Risk allocation for incomplete item descriptions in the BOQ (BOQ errors and omissions): employer responsible under re-measurable (unit-rate) contracts, contractor responsible under lump-sum contracts, contractor always responsible for the bill of preliminaries
Per GB/T 50500—2024, an incomplete item description is an "error or omission in the BOQ": under re-measurable (unit-rate) contracts the employer (tenderee) is responsible for the completeness of billed items, the accuracy of item descriptions and the accuracy of quantities, and at settlement the all-in unit rate is re-rated on the basis of the characteristics actually constructed to adjust the contract price; under lump-sum contracts the contractor is responsible and no adjustment is made except for provisional quantities; for the bill of preliminaries, the contractor is responsible under both re-measurable and lump-sum contracts.
Applicable Codes
- GB/T 50500—2024 第 3.1.8、6.1.6、8.2.1、8.9.1、8.9.2、3.3.3 条
- GB 50500—2013 第 4.1.2、9.5.1 条
- 《建设工程造价鉴定作业指引》T/ZBD 100.4—2023 第 4.4.4 条
Topic Positioning
This card answers "when item descriptions in the BOQ are incomplete (errors and omissions in the BOQ), who bears the tender-pricing and settlement risk" — setting out the allocation of responsibility and the price adjustment rules under GB/T 50500—2024, for quick reference in tender review and in assessing settlement disputes.
Core Conclusions
- Re-measurable (unit-rate) contracts (the mainstream in tendering): completeness of billed items, accuracy of item descriptions and accuracy of quantities are the employer's (tenderee's) responsibility; contract price adjustments arising from errors or omissions follow Section 8.2, and at settlement the all-in unit rate is re-rated on the basis of the characteristics actually constructed and the contract price is adjusted.
- Lump-sum contracts: completeness and accuracy of the BOQ are the contractor's responsibility; except for "provisional quantities" items, the contract price is not adjusted for errors or omissions in the BOQ.
- Bill of preliminaries: regardless of whether the contract is re-measurable or lump-sum, its completeness and accuracy are always the contractor's responsibility.
- Bidders must review the billed items and raise doubts in writing for clarification, but whether or not doubts are raised, completeness and accuracy of the BOQ remain the tenderee's responsibility.
- Adjustment sequence for errors or omissions under re-measurable contracts (8.9.1/8.9.2): for item additions/deletions or quantity changes ≤15%, prefer the contract unit rate → conversion by analogy to similar items → negotiated rate build-up; for the portion beyond 15%, the unit rate is reasonably reduced for added items and reasonably increased for deleted items.
- The contractor bears its own technical and management risks and market risks within the agreed range (3.3.3), and may not mix these into claims based on "incomplete item descriptions".
Applicable Boundaries
Applies to tendering and awarding activities using pricing on a bill of quantities basis where the contract was signed after 2025-09-01 (the implementation date of GB/T 50500—2024); earlier projects follow GB 50500—2013, with the same conclusions (old Clauses 4.1.2, 9.5.1). Exceptions: errors or omissions in the bill of preliminaries, portions under lump-sum contracts already supplemented and priced by the bidder, and risks borne by the contractor itself — no adjustment for BOQ errors or omissions may be claimed for these.
Further Reading
See GB/T 50500—2024 Clause 3.1.8 (division of responsibility for BOQ completeness), Clause 6.1.6 (tender review and clarification), Clause 8.2.1 (adjustment for errors or omissions under re-measurable contracts), Clauses 8.9.1–8.9.2 (adjustment methods and the 15% deviation rule), Clause 3.3.3 (contractor's own risks); old/new comparison with GB 50500—2013 Clauses 4.1.2 and 9.5.1; for construction cost expert assessment (judicial appraisal) practice see Guideline for Construction Cost Expert Assessment T/ZBD 100.4—2023, Clause 4.4.4, Item 3.
Keywords
- errors and omissions in the BOQ
- 项目特征描述不完整
- 项目特征不符
- 清单完整性 责任
- 风险承担
- 综合单价 重新确定
- GB/T 50500-2024
Cited By
- ←
Judging the code non-compliance of 'cut only, never add' in final account review, the clause basis for the contractor's claim to symmetric upward review (the full-review method, objective and fair deliverables, two-way quantity-difference pricing, BOQ errors on the employer), and the entrances for upward adjustment and the written-objection remedy
'Cut only, never add' has no code basis: GB/T 51095-2015 clause 8.3.5 requires the full-review method for final account review, barring key, sampling or analogy methods, and clause 1.0.3 requires fair stand, conduct, procedure, method and deliverables; T/ZBD 100.5-2023 clause 4.2.3 requires the review report to state the disallowed and the added prices and rates with item-by-item reasons. The quantity-difference rules are themselves two-way: GB 50500-2013 clause 9.6.2 lowers the all-in rate on the added part beyond +15% and raises it on the remaining part beyond -15%; GB/T 50500-2024 clause 8.2.1 splits at 15% (inclusive / exclusive) with the mirrored pricing of clauses 8.9.1 and 8.9.2. The accuracy and completeness of unit-rate work-item lists rest on the employer (clause 3.1.8) - the normative entrance for upward review - but the contractor must file itemised written objections within the agreed time, silence being deemed acceptance (clauses 10.3.8, 10.3.10).
