GB/T 50500-2024 rules for adjusting price differences, management fee, and tax after the actual price of provisionally priced materials/equipment is determined (Section 8.4)
Per GB/T 50500-2024 Section 8.4, once the actual price of provisionally priced materials (including engineering equipment) is determined, only the material provisional-price item in the all-in unit rate is adjusted (pre-tax difference = confirmed actual pre-tax unit price − provisional pre-tax unit price, times quantity); labor, machinery, management fee, profit and other costs are not adjusted; VAT is charged additionally on the difference and the contract price is adjusted. Replacement price: for items subject to mandatory tendering by law, the pre-tax winning purchase price replaces it; otherwise, the pre-tax inquiry/own-quote price confirmed by the employer. Specialist-work provisional prices are VAT-inclusive, replaced wholesale by the winning VAT-inclusive subcontract price — a different rule.
Applicable Codes
- GB/T 50500-2024 第 8.4.1、8.4.5、8.4.6 条
- GB/T 50500-2024 第 2.0.14、3.2.11、8.1.8 条
Topic Positioning
GB/T 50500-2024, Standard for Valuation of Construction Works with Bills of Quantities, Section 8.4: after the actual price of materials/equipment given provisional prices in the BOQ is determined, how the price difference, management fee, and tax of the contract amount are adjusted.
Core Conclusions
The core principle is "adjust only the material price itself": only the material provisional-price item (pre-tax price) in the all-in unit rate is adjusted; labor, machinery, management fee, profit and other costs are not adjusted at all; the adjusted contract unit price may be used for pricing BOQ deficiencies, provisional sums, and works variations. Difference = (confirmed actual pre-tax unit price − provisional pre-tax unit price) × quantity; VAT is charged additionally on the difference (difference × the applicable rate set by the competent government authority) and merged into the contract price adjustment. The replacement price basis depends on whether tendering is mandatory by law: where mandatory, the pre-tax winning purchase price of the material replaces the provisional pre-tax price; where not, the contractor's market inquiry/own quote or a joint inquiry by both parties, replaced by the employer-confirmed pre-tax price. Note the basis: provisional prices of materials (including engineering equipment) are pre-tax prices excluding VAT, whereas specialist-work provisional prices are VAT-inclusive, replaced wholesale by the winning VAT-inclusive subcontract price — this rule does not apply.
Applicable Boundaries
Applies to contract price adjustment after determination of prices of provisionally priced materials (including engineering equipment) in the BOQ; not applicable to specialist-work provisional prices (wholesale VAT-inclusive replacement). Management fee and profit are not re-charged on the difference. Express contract agreements prevail. For simplified-taxation projects, VAT is at the levy rate, with the same formula structure. The VAT calculation base deducts the specialist-work provisional amounts in the other items list.
Further Reading
See GB/T 50500-2024: Clause 2.0.14 (material provisional price terminology, including engineering equipment, as the VAT-exclusive price delivered to site), Clause 3.2.11 (VAT calculation base and deduction of specialist-work provisional amounts), Clause 8.1.8 (after agreement on the adjustment item, calculate the VAT adjustment per Section 3.2), Clause 8.4.1 (replacement rules for mandatory tendering and the basis difference between material and specialist-work provisional prices), Clause 8.4.5 (non-mandatory inquiry replacement and VAT recalculation), Clause 8.4.6 (adjust only the material provisional price, other costs unchanged, and the uses of the adjusted unit price).
Keywords
Cited By
- ←
Who bears the costs of organising tendering and of cooperation for provisionally priced materials and provisionally priced specialist works, in three scenarios (employer as tenderer / contractor as tenderer / joint tendering) (GB/T 50500-2024, 8.4.2-8.4.4 + GF-2020-0216, 13.4.1)
Under GB/T 50500-2024, 8.4.2-8.4.4: where the employer acts as tenderer, the employer bears the costs of organising the tendering work, and where the contractor's cooperation is needed the contractor bears its own cooperation costs; where the contractor acts as tenderer, the contractor bears the costs of organising the tendering work and these costs 'shall be deemed already included in the contractor's tender total price (the contract price at signing)', and where the employer's cooperation is needed the employer bears its own; where both parties act jointly as tenderers, each bears its corresponding costs (the split as agreed in the particular conditions). Common principle: organising and cooperation costs are borne by each party itself, the contractor's share is deemed included in its tender price and cannot be charged separately. GF-2020-0216, 13.4.1 matches this (the costs of contractor-organised tendering deemed included in the contract price at signing); for provisional-price items not subject to mandatory tendering, replacement prices are determined by enquiry or joint tendering under 8.4.7.
- ←
The validity of a construction (sub)contract for a specialist work carried at a provisional price within the general contracting scope where the law required tendering but none was conducted: the elements of invalidity, the scope of invalidity, the exception outlet, and the consequences of price-based compensation
Where a specialist work is included within the general contracting scope at a provisional price, falls within the scope of projects subject to compulsory tendering by law, and meets the size threshold (estimated price of a single construction contract above CNY 4 million, or procurable purchases in the same project that can be combined reaching the threshold in total), concluding a construction (sub)contract without tendering falls under 'compulsory tendering required but not conducted' in Article 1, paragraph 1, item (3) of Interpretation (I) (Fa Shi [2020] No. 25), and the contract is void under Civil Code Article 153, paragraph 1; the invalidity in principle reaches only that provisional-price part and not the whole general contract lawfully concluded through tendering. Interpretation (II) (Fa Shi [2026] No. 12), Article 1, creates an exception: where the project was subject to compulsory tendering at contract conclusion but no longer is at the time of suit, the court should not find the contract void merely for want of tendering. If, after invalidity, the works pass acceptance, the contractor is compensated by reference to the price provisions agreed in the contract (Civil Code Article 793, paragraph 1); 'by reference' includes the amount, the pricing method, the payment time, the adjustment method, and the settlement method (Fa Shi [2026] No. 12, Article 11).
