Overview of material price adjustment in construction works: applicable conditions, base price (reference price for adjustment), risk band, and calculation methods (GB/T 50500-2024 Sections 3.3/8.7 and Appendices A, G)

Four indispensable elements of material price adjustment: ① adjustable scope (only labour cost, principal material cost, and construction machinery fuel and power cost, listed per Appendix G.2 Tables G.2.1-1/2 as a contract annex); ② base price (reference price for adjustment) C₀ (the market price level 28 days before the tender deadline (= FIDIC Base Date), or for non-tendered works 28 days before contract signing); ③ risk band r (contractual agreement takes precedence, in practice 3%–5%; where absent or unclear, a cost fluctuation beyond 5% triggers); ④ quantities subject to price adjustment Q (per the contract's agreed rules). Trigger |Ci−C₀|/C₀>r; upward unit price for the excess beyond the band = Ci−C₀(1+r), downward = C₀(1−r)−Ci; price difference = Σ unit price for the excess beyond the band × Q, carrying value added tax (VAT) only, with no management fee or profit.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • T/ZBD 100.5-2023 建设工程结算审核作业指引
  • 建设部令第107号 建筑工程施工发包与承包计价管理办法

Topic Positioning

The master card of material price adjustment: per GB/T 50500-2024 Sections 3.3, 8.7 and Appendices A, G, it sorts out the four elements — applicable conditions, base price (reference price for adjustment), risk band, calculation methods — and the accompanying iron rules; details are in the cited sub-cards.

Core Conclusions

All four elements are indispensable: ① scope — only labour cost, principal material cost, and construction machinery fuel and power cost are adjustable; principal materials fill Appendix G.2 Tables G.2.1-1/2 as a contract annex; ② base price (reference price for adjustment) C₀ — the market price level 28 days before the tender deadline (= FIDIC Base Date), or for non-tendered works, 28 days before contract signing; ③ risk band r — contractual agreement takes precedence (in practice 3%–5%); where absent or unclear, a cost fluctuation beyond 5% triggers (8.7.2); ④ quantities subject to price adjustment Q — per the contract's agreed rules. Trigger |Ci−C₀|/C₀>r; upward unit price for the excess beyond the band = Ci−C₀(1+r), downward = C₀(1−r)−Ci; price difference = Σ unit price for the excess beyond the band × Q, carrying value added tax (VAT) only, with no management fee or profit (3.3.5). On schedule delays, prices follow responsibility (employer-caused takes the higher, contractor-caused the lower, 8.7.4); construction consumables, preliminaries, and management fee and profit are not adjusted (8.7.6).

Applicable Boundaries

Statute first, agreed terms prevail: where there is an agreement, follow the contract; the standard applies only as the fallback where there is none; agreements imposing an uncapped risk allocation to one party or 'all risks' are prohibited (3.3.1); lump-sum contracts are in principle not adjusted for cost fluctuation; the base price (reference price for adjustment) and construction-period price must share the same basis and source. This card is the master outline; sub-topics are in the cited cards.

Further Reading

GB/T 50500-2024: Appendix A.2.1 formula, A.2.4 the tender-vs-base price relation, A.2.3 multi-price averaging, A.2.5 the purchase price method, Appendix A.1 the index method, Appendix G.2, Clauses 8.7.1–8.7.6, 3.3.1–3.3.5, terminology 2.0.21; with T/ZBD 100.5-2023 Clause 3.1.7 and Construction Ministry Order No. 107, Article 12.