Pricing rules for prime-sum estimates (provisional sums) of specialist works: GB/T 50500-2024 VAT-inclusive, lump-sum per item, deduction from the VAT base, and substitution on adjustment (compared with GB 50500-2013)
GB/T 50500-2024 defines the prime-sum estimate of specialist works as "specialist-work costs estimated VAT-inclusive where requirements and price cannot be fixed at tendering" (2.0.15, excluding works directly awarded by the employer), listed under the other-items list, priced by lump-sum per item (3.2.7); the VAT base is the total of work-item, preliminaries, and other-items lists (excluding the specialist prime sum), so VAT is not charged on it again (3.1.6, 3.2.11); on adjustment, mandatory-tender items are wholly replaced by the winning VAT-inclusive subcontract price (8.4.1), others may be priced VAT-inclusive per Section 8.10 or jointly tendered by both parties (8.4.7). Compared with GB 50500-2013's vague "comprehensive prime sum including management fee and profit other than fees and taxes" (Section 4.4), the rules are refined in price basis, pricing-mode classification, VAT treatment, and substitution.
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works (第2.0.15、3.1.6、3.2.7、3.2.11、8.4.1、8.4.7条)
- GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works (第4.4、5.2.5、9.9节,已废止)
- 住房城乡建设部公告2024年第212号
Topic Positioning
The pricing rules for "specialist-work prime-sum estimates" under GB/T 50500-2024: VAT-inclusive price basis, lump-sum classification, deduction from the VAT computation base, substitution once actual prices are fixed, and a step-by-step comparison with the repealed GB 50500-2013 - for works priced under the 2024 standard (tender ceilings, bids, adjustments, settlement).
Core Conclusions
I. 2024 basic rules: (1) Term (2.0.15): "specialist-work costs provided by the employer in the BOQ, estimated VAT-inclusive where specific requirements and price cannot be determined at tendering"; "excluding specialist works directly awarded (nominated) by the employer" - covering only specialist works within the general-contract scope executed by the contractor. (2) Pricing mode (3.2.7): "the specialist-work prime sum may be priced by the lump-sum mode, calculated per item" - classified into the 2024 three-mode system (unit-price/lump-sum/percentage-fee) as lump-sum; material and equipment provisional unit prices go the unit-price route into work-item composite rates - a different mechanism. (3) VAT treatment (3.1.6, 3.2.11): the specialist prime sum "already includes VAT; the BOQ's VAT shall not charge its tax again"; VAT "shall be computed on the total of the work-item, preliminaries, and other-items lists (excluding the specialist-work prime sum) multiplied by the rate set by the authority"; "the other-items total used for VAT shall deduct the specialist-work prime sum contained" - when preparing bill footers, deduct it from the VAT base to avoid double taxation. (4) Substitution (8.4.1, 8.4.7): for mandatory-tender items, "the tendered VAT-inclusive specialist subcontract price shall replace the prime sum and adjust the contract price" - wholesale replacement; "material provisional prices are pre-tax (excluding VAT) while the specialist prime sum is tax-inclusive" - different substitution rules. For non-mandatory items, "the VAT-inclusive specialist-work price may be determined per Section 8.10 and replace the prime sum, or both parties may jointly tender to fix the VAT-inclusive subcontract price" - material provisional sums adjust only that item within the composite rate (pre-tax), leaving other costs unchanged.
II. Refinements versus 2013: (1) Price basis: 2013 Section 4.4 said "the specialist prime sum is a comprehensive estimate including management fee and profit other than statutory fees and taxes" - excluding fees and taxes; 2024 defines it as VAT-inclusive and excludes employer-nominated works. (2) Pricing mode: 2013 merely said "fill in the amount listed in the tender BOQ" (5.2.5), no mode classification; 2024 fixes lump-sum per item. (3) VAT: 2013 was silent on tax inclusion, double-taxation risk avoided by custom; 2024 states VAT-inclusive, deducts it from the base, and bars re-charging - a closed loop from listing to taxation. (4) Adjustment: 2013 Section 9.9 had four cases - materials/equipment mandatory-tender, not; specialist works not mandatory (priced per 9.3), mandatory (both parties tender per law: if the contractor does not bid, it tenders and submits documents/results to the employer for approval with costs in the contract price; if it bids, the employer tenders and bears costs, equal conditions favoring the contractor; the winning subcontract price replaces the prime sum). 2024 splits specialist works into two clauses (8.4.1 mandatory -> wholesale replacement by the winning tax-inclusive price; 8.4.7 non-mandatory -> per 8.10 or joint tender) and distinguishes material provisional sums (pre-tax, item-only) within the same section.
III. Practice: the specialist prime sum sits in the other-items list, listed "per item", outside work-item composite pricing - a VAT-inclusive total in the budget; when computing VAT at the unit-work bill footer, deduct it from the other-items total (3.2.11), else tax is double-charged.
Applicable Boundaries
Applies to BOQ works priced under GB/T 50500-2024 (recommended standard, Announcement No. 212 of 2024, effective 1 Sep 2025, repealing GB 50500-2013; actual force per tender documents and contract). Not applicable to material/equipment provisional prices (pre-tax unit basis, item-only adjustment - do not mix) or employer-nominated specialist works; VAT rates follow the authority. The 2013 clauses are for comparison only - repealed, not a pricing basis.
Further Reading
See GB/T 50500-2024 2.0.15 (term), 3.1.6 (pre-tax full-cost basis; no double tax on inclusive prime sums), 3.2.7 (lump-sum per item), 3.2.11 (VAT base deduction), 8.4.1/8.4.7 (substitution by tender status), 8.10 (pricing non-mandatory specialist works); 2013: Section 4.4, 5.2.5, Section 9.9 (four cases); re-tendering tests per Implementation Regulations Article 29 and NDRC Order No. 16.