GB/T 50500-2024 rules for adjusting price differences, management fee, and tax after the actual price of provisionally priced materials/equipment is determined (Section 8.4)

Per GB/T 50500-2024 Section 8.4, once the actual price of provisionally priced materials (including engineering equipment) is determined, only the material provisional-price item in the all-in unit rate is adjusted (pre-tax difference = confirmed actual pre-tax unit price − provisional pre-tax unit price, times quantity); labor, machinery, management fee, profit and other costs are not adjusted; VAT is charged additionally on the difference and the contract price is adjusted. Replacement price: for items subject to mandatory tendering by law, the pre-tax winning purchase price replaces it; otherwise, the pre-tax inquiry/own-quote price confirmed by the employer. Specialist-work provisional prices are VAT-inclusive, replaced wholesale by the winning VAT-inclusive subcontract price — a different rule.

Applicable Codes

  • GB/T 50500-2024 第 8.4.1、8.4.5、8.4.6 条
  • GB/T 50500-2024 第 2.0.14、3.2.11、8.1.8 条

Topic Positioning

GB/T 50500-2024, Standard for Valuation of Construction Works with Bills of Quantities, Section 8.4: after the actual price of materials/equipment given provisional prices in the BOQ is determined, how the price difference, management fee, and tax of the contract amount are adjusted.

Core Conclusions

The core principle is "adjust only the material price itself": only the material provisional-price item (pre-tax price) in the all-in unit rate is adjusted; labor, machinery, management fee, profit and other costs are not adjusted at all; the adjusted contract unit price may be used for pricing BOQ deficiencies, provisional sums, and works variations. Difference = (confirmed actual pre-tax unit price − provisional pre-tax unit price) × quantity; VAT is charged additionally on the difference (difference × the applicable rate set by the competent government authority) and merged into the contract price adjustment. The replacement price basis depends on whether tendering is mandatory by law: where mandatory, the pre-tax winning purchase price of the material replaces the provisional pre-tax price; where not, the contractor's market inquiry/own quote or a joint inquiry by both parties, replaced by the employer-confirmed pre-tax price. Note the basis: provisional prices of materials (including engineering equipment) are pre-tax prices excluding VAT, whereas specialist-work provisional prices are VAT-inclusive, replaced wholesale by the winning VAT-inclusive subcontract price — this rule does not apply.

Applicable Boundaries

Applies to contract price adjustment after determination of prices of provisionally priced materials (including engineering equipment) in the BOQ; not applicable to specialist-work provisional prices (wholesale VAT-inclusive replacement). Management fee and profit are not re-charged on the difference. Express contract agreements prevail. For simplified-taxation projects, VAT is at the levy rate, with the same formula structure. The VAT calculation base deducts the specialist-work provisional amounts in the other items list.

Further Reading

See GB/T 50500-2024: Clause 2.0.14 (material provisional price terminology, including engineering equipment, as the VAT-exclusive price delivered to site), Clause 3.2.11 (VAT calculation base and deduction of specialist-work provisional amounts), Clause 8.1.8 (after agreement on the adjustment item, calculate the VAT adjustment per Section 3.2), Clause 8.4.1 (replacement rules for mandatory tendering and the basis difference between material and specialist-work provisional prices), Clause 8.4.5 (non-mandatory inquiry replacement and VAT recalculation), Clause 8.4.6 (adjust only the material provisional price, other costs unchanged, and the uses of the adjusted unit price).