Liability for errors or omissions in the tender BOQ: GB 50500-2013 vs GB/T 50500-2024 (2013 Clause 4.1.2 mandatory provision vs 2024 Clause 3.1.8 split by unit-rate/lump-sum contract)

GB 50500-2013, Clause 4.1.2 (mandatory provision): 'the tender BOQ must form part of the tender documents, and its accuracy and completeness shall be the tenderer's responsibility.' GB/T 50500-2024, Clause 3.1.8, instead splits liability by the contract pricing method: for unit-rate contracts, the accuracy and completeness of the divisional and elemental BOQ rest with the employer (tenderer) - bidders may not alter it on their own, defects adjust the price per Section 8.2, with a 15% quantity change as the threshold; for lump-sum contracts they rest with the contractor, who may supplement the list, and per 8.2.3 the contract price and time are not adjusted for BOQ defects (except unit-priced items with provisional quantities); the item-priced measure list is in all cases the contractor's responsibility. The 2024 edition was approved by MOHURD Announcement No. 212 of 2024, is effective from 1 September 2025 with GB 50500-2013 repealed simultaneously, and changed from a mandatory (GB) to a recommendatory (GB/T) national standard.

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.1.8、4.1.4、6.1.6、8.2.1、8.2.3条
  • GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第4.1.2条(已废止)
  • 住房城乡建设部公告2024年第212号(2024-11-26,www.mohurd.gov.cn)

Topic Positioning

The normative evolution of liability allocation when the tender BOQ contains miscalculations or omissions (BOQ defects): comparison between GB 50500-2013, Clause 4.1.2 (mandatory provision; the tenderer is responsible for the accuracy and completeness of the list) and GB/T 50500-2024, Clause 3.1.8 (liability split by unit-rate/lump-sum contract), plus the price-adjustment path for BOQ defects. Applies to works procured by BOQ pricing under the GB/T 50500 series standards.

Core Conclusions

  1. 2013 edition (the source of the saying 'BOQ errors are the tenderer's problem'): GB 50500-2013, Code for Valuation with Bills of Quantities for Construction Works, Clause 4.1.2: 'The tender BOQ must form part of the tender documents, and its accuracy and completeness shall be the responsibility of the tenderer (employer).' This was a mandatory provision to be strictly enforced, allocating liability uniformly to the tenderer regardless of contract type.
  2. The 2024 edition has changed this - liability split by contract pricing method: GB/T 50500-2024, Standard for Valuation of Construction Works with Bills of Quantities, Clause 3.1.8:
    • For works under unit-rate contracts, the accuracy and completeness of the divisional and elemental work BOQ rest with the employer; bidders may not alter the list when bidding.
    • For works under lump-sum contracts, the accuracy and completeness of the priced divisional and elemental work BOQ rest with the contractor; bidders may supplement BOQ items and price them on their own based on the tender drawings and technical standards.
    • Under both unit-rate and lump-sum contracts, the completeness and accuracy of the item-priced measure list rest with the contractor, and bidders may decide at their own discretion whether to add items and prices.
  3. Edition history: approved by MOHURD Announcement No. 212 of 2024 as a national standard, effective from 1 September 2025, with the former national standard GB 50500-2013 repealed simultaneously; the 2024 edition moved from a mandatory national standard (GB) to a recommendatory one (GB/T).
  4. Consequence chain for BOQ defects:
    • Clause 4.1.4: where the tender BOQ is used for a unit-rate contract, defects in the divisional and elemental BOQ are borne by the employer and adjusted per Section 8.2; where used for a lump-sum contract, the contractor bears the responsibility of supplementing and completing the list, and per Clause 6.1.7 no adjustment is made.
    • Clause 6.1.6: unit-rate bidders shall verify the list within the prescribed time and raise written queries for clarification per the tender documents; 'regardless of whether the bidder has raised queries or objections, the completeness and accuracy of the divisional and elemental work BOQ are the responsibility of the tenderer (employer)'; where defects exist, the price and contract total are adjusted per Section 8.2.
    • Clause 8.2.1 (unit-rate contracts): re-measure per the contract drawings; where BOQ defects cause changes of list items (additions or deletions), or the bill quantity increases or decreases by not more than 15% (inclusive) of the contract quantity of the corresponding item, the contract price is adjusted per Clause 8.9.1; where the change exceeds 15% (exclusive), per Clause 8.9.2.
    • Clause 8.2.3 (lump-sum contracts): 'the contract price and contract time shall not be adjusted for contract-list defects', except items whose divisional quantities are expressly priced as provisional quantities, which may be adjusted per Clauses 7.2.1 and 8.2.1.
  5. Practical conclusion: under unit-rate contracts (the majority in practice), the right to adjust for BOQ omissions and miscalculations remains with the contractor and the liability with the tenderer; under lump-sum contracts the risk shifts to the contractor. Before compiling a budget or bid, first confirm the contract pricing method, then determine who bears BOQ defects and under which rules they are handled.

Applicable Boundaries

  • This card applies only to works tendered and contracted under the BOQ pricing mode; liability allocation presupposes a clearly defined pricing method (unit-rate/lump-sum) - the same list carries entirely opposite defect risk under different contract types.
  • The 2024 edition is a recommendatory national standard (GB/T); its liability provisions take effect through incorporation by the tender documents and the contract, and actual execution follows the tender documents and contract clauses; the 2013 edition (mandatory national standard) has been repealed since 1 September 2025 and no longer applies.
  • The completeness and accuracy of the measure list do not change with contract type - always the contractor's responsibility; 'provisional quantity' unit-priced items are the sole exception to the lump-sum no-adjustment principle.
  • This card covers liability allocation and the adjustment procedure, not the computation of adjusted amounts (unit-price adjustment rules within and beyond the 15% threshold - see Clauses 8.9.1/8.9.2 and the related card).

Further Reading

  • 2024 edition: GB/T 50500-2024, Standard for Valuation of Construction Works with Bills of Quantities - Clause 3.1.8 (basic provisions, BOQ liability), Clause 4.1.4 (BOQ compilation), Clause 6.1.6 (bid pricing, verification and clarification), Clauses 8.2.1 and 8.2.3 (price adjustment, BOQ defects), Clauses 8.9.1/8.9.2 (adjustment computation).
  • 2013 edition: GB 50500-2013, Code for Valuation with Bills of Quantities for Construction Works, Clause 4.1.2 (mandatory provision).
  • Basis of edition history: MOHURD Announcement No. 212 of 2024 (26 November 2024) publishing the Standard for Valuation of Construction Works with Bills of Quantities; the standard is published on the MOHURD website (www.mohurd.gov.cn).