- ←
Dividing price and quantity gaps of employer-supplied (free-issue) materials: price gaps to the employer and outside the contractor's adjustment scope, quantity gaps bounded by the effective wastage rate, custody and freight splitting at the delivery point with unloading (GB/T 50500-2024 clauses 3.6.1, 3.2.4, 3.6.3, 6.2.4, 8.7.5; against GB 50500-2013 clause 3.2.1)
Price gaps are the employer's and never enter the contractor's adjustment: 3.6.1 - 'at bidding, the prices of employer-supplied materials do not enter the all-in unit rates'; 3.2.4 - 'the material cost of employer-supplied materials does not enter the work-item list'; 8.7.5 - 'the material adjustments of 8.7.2~8.7.4 are not suited to employer-supplied items... adjustable by the employer on actual changes but not listed in the contract total' - the gap between actual purchase and contracted prices is the employer's own, forming no contractor adjustment income and no downward contract revision. Quantity gaps split at the effective wastage rate: contractor-caused over-draws are borne by the contractor per 3.6.3, clawed back at supply-contract prices from interim or final payments; within the rate, and employer-caused excesses (specification mismatch pushing wastage beyond the rate; employer-caused over-draws), fall on the employer. Custody and freight split at 'delivered to the delivery point and unloaded': before, the employer's (6.2.4 - bid rates exclude those costs); after, site custody, double handling and own installation wastage are the contractor's, coordination and custody services charged to the employer in attendance provisions (3.6.4).
- ←
Reading published price information as tax-inclusive or net, and the de-taxing conversion: de-tax by element (goods 13%, transport 9%, levy rate 3%), then custody, then into the all-in unit rate - with the order-bias test and double-tax prevention
Published prices are often tax-inclusive or freight-inclusive: read the release notes first. Tax-inclusive prices de-tax by each element's own rate (goods 13%, transport services 9%, simplified levy 3%) before purchasing and custody; a tax-inclusive delivered price divided once by 1.13 never adds freight or custody again. 'Add freight then divide the whole by 13%' differs algebraically from 'divide first, add later' only in form - both de-tax freight at 13%; the bias test is delta = F x (1/1.09 - 1/1.13) x (1+k). Net prices enter the all-in unit rate with VAT listed separately - one VAT only, throughout (GB/T 50500-2024 clauses 2.0.9, 3.1.6, 3.2.11).
- ←
Fee boundary for material price adjustment: the price difference carries VAT only, with no management fee or profit; the eight cost categories under Clause 8.7.6 are not adjusted (GB/T 50500-2024)
Per GB/T 50500-2024 Clause 3.3.5 item 4, price differences of labor, materials, and machinery fuel/power carry VAT only — no management fee or profit; Clause 8.7.6 lists eight categories not adjusted for price changes (construction consumables, small tool usage, preliminaries, other machinery usage beyond fuel/power, materials outside agreed adjustable items, changes beyond the agreed scope and band, management fee and profit, contractor's own-cause costs); Clause 8.7.3 opens a negotiation exception for abnormal, unforeseeable fluctuations.
- ←
Treatment of the four items of the bill of provisional sums and other charges under GB/T 50500-2024 in performance and at the final account: unused provisional sums revert to the employer, provisional prices replaced and adjusted, dayworks measured as incurred, main contractor's attendance and coordination provisions lump-sum or re-rated, plus the final account item sequence (sections 8.3-8.6, clauses 10.3.2 / 10.3.3)
Under GB/T 50500-2024: provisional sums (8.3.1, 8.3.5) are controlled by the employer and used per instruction; they accrue to the contractor only when actually incurred, and where no adjustment event occurs the whole amount is deducted at the final account with the balance reverting to the employer. Provisional prices (8.4) are replaced by the tender winning price or a price confirmed by the employer; for materials only the pre-tax material provisional price inside the all-in unit rate is adjusted and other costs stand, while nominated specialist works are replaced wholesale at tax-inclusive prices. Dayworks (8.6) are measured as incurred under section 7.5 and priced at the contract dayworks rates; the final account includes the amounts actually incurred and deducts the dayworks amounts of the original BOQ, with no separate preliminaries. Main contractor's attendance and coordination provisions (8.5): when priced per item they are at lump-sum risk and not adjusted at the final account; when priced by percentage rate they may adjust under clauses 8.5.1-8.5.5 for changes in the scope of materials or subcontract works, variations, or employer-caused time changes; contractor-caused delay is not adjusted and attracts delay damages. The final account lists items in the 13-item sequence of clause 10.3.2, and attendance provisions and preliminaries must be re-calculated per clause 10.3.3.
- ←
GB 50500-2013 Chapter 9 'Adjustment of the Contract Price' at a glance: the 15 adjustable events, their five-category grouping and clause order, the trigger conditions and direction of price adjustment for each event, submission time limits and confirmation (deemed approval) procedures, the order of application when several events coincide, and a clause mapping to GB/T 50500-2024
Clause 9.1.1 of GB 50500-2013 lists 15 adjustable events, and the official commentary groups them into five categories: changes in laws and regulations (9.2); variations (9.3 variation, 9.4 item description mismatch, 9.5 omitted BOQ items, 9.6 quantity deviation, 9.7 dayworks); changes in costs (9.8 changes in costs, 9.9 provisional prices); claims (9.10 force majeure, 9.11 earlier completion, 9.12 delay damages, 9.13 claims); and others (9.14 site instruction records plus other adjustment events agreed by both parties). Clause numbers are easily shifted: changes in costs is 9.8 (not 9.7, which is dayworks); force majeure 9.10; earlier completion 9.11; delay damages 9.12; claims 9.13; site instruction records 9.14. Direction of adjustment: under 9.6.2, where a quantity deviation exceeds 15%, the all-in unit rate of the increased portion beyond 15% is reduced, and where the quantity decreases by more than 15% the all-in unit rate of the remaining portion is increased (reverse correction); 9.3.1 sets a four-tier pricing ladder for variations (an applicable item takes the original rate; a similar item is referenced within a reasonable range; where neither applies, the contractor proposes a rate from published price information x its quoted floating rate for the employer's confirmation; where the published price information carries no price, a lawful market price from market survey is proposed for confirmation); under 9.8.2, where no band is agreed and a unit rate changes by more than 5%, the portion beyond 5% is adjusted. Where events coincide: if a variation also causes a quantity deviation above 15%, that item's rate is adjusted under 9.6.2 (clause 9.3.1 paragraph 1), preliminaries move in linkage under 9.6.3/9.3.2, and cost fluctuation is separately adjusted under Annex A for the price differential only, without double counting.
