Rate build-up basis and confirmation procedure when a BOQ omission or new item has neither an applicable nor an analogous rate: GB 50500-2013 Section 9.5 (citing the four tiers of cl. 9.3.1) mapped against GB/T 50500-2024 Sections 8.2/8.9/8.10, plus the time limits for adjustment reports
GB 50500-2013 cl. 9.5.1 provides that 'where, during performance, new divisional and sub-divisional works BOQ items arise because of omissions in the tender BOQ, the unit rates shall be determined per cl. 9.3.1 of this code and the contract price adjusted'. Tier 3 of cl. 9.3.1 reads 'where the priced BOQ contains neither an applicable nor an analogous item for the varied work, the contractor shall propose a unit rate for the varied work based on the variation documents, the measurement rules and pricing methods, the published price information issued by the government construction cost administration and the contractor's price fluctuation rate, and adjustment follows employer confirmation'; tier 4 switches, where the published price information lists no price, to a rate based on 'market prices with a lawful basis obtained through market enquiry and other means', again subject to employer confirmation -- so published price information comes first and a lawful market price only fills gaps, and tier 3 must carry the contractor's price fluctuation rate. GB/T 50500-2024 no longer has a stand-alone 'omission' section: erroneous and omitted items are folded into 'errors and omissions in the BOQ' (cl. 8.2.1 -> cl. 8.9.1/8.9.2), additional works outside the contract scope follow Section 8.10 (cl. 8.10.2 requires the contractor to submit the project execution plan or execution scheme, the programme and the priced offer to the employer for review and approval before executing the additional works), the adjustment procedure is unified as 'submission, checking, re-checking, review and confirmation' (cl. 8.1.2 to 8.1.4), and employer silence past the time limit counts as deemed approval of the contractor's report.
Applicable Codes
- GB 50500-2013 第9.1.2条、第9.1.4条、第9.3.1条、第9.3.2条、第9.5.1~9.5.3条、第9.6.2条(已废止)
- GB/T 50500-2024 第8.1.2~8.1.4条、第8.2.1~8.2.3条、第8.9.1~8.9.2条、第8.10.1~8.10.5条、第8.6.3条、第7.2.1条
- 住房城乡建设部公告 2024 年第 212 号(GB/T 50500-2024 自2025年9月1日起实施)
What This Card Covers
This card answers 'when a BOQ omission (folded into errors and omissions in the BOQ by the 2024 edition) or a new item outside the contract scope has neither an applicable nor an analogous rate in the priced BOQ, on what basis the rate is rebuilt and through which confirmation procedure it becomes usable for settlement'. It gives the original text of GB 50500-2013 Section 9.5 and the four tiers of cl. 9.3.1 it cites, maps them clause by clause against GB/T 50500-2024 (clause numbers noted in the text), and lists the submission-checking-re-checking-confirmation time limits for adjustment reports.
Core Conclusions
1. Original text of GB 50500-2013 Section 9.5 (BOQ omissions).
- Cl. 9.5.1: 'During performance of the contract, where new divisional and sub-divisional works BOQ items arise from omissions in the tender BOQ, the unit rates shall be determined per cl. 9.3.1 of this code and the contract price adjusted.'
- Cl. 9.5.2: 'Where new divisional and sub-divisional works BOQ items cause changes to preliminary items, the contract price shall be adjusted per cl. 9.3.2 of this code after the execution scheme submitted by the contractor is approved by the employer.'
- Cl. 9.5.3: 'Where the tender BOQ omits a preliminary item, the contractor shall submit the execution scheme for the new preliminary item to the employer for approval, and the contract price shall then be adjusted per cl. 9.3.1 and cl. 9.3.2 of this code.'
- Section 9.5 commentary: new divisional and sub-divisional works BOQ items are priced and adjusted per cl. 9.3.1; changes to preliminary items caused by a new item are calculated per cl. 9.3.2 after the execution scheme is approved by the employer; for an omitted preliminary item, the contractor submits the execution scheme for approval and the adjustment is calculated per cl. 9.3.1 and 9.3.2. In short: the 2013 edition lists 'omissions' as a stand-alone section but sets no separate pricing rule, referring straight back to the variation valuation clauses; both preliminary-item routes (changes caused by an omission, and an omitted preliminary item itself) make 'contractor submits an execution scheme, employer approves' a precondition of adjustment.
