Fee boundary for material price adjustment: the price difference carries VAT only, with no management fee or profit; the eight cost categories under Clause 8.7.6 are not adjusted (GB/T 50500-2024)
Per GB/T 50500-2024 Clause 3.3.5 item 4, price differences of labor, materials, and machinery fuel/power carry VAT only — no management fee or profit; Clause 8.7.6 lists eight categories not adjusted for price changes (construction consumables, small tool usage, preliminaries, other machinery usage beyond fuel/power, materials outside agreed adjustable items, changes beyond the agreed scope and band, management fee and profit, contractor's own-cause costs); Clause 8.7.3 opens a negotiation exception for abnormal, unforeseeable fluctuations.
Applicable Codes
- GB/T 50500-2024 第3.3.5条(物价变化合同价格调整)
- GB/T 50500-2024 第8.7.6条(不应因物价变化调整的费用)
- GB/T 50500-2024 第7.3.1条(措施项目不予计量调整)
- GB/T 50500-2024 第3.2.11条(增值税计税基础)
- GB/T 50500-2024 App. A.1.1(价格指数调差法)
- GB/T 50500-2024 App. A.2.1(价格信息调差法)
- GB/T 50500-2024 App. G.2 Table G.2.1-1/Table G.2.1-2
- 陕西省建设工程费用规则(2025版)5.1 计费基础及计价程序
- 江苏省建设工程费用参考(2026)二、管理费和利润参考费率
- 京建法〔2021〕11号 企业管理费与利润计取规则
- JTG 3830-2018 公路工程建设项目概算预算编制办法
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 4.1
- T/ZBD 100.5-2023 建设工程结算审核作业指引 第3.1.7条
- https://jst.zj.gov.cn/col/col1229129246/art/2020/art_84c0da88c3e9d02be3b1964f9791d9ad.html
- http://xxgk.jl.gov.cn/szf/gkml/202205/t20220531_8462652.html
- https://zjt.jiangxi.gov.cn/jxszfhcxjst/wjtz/pc/content/content_1765332785668222976.html
Topic Positioning
This card answers "do material adjustment amounts carry management fee, profit, and tax": which costs to charge and which expressly not to charge when adjusting for price changes, plus the exception channel for abnormal fluctuations.
Core Conclusions
Adjustment amount = beyond-band price difference x (1 + applicable VAT rate). Per GB/T 50500-2024 Clause 3.3.5 item 4, adjustments of labor, material, and machinery fuel/power price differences carry VAT and must not carry management fee or profit (those risks are priced in by the bidder as risk cost in its bid). Clause 8.7.6 lists eight categories not adjusted for price changes: construction consumables; small and medium tool usage costs; preliminaries; other machinery usage costs beyond fuel/power; material costs outside the contract-agreed adjustable items; price changes beyond the agreed adjustable scope and band; management fee and profit; costs arising from the contractor's own causes. Clause 8.7.3 sets the exception: for abnormal, unforeseeable fluctuations at contracting that make continued performance obviously unfair, negotiate adjustment under fair risk sharing.
Applicable Boundaries
Applies where the contract agrees adjustment or Clause 8.7.2's 5% fallback applies; only the beyond-band portion is charged, within-band portions unadjusted. Fuel/power adjustment presupposes that the contract allows adjustment of large construction machinery. Differences are computed on tax-exclusive prices (8.7.1) and taxed at the material's applicable rate; measure costs, consumables, small tools, management fee, and profit do not float with prices.
Further Reading
See GB/T 50500-2024 Clauses 3.3.5, 8.7.1, 8.7.2, 8.7.3, 8.7.6 and Appendix A.2 (price-information adjustment formulas); settlement-audit caliber per T/ZBD 100.5-2023 Clause 3.1.7 (adjust only the price-change costs and corresponding taxes).