- ←
Contract price adjustment calculation for VAT rate changes (GB/T 50500-2024 clauses 8.8.6 and 3.2.11) and the negative finding that a mere re-versioning of local charge standards / percentage-rate documents is not a 'change of laws and regulations' (T/ZBD 100.4-2023 clauses 4.4.1, 4.4.8, 3.1.4)
A VAT rate change adjusts the difference only, under clause 8.8.6 of GB/T 50500-2024: works priced and paid after the new rate takes effect are charged VAT at the adjusted rate, and the difference from the VAT computed at the original rate of the contract base date adjusts the contract price; amounts paid before implementation are not retraced. Per clause 3.2.11 the taxable base is the total of the bills of work items, preliminaries and other charges (less provisional sums for nominated specialist works), so delta VAT = B x (r1 - r0), and expressed on the original tax-inclusive price P1 = P0 x (1 + r1) / (1 + r0). Local consumption quota manuals, on-cost norms and charge standards / percentage-rate documents are not themselves laws or regulations; they are the 'provisions issued accordingly' (the calculation basis) in clause 8.8.1, so a mere re-versioning does not constitute an adjustable 'change of laws and regulations' (T/ZBD 100.4-2023 clause 4.4.8: no adjustment for version updates of valuation rules). However, changes after the tender submission deadline in government-fixed and government-guided prices, policy rates, or mandatory national standards fall under the clause 4.4.1 exception: works prices after the change takes effect are adjusted, unless the contract expressly allocates the price risk of such elements.
- ←
Cost items expressly excluded from the all-in unit rate in BOQ-based pricing (VAT, statutory levies and fees, main contractor's attendance and coordination provisions, provisional sums, employer-borne costs, statutory safety provisions), the correct billing position of each, and audit identification of mixed allocation
Under GB/T 50500-2024 Clause 2.0.9 the all-in unit rate 'includes labour cost, material cost, plant and small tools cost, management cost, profit and risk costs within a defined range, and excludes VAT', and Clause 3.1.6 makes it a 'fully inclusive price excluding VAT'. Hence VAT (charged at the summary level under Clause 3.2.11), main contractor's attendance and coordination provisions (Clauses 2.0.17, 3.2.9 and 4.2.6, listed separately in the bill of provisional sums and other charges by item or by percentage rate), provisional sums (Clauses 2.0.13 and 8.3.1, at the employer's disposal and not owned by the contractor), the price of employer-supplied materials with their delivery and unloading charges and the material cost of the employer-borne permitted wastage (Clauses 3.2.4 and 6.2.4), and statutory safety provisions (Clause 3.2.5, non-competitive and separately listed in the bill of preliminaries) must not enter the all-in unit rate of work items; the 2024 edition cost composition no longer has a 'statutory levies and fees' heading (the five insurances and one housing fund for production workers now go into labour cost, and those for management staff plus the construction effluent fee go into overheads), so adding a separate statutory levies heading and charging it again is an error.
- ←
Labour cost pricing basis within the all-in unit rate: norm-based labour cost (base-period workday rate) versus current-period published labour price information and labour market prices, the applicable rules at the tender price ceiling and tender stages, and the test that the labour cost differential and the labour cost inside the all-in unit rate are not adjusted twice
Labour cost in the all-in unit rate = norm (budget) labour consumption x the current-period labour rate (published price information or a market price confirmed by the parties): consumption is locked to the quota manual while the rate is opened to the current-period market (GB/T 51095-2015, clause 5.3.9). The base-period workday rate published with the quota manuals is not itself the pricing input for BOQ rate build-up; it is a component of norm-based labour cost and the comparison base of the labour cost differential. At the tender price ceiling stage the published labour rates / published price information take precedence (GB/T 50500-2024, clauses 5.2.1 and 5.2.8); the tender is priced freely by the tenderer on its in-house norms and the market, but not below cost and not above the tender price ceiling (clauses 6.1.1, 6.1.3, 6.2.1). Differentials caused by changes in costs carry VAT only, not overheads or profit (clause 3.3.5); the same labour differential may be taken once only, in either the current-period-price pricing system or the base-period-price-plus-differential system, and must not be stacked on the labour cost already inside the all-in unit rate.
- ←
Section order of Chapter 9 'adjustment of the contract price' in GB 50500-2013 mapped to the clause numbers of GB/T 50500-2024: dayworks 9.7 -> 8.6, provisional prices 9.9 -> 8.4, claims 9.13 -> 8.11, provisional sums 9.15 -> 8.3
GB 50500-2013 (withdrawn) Chapter 9 runs: 9.2 changes in laws and regulations, 9.3 variations, 9.4 mismatch of item descriptions, 9.5 BOQ omissions, 9.6 quantity deviations, 9.7 dayworks, 9.8 changes in costs, 9.9 provisional prices, 9.10 force majeure, 9.11 earlier completion (acceleration compensation), 9.12 delay damages, 9.13 claims, 9.14 site instruction records, 9.15 provisional sums. GB/T 50500-2024 consolidates these price-adjustment events into Chapter 8: BOQ errors 8.2, provisional sums 8.3, provisional prices 8.4, dayworks 8.6, changes in costs 8.7, variations 8.9, additional works 8.10, claims 8.11; the final account items are listed in Clause 10.3.2 (provisional sums item 3, provisional prices item 4, dayworks item 6, claims item 11). The common miscitations 'provisional prices 9.8, dayworks 9.9, claims 9.14' all fail against the actual section order of both editions.
- ←
Deduction of employer-supplied (free-issue) materials from payments and allocation of costs: deduction mechanism, procurement/custody fee and wastage responsibility (GB/T 50500-2024, T/ZBD 100.4-2023)
Where employer-supplied (free-issue) material prices are not included in the all-in unit rate (stripped pricing), settlement naturally requires no deduction; where the contract stipulates prior inclusion, deduct from the settlement amount at actual consumption (issued quantity − stock) × the supply contract unit price. Procurement and custody costs follow the material and belong to the procuring party (the employer); the cost of the contractor's custody and assistance services is borne by the employer and charged under the main contractor's attendance and coordination provisions; wastage within the valid wastage rate is borne by the employer, over-drawing attributable to the contractor is borne by the contractor, and employer-caused causes (non-conforming specifications, untimely supply) are borne by the employer.
