cost fluctuation
- 01
Rules for handling contract price adjustment for cost fluctuation in final account review and construction cost expert assessment: routing by contract type, price-dating principles for delay periods, the exception for government-priced materials, and the eight categories of costs not adjusted for changes in costs listed in GB/T 50500-2024 clause 8.7.6
Final account review and expert assessment proceed on two levels. (i) Ro…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.3.6条、第8.7.2条、第8.7.3条、第8.7.6条GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.6.2条T/ZBD 100.5-2023 · Work Guideline for Settlement Audit of Construction Works 第3.1.7条2026-10-29 - 02
Preliminaries — the "lump sum, no adjustment" principle and the full landscape of adjustable exceptions (GB/T 50500-2024 cl. 3.3.7, 7.3.1)
Under GB/T 50500-2024, the China national pricing standard for BOQ (Code…
GB/T 50500-2024 第3.3.7条(措施费包干与三类例外)GB/T 50500-2024 第7.3.1条(措施项目计量调整封闭清单)GB/T 50500-2024 第7.4.4、8.9.4、8.9.5、8.9.6、8.9.7条(工程变更引起措施项目计量与计价)2026-10-25 - 03
Fee boundary for material price adjustment: the price difference carries VAT only, with no management fee or profit; the eight cost categories under Clause 8.7.6 are not adjusted (GB/T 50500-2024)
Per GB/T 50500-2024 Clause 3.3.5 item 4, price differences of labor, mat…
GB/T 50500-2024 第3.3.5条(物价变化合同价格调整)GB/T 50500-2024 第8.7.6条(不应因物价变化调整的费用)GB/T 50500-2024 第7.3.1条(措施项目不予计量调整)2026-10-25 - 04
GB/T 50500-2024 clause set 8.8: adjustments of contract price and duration for changes in laws, regulations and policies - scope, the one-way adjustment rule during extended durations, and no adjustment of overheads and profit
GB/T 50500-2024 clause 8.8: for laws, regulations, policy provisions or…
GB/T 50500-2024 建设工程工程量清单计价标准 第8.8.1条GB/T 50500-2024 第8.8.2条GB/T 50500-2024 第8.8.3条2026-10-18 - 05
Can published price information directly serve as the basis for material price adjustment: legality + three preconditions (listing / beyond band / tax) (GB/T 50500-2024)
Published price information (government guidance prices) is a price sour…
GB/T 50500-2024 建设工程工程量清单计价标准2026-09-25 - 06
Composition of multi-month construction material published price information (government guidance prices): three methods for determining multiple market prices within a measurement period (GB/T 50500-2024 Appendix A.2.3 — arithmetic mean / quantity-weighted / price for the main consumption period)
Multi-month construction does not automatically mean weighting: when mea…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works App. A.2.1、A.2.3、A.2.5、A.1.5GB/T 50500-2024 第3.3.5条、8.7.1~8.7.6条GB/T 50500-2024 App. GTable G.2.1-12026-09-25 - 07
Price adjustment (for fluctuation) calculation for ready-mixed (commercial) concrete: whole-factor adjustment per m³, adjustment to actual beyond the risk band, and tax treatment (GB/T 50500-2024 Appendix A.2 adjustment based on published price information)
Ready-mixed concrete is adjusted as one whole adjustable factor per m³ (…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works App. A.2(价格信息调差法)GB/T 50500-2024 第3.3.5条GB/T 50500-2024 第8.7.2条2026-09-25 - 08
Adjustment of the contract price (GB/T 50500-2024 Chapter 8): eleven triggering events, mechanism by section, and FIDIC mapping
Adjustment of the contract price is the mechanism for changing the contr…
GB/T 50500-2024 建设工程工程量清单计价标准(第8.1.1/8.1.2条、第8.2~8.11节、第7.5节、App. A、App. G)FIDIC Red/Yellow Book 2017(第13.3、13.4、13.6、13.7、20.2.1 条〔对照〕)GB/T 50875-2013 工程造价术语标准2026-09-25 - 09
Overview of material price adjustment in construction works: applicable conditions, base price (reference price for adjustment), risk band, and calculation methods (GB/T 50500-2024 Sections 3.3/8.7 and Appendices A, G)
Four indispensable elements of material price adjustment: ① adjustable s…
GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.5-2023 建设工程结算审核作业指引建设部令第107号 建筑工程施工发包与承包计价管理办法2026-09-25 - 10
Handling rules when the price-information issue and the construction month are misaligned (GB/T 50500-2024 Appendix A adjustment)
Price-information adjustment takes the issue corresponding to the measur…
GB/T 50500-2024 App. A.2.1~A.2.5GB/T 50875-2013 第2.1.16条T/ZBD 100.1-2022 第7.2.3条2026-09-25 - 11
Mechanism for material price changes under fixed unit-price contracts: unit price locked + quantities at actuals + beyond-band adjustment (GB/T 50500-2024)
Under unit-price contracts the all-in unit rate is fixed within the cont…
GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.5-2023 建设工程结算审核作业指引T/ZBD 100.4-2023 建设工程造价鉴定作业指引2026-09-25 - 12
Price-taking rules when one material has multiple published prices / original prices: weighted average by supply quantity at compilation, three agreed methods at adjustment, unified caliber
When one material has multiple prices, take prices by scenario: at compi…
TB 10811-2024 铁路基本建设工程设计概(预)算费用定额GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.1-2022 建设工程造价数据建设通用标准2026-09-25 - 13
Material price adjustment channels under fixed lump-sum contracts: no adjustment within the agreed risk band, adjustment beyond the risk band, mandatory adjustment for statutory causes
Under a fixed lump-sum contract, cost fluctuations within the agreed ris…
GB/T 50500-2024 第3.3.1~3.3.3、3.3.5、8.7.1~8.7.6条GB/T 50500-2024 App. A、App. G.2建设部令第107号 第12条2026-09-25 - 14
Determining the pricing risk scope within the all-in unit rate: contract agreement first + statutory fallback of GB/T 50500-2024 Sections 3.3/8.7
Risk-scope determination follows 'contract agreement first, statutory fa…
GB/T 50500-2024 建设工程工程量清单计价标准 第3.3.1~3.3.6条GB/T 50500-2024 第8.7节GB/T 50500-2024 App. A2026-09-25