2. The four tiers of cl. 9.3.1 (the valuation ladder shared by omissions and variations), original text. 'Where a variation causes changes to priced BOQ items or their quantities, adjustment shall follow these provisions: 1 Where the priced BOQ contains a rate applicable to the varied work, that rate shall be adopted; but where the variation changes the quantity of that BOQ item and the quantity deviation exceeds 15%, the rate shall be adjusted per cl. 9.6.2 of this code. 2 Where the priced BOQ contains no applicable but an analogous item for the varied work, the rate of the analogous item may be referenced within a reasonable range. 3 Where the priced BOQ contains neither an applicable nor an analogous item for the varied work, the contractor shall propose a unit rate for the varied work based on the variation documents, the measurement rules and pricing methods, the published price information issued by the government construction cost administration and the contractor's price fluctuation rate, and adjustment shall follow employer confirmation. The contractor's price fluctuation rate may be calculated by the following formulas: tendered works / non-tendered works (both formulas are in the original text of the code). 4 Where the priced BOQ contains neither an applicable nor an analogous item for the varied work, and the published price information issued by the government construction cost administration lists no price, the contractor shall propose a unit rate for the varied work based on the variation documents, the measurement rules, the pricing methods and market prices with a lawful basis obtained through market enquiry and other means, and adjustment shall follow employer confirmation.' The rebuild order can be distilled: (1) the factual and rule basis is the variation documents, the measurement rules and the pricing methods (used to derive labour, material and plant consumption and build the rate); (2) the price source is first the published price information issued by the government construction cost administration; (3) only where that lists no price does 'market price with a lawful basis obtained through market enquiry and other means' take over; (4) tier 3 must multiply in the contractor's price fluctuation rate (two formulas, tendered and non-tendered works; take the formulas from the code's original text); (5) tiers 3 and 4 both require 'propose the rate -> employer confirms -> adjust'; confirmation precedes settlement.
3. Adjustment report time limits under GB 50500-2013 (procedure for omission-based upward adjustments).
- Cl. 9.1.2: 'Within 14 days after a contract price increase event arises (excluding quantity deviation, dayworks, site instruction records and claims), the contractor shall submit to the employer a contract price increase report with the supporting documents; if the contractor submits no report within 14 days, it shall be treated as having no price adjustment claim for that event.'
- Cl. 9.1.4: the employer (or the contractor) shall verify within 14 days of receiving the other party's price increase (decrease) report and documents, and notify confirmation in writing; where it has questions it shall raise comments for discussion; failure to confirm or to raise comments within 14 days of receipt means the report submitted is deemed approved by the receiving party; where comments are raised, the other party shall verify and confirm in writing within 14 days of receipt, and its failure to confirm or object within 14 days means the comments are deemed approved. An omission is a 'contract price increase event' (and not among the excluded four: quantity deviation, dayworks, site instruction records and claims), so it is bound by the twin limits of '14 days to submit + 14 days to verify and confirm', and silence past the limit produces 'deemed approval'.
4. Counterpart clauses in GB/T 50500-2024 (the structure has changed; cite the new clause numbers).
- Entry for identifying omissions: the 2024 edition no longer has a stand-alone 'omission' section; 'erroneous or omitted BOQ items, mismatching item descriptions and quantity deviations' are uniformly 'errors and omissions in the BOQ'. Cl. 8.2.1: works under unit-rate contracts shall re-measure all BOQ items and quantities of the divisional and sub-divisional lists of the contract drawings per cl. 7.2.1; where the defect causes a change of BOQ items (items added or removed), or a change of BOQ quantities no more than 15% (inclusive) of the quantity contained in the contract BOQ for the item, the contract price is adjusted per cl. 8.9.1; where the quantity change exceeds 15% (exclusive), per cl. 8.9.2.
- Preliminary items changed by an omission: cl. 8.2.2: once the defect corrections under cl. 8.2.1 are complete, the bill of preliminary items and the contract time shall not be adjusted, except for statutory safety provision items and the preliminary items under item 2 of cl. 7.2.1; among preliminary items, only statutory safety provision items calculated per the contract, formwork and temporary works listed in the divisional and sub-divisional list, and preliminary items agreed as measurable may be adjusted -- the other preliminary items are not adjusted for BOQ defects (the statutory safety provisions cost may be adjusted by the standard's formula). This differs from the 2013 cl. 9.5.2 and 9.5.3 approach of 'adjust preliminaries once the scheme is approved' -- the 2024 edition locks preliminaries in principle.
- Additional works outside the contract scope (a separate track, 2024 Section 8.10): cl. 8.10.1: for additional works outside the agreed scope required by the employer, the contractor may price them using the itemisation requirements, the measurement rules and any supplementary measurement rules of the national and industry quantity take-off standards agreed in the contract, the contract unit rates and the tender pricing level, or the measurement and pricing rules may be renegotiated and an additional works contract or supplementary agreement signed; the preliminaries shall include the cost of extended-use or new preliminary items. Cl. 8.10.2: before executing the additional works the contractor shall submit for the employer's review its project execution plan or execution scheme, its programme, and its priced offer for the costs it requests (including the divisional and sub-divisional list and the bill of preliminary items), which the employer shall approve within a reasonable time. Cl. 8.10.3: where the divisional and sub-divisional list of the additional works uses contract unit rates, the rates are adjusted per Sections 8.7 and 8.8 and priced per Section 8.9, and the price effects of four difference factors must be met -- the difference between the labour, material and plant unit rates inside the contract rate and reasonable market prices when the additional works are executed; the batch or small-lot purchase effect of quantity differences between the quantities behind the contract rate and the related items of the additional works; the correction of under- or over-stated rates inside the contract rate; and the difference between contract rates fixed by tender competition and the all-in unit rate of the additional works fixed by negotiation. Cl. 8.10.5: where a variation occurs in the additional works, pricing may use the all-in unit rates in the priced offer approved by the employer under cl. 8.10.2 together with the pricing rules of Section 8.9; cl. 8.2.2 and cl. 8.2.3 are not suited to pricing additional works.