- ←
Provisional prices (materials / specialist works): the settlement adjustment procedure of replacing the provisional price with the actual confirmed price - legal position, the submission-checking-review-re-examination-confirmation chain and deemed approval on expiry, the two confirmation routes (compulsory tendering and otherwise), adjusting only the pre-tax material price, the deduction direction when the confirmed price is lower, the boundary against material price adjustment, and the clause mapping of GB/T 50500-2024 against GB 50500-2013
The final account replaces the provisional price with the 'confirmed price' (the tender-winning pre-tax price, or the tax-inclusive tender-winning specialist subcontract price, for items that must be tendered by law; or the pre-tax price from market enquiry or the contractor's own quotation confirmed by the employer for items outside compulsory tendering); published price information is not a basis for settlement adjustment (it only guides the provisional unit rate when compiling the tender price ceiling, or serves as the adjustment baseline where the contract makes that material price-adjustable); the procedure runs under GB/T 50500-2024 clauses 8.1.2 to 8.1.6 - submission, checking, review, re-examination and confirmation - and failure to confirm or comment within the time limit is deemed approval; the adjustment replaces only the material provisional price inside the all-in unit rate (pre-tax); labour, plant, overheads and profit do not move (clause 8.4.6), VAT being charged on the difference; where the confirmed price is below the provisional price the adjustment runs the same way down, deducted from the current progress payment or interim settlement by construction stage, and the final account lists 'provisional price adjustment amounts' separately; BOQ items carrying material provisional prices are outside the material cost adjustment of clauses 8.7.2 to 8.7.4 (clause 8.7.5). The 2013 counterparts are clauses 9.9.1 to 9.9.4.
- ←
Boundary distinctions among omitted BOQ items (BOQ errors), provisional prices, provisional sums, dayworks and site instruction records in contract price adjustment: required but not listed vs listed but unpriced vs confirmation evidence for unforeseen matters
Under GB/T 50500-2024: omission falls under 'BOQ errors' (clause 2.0.27, differences between the BOQ and the contract drawings in items, item descriptions and quantities), handled by re-determining the all-in unit rate under sections 8.2 and 8.9; a provisional price is an item already listed but with the price provisional - once the price is fixed only the price element is replaced: for items subject to mandatory tendering by law, the pre-tax tendered material price or the VAT-inclusive tendered specialist subcontract price replaces it (8.4.1); for items not subject to mandatory tendering, the pre-tax price confirmed by the employer from enquiry or the contractor's own quote replaces it, with the VAT change computed (8.4.5, 8.4.7); a material provisional price adjusts only the pre-tax material price within the all-in unit rate, leaving all other cost elements untouched. Provisional sums are controlled by the employer and used on instruction (8.3.1); when used for works not fully foreseen or specified, the price is adjusted as contract unit rates x quantities from the confirmed drawings (8.3.2); where no adjustment event has occurred, the whole amount is deducted at final account (8.3.5). Dayworks are a pricing method for work not suitably priced under the contract and the pricing standards (8.6.1); at settlement they are counted as actually incurred, but the daywork items already included in the contract price are deducted (8.6.5). Site instruction records are certification of process facts (GB/T 50875-2013 clause 3.4.8, GB/T 50500-2024 clause 12.2.1) and are not an independent price adjustment matter in themselves. The same matter must not be priced twice - once as a new BOQ item for omission and again under dayworks or provisional sums.
- ←
The VAT charging base of the bill of quantities and the non-duplication of tax on provisional sums for specialist works (GB/T 50500-2024 clauses 3.2.11 and 3.1.6)
VAT = [work-item list + preliminaries list + other-items list (less the provisional sums for specialist works)] total x the VAT rate set by the authorities; the specialist provisional sums are VAT-inclusive, and no further tax may be charged on them (clauses 3.2.11 and 3.1.6). Under general taxation the construction rate is 9% (price and tax separated); under the simplified scheme the levy rate is 3% (factor prices carry input tax, the base being the tax-exclusive works cost that already includes input tax).
- ←
Settlement pricing when the confirmed price of a provisionally priced material differs from published price information: the procedurally formed confirmed price (net award price, or employer-confirmed enquiry price) replaces the provisional sum, published prices serving only as the contractually agreed base or a provisional fallback in disputes
Settlement follows the confirmed price formed under the contractual procedure - for mandatory-tender items, the net-of-VAT material award price replaces the provisional price; otherwise the employer-confirmed (or jointly enquired) net price does (GB/T 50500-2024 clauses 8.4.1, 8.4.5); published price information neither replaces the confirmed price nor caps or floors it - it applies only where the contract makes it the base, or where a period market price is missing or the dispute is large, provisionally, 'to be trued up in later payments against actual market prices' (Appendix A clause A.2.2). The difference adjusts only the material provisional price (net) within the all-in unit rate, other cost heads unchanged, carrying VAT but never overheads or profit (clauses 8.4.6, 3.3.5 item 4).
- ←
Setting overheads and profit in repricing variations and other price adjustments (GB/T 50500-2024 Articles 3.6.6, 8.4.6, 8.8.5, 8.9.1)
On repricing (no identical or similar rates), GB/T 50500-2024 Article 8.9.1 negotiates a market-reasonable all-in unit rate - by reference to the pricing rules and pricing level of analogous contract rates or to analogous items of similar works; the expert-assessment basis is reasonable cost plus the contract overheads and profit rates (T/ZBD 100.4-2023 Article 4.6.2), the supervision basis the cost-plus-profit principle (GB/T 50319-2013 Article 6.3.3). Similar-rate conversion (tier 2) swaps only the differing elements, the original overheads and profit preserved. Where employer-supplied materials become contractor-purchased, add to the original all-in unit rate the material cost (with reasonable wastage) plus overheads and profit, at the rates of the item's rate build-up or the nearest analogous item (Article 3.6.6). Reverse rules: on laws and policy changes, the overheads and profit within the total price and unit rates are not adjusted (8.8.5); provisional-sum materials adjust only the pre-tax provisional material price, nothing else (8.4.6); fluctuation differentials carry VAT only, no overheads or profit (3.3.5).
- ←
Charging boundary of material price differentials (construction-period adjustment): VAT only - no overheads or profit, and no participation in the charging bases of total-price preliminaries or statutory levies (GB/T 50500-2024 Article 3.3.5 paragraph 4, Article 8.7.6)
Differentials formed by construction-period material price settlement adjustments carry VAT only - no overheads or profit, and they do not join the charging bases of total-price preliminaries or statutory levies. Basis: GB/T 50500-2024 Article 3.3.5 paragraph 4 - differentials of labour, materials and the fuel-power element of plant within all-in unit rates carry VAT but not overheads or profit; Article 8.7.6 items 3 (preliminaries) and 7 (overheads and profit) are listed among fees not adjusted for cost fluctuation; and since total-price preliminaries charge on labour plus plant, and statutory levies on quota labour, material differentials - being material in nature - fall outside both bases anyway. Express contract terms prevail.
