day hard time bar): adjacent institutions, not chapter-for-chapter equivalents.
- ←
Appendix A price adjustment (for fluctuation) methods for changes in costs, GB 50500-2013 vs GB/T 50500-2024: weighting coefficient basis and adjustment threshold differences
The two editions share the same formula skeleton in Appendix A (index-based (formula) adjustment dP = P0[A + sum BiFit/Fi0 - 1]; adjustment based on published price information adjusts the portion beyond the risk band (no-adjustment tolerance, e.g. ±5%) at actual values); differences lie in the basis and mechanisms: (1) weighting — 2013 variable weights are 'proportions of the total tender price in the tender letter' (including VAT), 2024 uses 'weights of the contract price excluding VAT' (separation of net price and VAT), and 2024 adds A.1.4 fallback 'where variable weights are not agreed, the corresponding weights of the tender price ceiling may be used' and A.1.1 merges the fluctuation range into the base price index F0; (2) thresholds — both editions' fallback is 5% (beyond which actual-value adjustment applies; 2013 clause 9.8.2, 2024 clause 8.7.2), and 2024 adds the sign rule for the r risk band coefficient, defines the base price (reference price for adjustment) as the market price 28 days before the tender deadline (= FIDIC Base Date) (28 days before contract signing for non-tendered works), and the 8.7.6 list of items not subject to price adjustment. GB 50500-2013 was mandatory (replaced); 2024 is recommended national standard GB/T.
- ←
Price-difference calculation method after material prices exceed the risk band (price-information adjustment method, GB/T 50500-2024 Appendix A.2)
The excess beyond the risk band is adjusted per actuals: when prices rise, unit price difference = Ci - C0 x (1 + r); when prices fall, = C0 x (1 - r) - Ci; adjustment amount = unit price difference x adjusted quantity Q; where the contract does not agree a risk band, fluctuation beyond 5% triggers adjustment (Clause 8.7.2); where the bid price differs from the base price, the cross-basis rule of A.2.4 applies to prevent arbitrage; the price difference carries VAT only, with no management fee or profit.
- ←
Which period's published price applies to settlement material prices: the two-date system — base price locked at the contract base date (28 days before bid closing) plus period-by-period pricing per measurement cycle (GB/T 50500-2024 Annex A.2 price-information method)
Settlement material prices are not taken from a single period (completion date or submission date) but from the "base price locked at the contract base date + current prices per measurement cycle" two-date system: base C0 at 28 days before bid closing (non-tendered: 28 days before contract signing); current Ci per measurement cycle from the cost authority's published price information (or jointly confirmed market prices, or same-period trading-center award prices); differences beyond the contractual risk band are computed per cycle and totalled into the final account; with no band agreed, a 5% fluctuation triggers adjustment; express contracts govern.
- ←
Cement price adjustment calculation: determining the adjustment object by usage path (site-mixed / ready-mixed concrete / direct purchase) + price-information adjustment method formulas and caliber points (GB/T 50500-2024 Appendix A.2)
Cement adjustment first fixes the object by usage path: site-mixed concrete/mortar and direct purchase adjust cement (CNY/t, quantity per mix-ratio cement usage or the employer-confirmed purchase quantity), ready-mixed concrete adjusts concrete (CNY/m3) with cement not separately adjusted (the published price information already includes raw-material costs, preventing double-counting). Formulas (Appendix A.2): rising overrun unit price difference = Ci − C0×(1+r), falling = C0×(1−r) − Ci, amount = unit price difference × Q; absent an agreed risk band, fluctuation beyond 5% triggers (8.7.2); the price difference carries VAT only, without management fee or profit (3.3.5); bagged/bulk calibers consistent, listed by type and strength grade, rising and falling adjusted symmetrically in both directions.
- ←
GB/T 50500-2024 rules for determining the base date: agreement first; tendered works = 28 days before the tender deadline, non-tendered works = 28 days before contract signing (term 2.0.21)
The base date (GB/T 50500-2024 term 2.0.21) is the date on which the contractor, during the tender period, determined the tender total price, the BOQ all-in unit rates and their sums, and it serves as the price datum for adjustment for changes in costs and for adjustment arising from changes in laws, regulations and policies. Determination order: agreement first, statutory fallback — where the tender documents (inquiry documents for non-tendered works) and the contract are silent, tendered works take 28 days before the tender deadline (= FIDIC Base Date) and non-tendered works 28 days before contract signing. That point is at once the base period of index-based (formula) adjustment (A.1.6), the base price C₀ of adjustment based on published price information (A.2.1), and the common starting point for adjustment for changes in laws, regulations and policies (8.8.1).
- ←
Rules for determining the quantity (Q) of materials subject to price adjustment: contractual agreement takes precedence, and key points on matching the quantity basis and the period (GB/T 50500-2024)
There is no unified statutory formula for the adjustable-factor quantity Q; it is determined by the calculation method agreed by the employer and contractor in the contract (Appendix A.2.1 + Note 2 of Table G.2.1-1), and must be detailed and clarified in the tender documents / contract special clauses. In practice, the most common basis is "quantities measured for the current period x material consumption under quota norms (prescribed resource consumption standards)/mix ratio (including wastage)", or the purchase quantities confirmed by the employer (A.2.5). Q must correspond to the basis of the price adjustment period and to the price Ci for the measurement period; where the contract is silent, the standard provides no fallback determination and disputes easily arise.
- ←
GB/T 50500-2024, China's BOQ pricing standard: positioning, 2024-vs-2013 changes, chapter map and card-group navigation
GB/T 50500-2024, the China national pricing standard for BOQ-based pricing (MOHURD Announcement No. 212 of 2024, approved 26 November 2024), came into force on 1 September 2025 and repealed GB 50500-2013. Its status shifted from a partly mandatory code to a recommended national standard (GB to GB/T), aiming to regularise pricing rules and let the market form construction costs. It governs pricing activity in tendering, contracting and execution for construction works; EPC and other general-contracting models apply it by reference, and the requirement that state-funded projects use BOQ pricing is carried by a MOHURD ministerial order. Nine headline revisions (per the foreword): risk scope and allocation rules by contract form; a new bid clarification mechanism; revised pricing of preliminaries; the 'contract price agreement' chapter replaced by contract selection and requirements; revised measurement and adjustment rules; site visas abolished and additional-works pricing introduced; interim settlement by construction stage added; dispute resolution revised; the cost-expert-assessment chapter deleted. The structure was rebuilt from 16 chapters into 12 chapters plus annexes: 'tender control price' renamed tender price ceiling; completion settlement and contract-termination settlement merged into 'works settlement and payment' (absorbing stage settlement); dispute resolution and expert assessment merged; pricing tables moved to annexes (with a new Annex G, schedule of price-adjustable key materials).