- Confirmation procedure: cl. 8.1.2: the contractor shall measure the quantities of the adjustment event per Chapter 7, calculate the adjusted price per Sections 8.2 to 8.11, and submit it with the relevant documents to the employer for checking within the agreed time; the parties may proceed by the 'submission, checking, re-checking, review and confirmation' procedure. Cl. 8.1.3: having received the contract price adjustment report and documents, the employer shall verify within the agreed time, notify confirmation in writing, or reply in writing with checking comments if it does not confirm; neither confirming nor raising checking comments means the report submitted by the contractor is deemed approved by the employer. Cl. 8.1.4: where the employer raises checking comments, the contractor shall re-check within the agreed time of receipt, notify acceptance in writing or reply with its re-checking comments; neither confirming nor raising objections means the employer's comments are deemed accepted by the contractor.
- Written confirmation requirements (common to both editions): from the contractor, the adjustment report / adjusted rate plus the supporting documents (execution scheme, project execution plan, programme, priced offer, etc.); from the employer, a written confirmation notice; silence by either party past the limit triggers the presumption of 'deemed approval'. The settlement basis is the all-in unit rate confirmed in writing (or presumed approved by law).
5. Choosing between editions. Projects follow the standard edition agreed in the contract: GB 50500-2013 was withdrawn on 1 September 2025 upon implementation of GB/T 50500-2024 (Announcement No. 212 of 2024 of the Ministry of Housing and Urban-Rural Development); contracts signed after 1 September 2025 must cite GB/T 50500-2024 clause numbers, and any citation of the 2013 Section 9.5 must note that the edition is withdrawn.
Applicability Boundaries
- This card targets the tier 'neither an applicable nor an analogous rate'; where an applicable rate exists the contract rate is used directly (2013 cl. 9.3.1 tier 1 / 2024 cl. 8.9.1 item 1), and where an analogous rate exists the conversion uses the analogous item (tier 2 / item 2) -- both outside this card.
- Responsibility for omissions (employer under unit-rate contracts, contractor under lump-sum contracts, and always the contractor for the bill of preliminary items) is covered by cards on responsibility allocation; this card resolves only the pricing basis and the confirmation procedure.
- The exact formulas of the 2013 'price fluctuation rate' (one for tendered, one for non-tendered works) sit in the code's original text; this card does not repeat them -- consult GB 50500-2013 cl. 9.3.1 when applying.
- Under the 2024 edition preliminaries are in principle not adjusted for BOQ defects (cl. 8.2.2); the old 2013 cl. 9.5.2 / 9.5.3 approach of 'approved scheme means adjustment' must not be carried over; claims for omitted preliminary items must be judged under cl. 8.2.2 and item 2 of cl. 7.2.1.
- Stand-alone adjustment rules for dayworks (2024 cl. 8.6.3), provisional prices and cost fluctuation are out of scope.
- The 2024 edition is a recommended national standard (GB/T) whose clauses bind through tender documents and contractual agreement; where the contract provides otherwise, its terms prevail.
- The 14-day limits of both editions yield to contractually agreed periods; the standard values are default fallbacks.
Further Reading
- GB 50500-2013: cl. 9.1.2 and 9.1.4 (submission, verification and confirmation limits), cl. 9.3.1 (the four valuation tiers and the price fluctuation rate formulas), cl. 9.3.2 (adjustment for changed preliminary items), cl. 9.5.1 to 9.5.3 (BOQ omissions), cl. 9.6.2 (rate adjustment above a 15% quantity deviation).
- GB/T 50500-2024: Sections 7.1, 7.2 and 7.4 (confirmation and quantities for variations and BOQ defects), cl. 8.1.2 to 8.1.4 (adjustment procedure and deemed approval), cl. 8.2.1 to 8.2.3 (BOQ defects and non-adjustment of preliminaries), cl. 8.9.1 to 8.9.2 (the all-in unit rate tiers and the 15% boundary), cl. 8.10.1 to 8.10.5 (pricing and approval of additional works outside the contract scope), cl. 8.6.3 (pricing of dayworks all-in unit rates).
- Edition history: Announcement No. 212 of 2024 of the Ministry of Housing and Urban-Rural Development; GB/T 50500-2024 takes effect on 1 September 2025 and GB 50500-2013 is withdrawn at the same time.
Keywords
- 工程量清单缺项
- 清单漏项
- derivation of new (built-up) rates
- 承包人报价浮动率
- 综合单价报发包人确认
- 措施项目缺项
- 新增工程计价
- 14天调价报告