- ←
Adjustment of contract prices of signed works upon quota revision or updates of measurement and pricing rules: pure version updates are not adjusted; policy-based rates, government pricing and mandatory standard changes are adjusted
Where a party seeks a contract price adjustment solely on the ground that the measurement rules or pricing rules have been updated, the expert appraiser maintains the pricing principles of the original price determination or tender in the contract and makes no adjustment (T/ZBD 100.4-2023 Article 4.4.8). The exception is Article 4.4.1: where government-fixed and government-guided price items, policy-based rates or national mandatory standards change after the tender deadline, the appraiser adjusts the price of the works executed after the time of change, whatever the contract says, issuing alternative opinions with explanations; but where the contract has expressly agreed the risk allocation for such element prices, the contract governs. Under BOQ pricing, price changes caused by laws, regulations and policy changes after the base date (newly added, amended or repealed provisions, changed government interpretations) are adjusted per GB/T 50500-2024 Article 8.8.1, and the overheads and profit within the total price and unit rates are not adjusted (8.8.5); where national fiscal and tax policy changes the VAT rate, VAT is computed at the new rate and the price adjusted by the difference between the old and new rates (8.8.6). The appraisal method is also chosen by contract type (T/ZBD 100.4-2023 Article 4.2.4).
- ←
Whether the all-in unit rate includes statutory levies and taxes: comparison and determination between BOQ-based pricing (non-fully-loaded) and the fully loaded all-in rate
Whether the all-in unit rate includes statutory levies and taxes depends on the pricing basis: under GB/T 50500-2024 BOQ-based pricing it excludes value added tax (VAT) (a price-exclusive tax listed separately) and no longer lists statutory levies and fees as a separate item (social insurance and housing fund contributions are amortized into labour cost and the overheads percentage rate); under the fully loaded all-in rate basis (GB/T 51095-2015 Clause 6.2.3, DB42/T 823-2021, DB14/T 1319-2021 highway) it includes statutory levies and fees and taxes. Confirm the applicable basis before pricing and review; the two sets must never be mixed.
- ←
The basis and cost attribution of the equipment-versus-material division in construction pricing (GB/T 50531-2009 general provisions, including process-type principal materials treated as equipment)
Per GB/T 50531-2009: divide equipment from material by supply scope, character and the standard's definitions - never by article name alone (clause 3.1.1); equipment-class costs enter permanent equipment procurement, material-class costs enter building-works or installation-works costs by discipline (clauses 1.0.3, 3.2.2). Equipment covers building services equipment, process equipment and process-type principal materials (long-distance pipelines, cables and the like special valves priced as equipment); the equipment scope = body + 5 items supplied with it (spares and fittings, companion piping and instruments, factory ladders platforms and railings, inspection and metering tackle, oils chemicals and packing). Fallback: not made on site counts as equipment, partly off-site with site assembly counts as equipment, catalogue products fabricated on site may count as material (clause 3.1.7).
- ←
Organizing the certification of material quality and price for installation materials and equipment: four applicable situations, a six-step implementation process, situation-based rules for employer approval of material prices, and dispute fallbacks
Certification of material quality and price is organized as 'lock quality first, then lock price, then lock evidence': the employer ultimately confirms the price; the contractor submits for approval before procurement; the supervisor reviews quotations, undertakes witnessed sampling and testing, and joins market price enquiries; the project-management body prepares the market price enquiry and pricing implementation plan; contractually adjustable materials must be jointly subject to market price enquiry and the price agreed by the employer, contractor and supervisor before procurement; follow the six steps 'prepare plan -> enquire and compare -> confirm price -> seal samples -> entry inspection -> settlement adjustment'; retroactively supplemented certifications of material quality and price carry weak weight in construction cost expert assessment (judicial appraisal).
- ←
GB/T 50500-2024 VAT pricing basis: all-in unit rates are fully inclusive prices excluding VAT, with VAT listed and assessed separately
BOQ item all-in unit rates and their totals are fully inclusive prices excluding VAT (labour cost + material cost + plant and small tools cost + management fee + profit + agreed risk costs + indispensable auxiliary work costs), with taxes and duties listed separately under VAT; the VAT base = the combined amounts of the bill of quantities for divisional and sub-divisional works + the bill of preliminaries + the bill of provisional sums and other charges (less provisional sums for nominated specialist subcontract works) x the prescribed rate; provisional sums for nominated specialist subcontract works are tax-inclusive provisional amounts, on which VAT is no longer assessed.
- ←
A determination framework for whether curtain-wall design-development (detail design) costs are included in the contract price: the watershed is to whom the development obligation belongs
Whether curtain-wall design-development costs are included in the contract price depends on "whose contractual obligation the development is": development necessary for the contractor's construction (fabrication drawings, subdivision layout, embedded part positioning, edge detailing, etc.) is the contractor's obligation, its cost already amortized into all-in unit rates/measure costs, not charged again; special designs, curtain-wall consultants, and BIM consulting separately commissioned by the employer are design services commissioned by the employer, outside the construction contract price, contracted and charged separately. Judge by the contract agreement, whether the development changes the design intent, whether the tender BOQ lists it separately, and the positioning in industry specifications; the tender documents and special contract conditions prevail.
- ←
Whether published price information includes VAT: the code caliber is a tax-exclusive price, while regional publications mix tax-inclusive and tax-exclusive in practice
Under the code caliber, price information as a pricing basis should be a tax-exclusive price excluding deductible input VAT (GB/T 50500-2024 Clause 3.1.6, T/ZBD 100.2-2022 Clause 4.4.2, TB 10801-2024 general principles), with VAT = tax-exclusive cost x tax rate (9% under general taxation) listed separately; however, the actual calibers of regionally published price information mix tax-inclusive and tax-exclusive — always verify against the current issue's publication notes before use; provisional prices of specialty works are tax-inclusive as an exception.
- ←
Adjustment of the contract price (GB/T 50500-2024 Chapter 8): eleven triggering events, mechanism by section, and FIDIC mapping
Adjustment of the contract price is the mechanism for changing the contract price during performance. GB/T 50500-2024 Cl. 8.1.1 lists eleven triggering events: BOQ errors, provisional sums, PC sums (provisional estimates), contractor's services, dayworks, changes in costs, changes in laws and policies, variations, additional works, claims, and other events agreed by the parties; the procedure runs submit, check, re-check, review and confirm (8.1.2). Key mechanics: BOQ errors and variations share one re-rating ladder (identical items at contract rates; analogous items converted; different items negotiated), with a 15% quantity boundary for re-rating (8.2/8.9); provisional sums are controlled by the employer and any unused balance reverts at final account (8.3); PC-sum items are replaced by tender prices — materials pre-VAT, specialist works VAT-inclusive (8.4); dayworks are measured under 7.5 (certified dayworks records) and priced at the BOQ daywork rates (8.6, with deemed approval if verification is overdue, 7.5.5); changes in costs are adjusted beyond the agreed band — 5% by default — by index-based (formula) adjustment or adjustment based on published price information (8.7 + Annex A), the differential carrying VAT only; changes in laws pivot on the base date, adjusting price and/or time for enactments, amendments, repeals or new interpretations after it, with no upward adjustment during contractor-caused delay (8.8); additional works may follow contract rates or freshly negotiated rules under a supplementary agreement (8.10); claims cover events outside 8.2-8.10 — compensatory, not punitive, and mutual, with profit added for eight categories of employer-risk events (8.11). FIDIC counterparts sit scattered across Clause 13 (variation valuation 13.3, provisional sums 13.4, changes in laws 13.6, changes in cost 13.7 — 2017 numbering) and Clause 20 claims (28-day hard time bar): adjacent institutions, not chapter-for-chapter equivalents.
- ←
Pricing rules for prime-sum estimates (provisional sums) of specialist works: GB/T 50500-2024 VAT-inclusive, lump-sum per item, deduction from the VAT base, and substitution on adjustment (compared with GB 50500-2013)
GB/T 50500-2024 defines the prime-sum estimate of specialist works as "specialist-work costs estimated VAT-inclusive where requirements and price cannot be fixed at tendering" (2.0.15, excluding works directly awarded by the employer), listed under the other-items list, priced by lump-sum per item (3.2.7); the VAT base is the total of work-item, preliminaries, and other-items lists (excluding the specialist prime sum), so VAT is not charged on it again (3.1.6, 3.2.11); on adjustment, mandatory-tender items are wholly replaced by the winning VAT-inclusive subcontract price (8.4.1), others may be priced VAT-inclusive per Section 8.10 or jointly tendered by both parties (8.4.7). Compared with GB 50500-2013's vague "comprehensive prime sum including management fee and profit other than fees and taxes" (Section 4.4), the rules are refined in price basis, pricing-mode classification, VAT treatment, and substitution.
- ←
Overview of material price adjustment in construction works: applicable conditions, base price (reference price for adjustment), risk band, and calculation methods (GB/T 50500-2024 Sections 3.3/8.7 and Appendices A, G)
Four indispensable elements of material price adjustment: ① adjustable scope (only labour cost, principal material cost, and construction machinery fuel and power cost, listed per Appendix G.2 Tables G.2.1-1/2 as a contract annex); ② base price (reference price for adjustment) C₀ (the market price level 28 days before the tender deadline (= FIDIC Base Date), or for non-tendered works 28 days before contract signing); ③ risk band r (contractual agreement takes precedence, in practice 3%–5%; where absent or unclear, a cost fluctuation beyond 5% triggers); ④ quantities subject to price adjustment Q (per the contract's agreed rules). Trigger |Ci−C₀|/C₀>r; upward unit price for the excess beyond the band = Ci−C₀(1+r), downward = C₀(1−r)−Ci; price difference = Σ unit price for the excess beyond the band × Q, carrying value added tax (VAT) only, with no management fee or profit.
- ←
GB/T 50500-2024 comparison of specialist-work provisional amounts (VAT-inclusive) and material provisional prices (VAT-exclusive): listing, taxation, and adjustment rules
Under GB/T 50500-2024 "Standard for BOQ pricing of construction works": the specialist-work provisional amount is a VAT-inclusive price (listed in other items, deducted from the VAT computation base to avoid double taxation, replaced wholesale by the successful VAT-inclusive subcontract price at adjustment); the material provisional price is a VAT-exclusive pre-tax unit price (entered into the comprehensive rate of a work-section item, VAT charged normally on the VAT line, adjustment limited to the pre-tax material difference within the comprehensive rate). The two have opposite tax calibers and differ in listing, taxation, and adjustment — mixing them double-counts or omits VAT.
- ←
Full-process handling rules for prime cost (PC) sums for materials included in the all-in unit rate across tender, performance and settlement (GB/T 50500-2024)
For prime cost (PC) sums for materials (tax-exclusive unit prices), tenderers must include them in the all-in unit rate as stated in the BOQ without unilateral alteration, and separately include safekeeping, secondary handling and loss costs and list them in Table E.2.3; during performance, after the winning tender price or the employer's approval of material prices, only the material PC sum item within the all-in unit rate is replaced, with other costs not adjusted; such items are not subject to the general adjustment for cost fluctuation under Clauses 8.7.2–8.7.4; for settlement and construction cost expert assessment (judicial appraisal), the material price confirmation sheet / winning tender basis serves as the price-adjustment voucher.
- ←
Four-tier progressive identification of high-risk bid-pricing clauses in tender documents (rejection clauses -> substantive requirements -> price locking -> performance funding)
Read tender documents as risk-allocation contracts: (1) rejection clauses (the seven statutory grounds of Implementation Regulations Article 51 as baseline, sector measures expand with catch-all clauses; below-cost is the hidden trap); (2) substantive requirement clauses ("must/shall/shall not" wording + deviation tables—non-response is statutory rejection); (3) price-locking clauses (GB/T 50500-2024: risk-scope clarification, three elements of price adjustment, lump-sum by total, lump-sum per item, preliminaries responsibility, unbalanced bidding); (4) performance funding clauses (Article 3.4.8 14-item checklist, performance deposit <=10%, seven quality-reserve agreements).
- ←
Establishing material sample-sealing and quality-and-price confirmation ledgers in decoration projects: samples govern quality, confirmed prices govern price, ledgers keep traceability
Sample-sealing governs quality, price confirmation governs price, ledgers keep traceability — a trinity: the sample-sealing ledger scopes per GB 50210-2018 Clause 3.3.8 + GB/T 50500-2024 Clause 3.7.2, with four-party confirmation, three-party sealing, and entry-comparison traceability; the price-confirmation ledger completes signing per the DB37/T 5096-2017 inquiry-pricing procedure before procurement — after-the-fact supplementary signing carries weak evidentiary weight in construction cost expert assessment (judicial appraisal) (GB/T 51262-2017 Clause 5.6.4); the two ledgers merge into one material control master ledger; provisional-sum material replacement adjusts the material cost only, with VAT counted separately (GB/T 50500-2024 Clauses 8.4.5/8.4.6).
- ←
Six-step labour-material-plant analysis for the all-in unit rate: apply quota line items -> take consumption and compilation-period unit prices -> add management fee and profit -> fill the all-in unit rate analysis sheet
Labour-material-plant analysis splits the all-in unit rate by "consumption x unit price" into three direct costs — labour cost, material cost, and plant and small tools cost — then superimposes management fee, profit, and the agreed risk cost; consumption is taken from quota line item factor values, unit prices from the report compilation-period market prices / published price information (government guidance prices), and fees per the matching norms for on-costs and expenses (GB/T 51095-2015 Clause 5.3.9). The analysis sheet must be fully consistent with the BOQ all-in unit rate (GB/T 50500-2024 Clause 3.1.7), in the form of Appendix E.2.2.
- ←
Three bases for the composition of the construction price: cost elements, BOQ-based pricing, and final-account listing
The construction price (cost of works (construction and installation)) has three composition bases: (1) by cost elements (GB/T 50875-2013 Clause 2.2.10) = labour cost + material cost + construction machinery usage cost + management fee + profit + statutory levies and fees + taxes and duties (VAT under the current standard); (2) by BOQ-based pricing (GB/T 50500-2024) = divisional/sub-divisional works cost + preliminaries + other-item cost + VAT — the 2024 edition abolishes the separate statutory-levies item, the all-in unit rate being a fully inclusive price excluding VAT, and the VAT base deducting provisional sums for nominated specialist subcontract works; (3) by final-account listing (Clause 10.3.2) — 13 items. Mind the differences between the 2013 and 2024 bases when comparing.
- ←
Determining re-tendering of provisional-sum specialty works, organization modes, and tax-inclusive price confirmation rules (Implementation Regulations Article 29 + GB/T 50500-2024 Section 8.4)
Specialty works included in the general-contract scope as provisional sums that fall within mandatory-bidding scope and meet scale thresholds (construction single-contract estimate above RMB 4 million, etc.) must be re-tendered; the re-tendering entity and mode (joint tendering / owner tendering / general contractor tendering) should be agreed in the general contract. Price confirmation: where tendering is mandatory, the winning tax-inclusive specialty subcontract price wholly replaces the provisional sum; where not mandatory, per Section 8.10, joint tendering, or contractor inquiry confirmed by the owner. Specialty-work provisional sums are VAT-inclusive—unlike the pre-tax replacement rule for material provisional sums.
- ←
GB/T 50500-2024 Appendix E pricing cost summary: Table E.1.1 summary hierarchy (project → single project → unit work) and aggregation rules for billed items, preliminary items, other charges and VAT
GB/T 50500-2024 Appendix E contains a single general summary table — Table E.1.1 "Project summary table" — using three-level numbering (1 → 1.1 → 1.1.1) to express the project → single project → unit work hierarchy; Note 2: "This table is preferably used for the summary calculation of works where the contract subject is the object of preparation of the bill of quantities; works where a single project or unit work is the object of preparation of the bill of quantities may also be summarised using this table." Aggregation rules: billed (BOQ) item costs (the only level expanded down to unit-work detail) roll up level by level; preliminary items (with 2.1 safety-production preliminary items listed separately) and other charges (broken out into provisional sums / provisional sum for nominated specialist subcontract works / dayworks / main contractor's attendance and coordination provisions / other items agreed in the contract) are summarised at whole-project level; VAT is listed separately and its calculation base excludes the provisional sum for nominated specialist subcontract works (Note 1); total = 1+2+3+4. All-in unit rates are fully inclusive prices excluding VAT (Clause 3.1.6, term 2.0.9); statutory levies and fees are no longer listed separately in the 2024 edition, having been merged into management fee; settlement follows Table E.6.1, with amounts adjusting for errors and omissions in the BOQ entered respectively under "contract price adjustment amount" of billed items and preliminary items.
- ←
Publication period of winning-candidate lists and objection/complaint procedures for evaluation results under the Implementation Regulations (Articles 54 and 60)
For mandatory-tender projects, the tenderer shall publish the winning candidates within 3 days of receiving the evaluation report, for at least 3 days; bidders or interested parties objecting to the results shall object during the publication period, and the tenderer shall reply within 3 days of receipt and suspend the proceedings until the reply. Dissatisfied parties may complain to the administrative supervision department within 10 days of knowing or should have known; complaints on Articles 22/44/54 matters require a prior objection (objection first), whose response period is excluded from the 10 days.
- ←
Budget pricing of custom cabinets, partitions, and ready-made furniture: BOQ listing calibers (011501/011207) and three pricing paths
Pricing custom cabinets/partitions/ready-made furniture first splits two routes — "site-built" vs "ready-made procurement": GB/T 50854-2024 Appendix Q.1.1 cabinets/frames/counters 011501 — site-built cabinets by orthographic projection area (011501001~003), ready-made cabinets by count/set (011501004); Appendix M.7.1 partition walls 011207 — by frame peripheral area (011207001~002), ready-made partitions 011207003 installation only. Three pricing paths: site-built per quota (materials adjusted per developed drawings), ready-made per purchase price + installation labor (ready-made is an unpriced main material requiring inquiry and listing), partitions in two tiers of site-built and ready-made. Where ready-made items are listed as provisional sums, only the material cost is adjusted after price confirmation (GB/T 50500-2024 Clause 8.4.6).
- ←
Six-step method for reviewing the reasonableness of all-in unit rates: rate build-up basis -> labour/materials/plant -> on-costs -> special items -> horizontal comparison -> arithmetic
Reviewing an all-in unit rate means breaking down and verifying the three pricing elements (labour/material/plant consumption x unit price + on-costs) layer by layer, plus horizontal comparison against market benchmarks. Six steps: (1) compliance of the rate build-up basis; (2) labour/material/plant consumption at quota norm values, unit prices at compilation-period market/published price information (government guidance prices); (3) compliance of on-cost rates and bases (in the 2024 edition, check for double-counting after statutory levies and fees are rolled in); (4) special items (provisional sums for specified materials adjust material price only; employer-supplied (free-issue) materials; attribution of risk allowances); (5) horizontal comparison against tender price ceilings/similar works/analogous projects and identification of unbalanced rates / rate loading; (6) arithmetic check (unit price x quantity = extended amount; analysis sheet consistent with the BOQ).
- ←
GB 50500-2013 -> GB/T 50500-2024: changes to the clauses on statutory levies and fees, taxes and the mandatory health, safety and environmental (HSE) provisions — mandatory provisions withdrawn, the bills restructured into four parts, and the item renamed statutory safety provisions
2013 Clause 3.1.6, “statutory levies and fees and taxes must be calculated in accordance with the provisions of the state, provincial or industry construction authorities and shall not be treated as competitive costs” (a mandatory provision), disappears entirely from GB/T 50500-2024: the 2024 edition is a recommended GB/T standard with no mandatory provisions anywhere; under Clause 3.1.2 the bills become four parts (work items / preliminaries / provisional sums and other charges / VAT), statutory levies and fees are no longer a separate billed item, and taxes are renamed VAT (Clause 3.2.11: the tax base is the total of work items + preliminaries + other items, less the provisional sum for nominated specialist subcontract works, multiplied by the tax rate). The mandatory health, safety and environmental (HSE) provisions are renamed “statutory safety provisions” (Clause 3.2.5), and their “non-competitive” character is expressly retained (“is a non-competitive item”), but the wording is softened from “must ... shall not be treated as competitive costs” to “shall be priced in accordance with the relevant provisions of the state and provincial or industry authorities”. GB/T 50500-2024 takes effect on 1 September 2025, and GB 50500-2013 is repealed at the same time.
- ←
Impact of the general vs the simplified VAT scheme on construction project profit and the critical input deduction rate decision
General VAT method: tax payable = output tax − input tax (inputs deductible); simplified VAT scheme: tax = sales amount × 3%, inputs non-deductible and fully sunk into costs. At the same tax-inclusive contract price, weight the composite input deduction rate r by cost structure (materials 13% special invoices, machinery rental 9%, labour subcontracting 3% simplified invoices, self-performed labour 0): above the critical value (≈6%–6.5% at a 10% gross margin) choose the general method, below it the simplified scheme; free-issue (employer-supplied) materials and labour-intensive projects with shallow input pools are often better under the simplified scheme, which additionally allows differential taxation on subcontract payments.
- ←
Definition and cost composition of the all-in unit rate (GB/T 50500-2024 Clause 2.0.9, GB/T 50875-2013 Clause 2.2.58)
All-in unit rate = labour cost + material cost (including engineering equipment) + plant and small tools cost + overheads (company and site) + profit + risk cost within the agreed scope and range, required to complete one specified unit of measurement of a billed (BOQ) item; VAT is excluded (a price-exclusive tax). Basis: GB/T 50500-2024 Clause 2.0.9 and GB/T 50875-2013 Clause 2.2.58; building works BOQ-based pricing uses the "incomplete-cost" caliber excluding statutory levies and fees and taxes, while highways and other industries may use the fully loaded caliber including statutory levies and fees and taxes — confirm the applicable industry standard before citing.
- ←
GB/T 50500-2024, China's BOQ pricing standard: positioning, 2024-vs-2013 changes, chapter map and card-group navigation
GB/T 50500-2024, the China national pricing standard for BOQ-based pricing (MOHURD Announcement No. 212 of 2024, approved 26 November 2024), came into force on 1 September 2025 and repealed GB 50500-2013. Its status shifted from a partly mandatory code to a recommended national standard (GB to GB/T), aiming to regularise pricing rules and let the market form construction costs. It governs pricing activity in tendering, contracting and execution for construction works; EPC and other general-contracting models apply it by reference, and the requirement that state-funded projects use BOQ pricing is carried by a MOHURD ministerial order. Nine headline revisions (per the foreword): risk scope and allocation rules by contract form; a new bid clarification mechanism; revised pricing of preliminaries; the 'contract price agreement' chapter replaced by contract selection and requirements; revised measurement and adjustment rules; site visas abolished and additional-works pricing introduced; interim settlement by construction stage added; dispute resolution revised; the cost-expert-assessment chapter deleted. The structure was rebuilt from 16 chapters into 12 chapters plus annexes: 'tender control price' renamed tender price ceiling; completion settlement and contract-termination settlement merged into 'works settlement and payment' (absorbing stage settlement); dispute resolution and expert assessment merged; pricing tables moved to annexes (with a new Annex G, schedule of price-adjustable key materials).
- ←
Provisional sums at final account: settlement line item, replacement paths, VAT basis and review essentials (GB/T 50500-2024)
At final account, provisional sums are dealt with as "the actually determined price replaces the provisional price, with the contract price adjusted by the difference": PC sums for materials (pre-tax) are replaced by the pre-tax winning bid price or by the pre-tax price from an inquiry/self-quotation confirmed by the employer, adjusting only the PC sum item for materials within the all-in unit rate, with all other cost elements unchanged; provisional sums for nominated specialist subcontract works (tax-inclusive) are replaced in their entirety by the winning tax-inclusive subcontract price. These enter settlement line item 4, "adjustment of provisional prices after procurement"; provisional sums for nominated specialist subcontract works do not enter the VAT calculation base; the core vouchers are the price-confirmation sheet (employer's approval of material prices) / letter of acceptance confirmed by both parties.
- ←
Determining material cost within the all-in unit rate: the two-step norm resource consumption × material unit price method, special situations, and the tax-exclusive boundary
Material cost = norm material consumption × norm-based material price for estimating: consumption is taken from the factor quantities of the budget quota norms (prescribed resource consumption standards) line item; the material unit price is the composite average price from the place of origin to the site warehouse up to issuance from the warehouse, with industry-specific formulas (railway: (original price + freight and handling included in the material price) × (1 + purchasing and custody percentage rate); highway: (original price + freight and handling charges) × (1 + off-site transport wastage rate) × (1 + purchasing and custody percentage rate)). Prime cost (PC) sums for materials are included at the tax-exclusive unit price stated in the BOQ; cost fluctuations beyond the agreed risk band (no-adjustment tolerance, e.g. ±5%; if not agreed, 5%) are adjusted per Appendix A, the price difference carrying value added tax (VAT) only, with no management fee or profit; material cost never includes VAT.
- ←
Price adjustment rules for brand changes of decoration materials: three situations, adjusting the material cost only, and the certification of material quality and price procedure
Brand-change price adjustment = replace the original price with the confirmed pre-tax price → adjust the material cost only (other costs unchanged) → VAT counted separately. Provisional-sum materials are replaced by tender/market price enquiry prices; non-provisional-sum (contract-agreed brand) materials must undergo the employer's certification of material quality and price before procurement — unconfirmed prices are not adjusted; under the railway system the price differential is computed as norm resource consumption x the difference between preparation-period and base-period prices.