- ←
Differences in final account adjustment between lump-sum contracts (fixed total price) and unit-rate contracts (fixed unit rates): treatment rules for quantity changes, BOQ errors, design changes and cost fluctuation, mapped to GB/T 50500-2024 clause numbers
GB/T 50500-2024 uses 'lump-sum contract / unit-rate contract' rather than 'fixed total price / fixed unit rate'; the substantive difference lies in the allocation of quantity and price risk. A lump-sum contract wraps up both quantities and prices - the measured-works BOQ items need not be re-measured, and price changes arising from BOQ errors are deemed included in the contract total and are not adjusted during performance (clauses 4.1.6, 7.2.2, 8.2.3); only 'provisional quantity' unit-rate-priced items and variations may be adjusted. A unit-rate contract fixes the rates and re-measures the quantities - all BOQ items and quantities of the measured works must be re-measured, BOQ errors fall on the employer, and quantity changes are priced under clause 8.9.1 or clause 8.9.2 depending on the 15% (inclusive / exclusive) boundary (clauses 2.0.6, 4.1.4, 8.2.1). The adjustment rules for cost fluctuation (where no band is agreed, adjustment under Annex A is allowed once the movement exceeds 5%, the differential bearing VAT only, with no overheads or profit) and for changes in laws and regulations and policy are identical for both contract types.
- ←
Trigger table for the +/-15% quantity deviation threshold: the three outcomes of retaining the original price, adjusting the rate and deriving new rates, and the dividing lines between them (GB/T 50500-2024 Articles 8.2.1, 8.9.1, 8.9.2 and 8.9.3)
Under GB/T 50500-2024 the 15% mark is only a threshold on quantity, and it decides only between 'retain the original price' and 'adjust the rate': where the billed quantity of a BOQ item increases or decreases by no more than 15% (15% included) of the quantity contained in the contract BOQ for that item, the all-in unit rate is set under Article 8.9.1 (item 1: same conditions plus same item description, adopt the contract rate, that is, retain the original price; item 2: similar item description or similar conditions, convert the contract rate of an analogous BOQ item; items 3 to 5: negotiate a market-reasonable all-in unit rate, in substance deriving new rates); where the change exceeds 15% (15% excluded), Article 8.9.2 applies: with an increase, the contract rate and the new all-in unit rates are reasonably reduced to reflect the discounts on labour and material procurement prices; with a decrease, they are reasonably increased to reflect the loss of those discounts. A change of exactly 15% (inclusive) does not trigger the rate-adjustment tier. 'Deriving new rates' is triggered not by quantity but by changes in the item description or the construction conditions; the two lines are independent and can combine.
- ←
Classifying divergence between the design earthwork balance and the actual site balance, allocating responsibility among the four parties, and the cost adjustment pathway (with the chain of evidence and the normative basis)
GB 50201-2012 clause 4.1.3 sets the division-of-duty baseline: the balance figures are 'basic balance data put forward by the designer, on which the contractor then performs balance calculations according to the actual situation ... with multiple balance adjustments further made during construction'; hence divergence between the actual and the design table does not of itself constitute a variation or ground a claim. The divergence must first be characterised into three types - measurement-basis type (conversion factors not unified; whoever miscalculated corrects it), factual type (original ground levels / geology / design omissions; allocated by cause) and fault type (the defaulting party bears it, including enlarged losses) - and responsibility then allocated item by item by cause: erroneous original data from the employer, adverse physical conditions, instructed variations and insufficient design documents are borne externally by the employer (which may recover from the investigator or designer), while the contractor bears its own method adjustments, over-excavation and what it should have foreseen.
- ←
Constituent requirements of BOQ item descriptions and the three common defects (vague description / missing measurable parameters / disconnect from the work process), with corrected drafting (GB/T 50500-2024 clauses 2.0.5, 2.0.27, 4.1.7, 4.2.2, 4.2.4; GB/T 50854-2024 clause 4.1.2)
An item description, by definition (GB/T 50500-2024 clause 2.0.5), is 'a textual description stating the nature and requirements of the BOQ item itself ...'; a description written wrongly falls under clause 2.0.27, BOQ errors (including 'mismatched item description'), and enters the price-adjustment channel rather than mere textual polish. The hard yardstick of accurate description is GB/T 50854-2024 clause 4.1.2 - 'item descriptions must be given accurately and comprehensively ... sufficient to satisfy the need to determine the all-in unit rate' - and they must be 'prepared on the basis of the design documents and in combination with the completion and handover requirements' (GB/T 50500-2024 clause 4.2.2); any parameter whose variation would change labour, material and plant consumption or the basis of percentage charges must be stated, while decorative words that do not change the price are useless if stated.
- ←
Attributing the ironmongery of proprietary doors and windows (hinges, locks, handles, closers, coordinators): the list basis folds it into the door's all-in rate with no separate item, while quota bases split by their door-and-window chapter notes - 'proprietary with ironmongery / hinges only / ordinary in, special out' - with special ironmongery on separate items
Two bases decide 'included or not': the list basis (GB/T 50854-2024 Appendix H) holds hinges, pivots, handles, locks, latches, stops, closers, rollers and tracks, floor springs and the like as inherent to the door - folded into the all-in rate, never listed apart, save 'locks installed alone' at 010801006 per set; where the item description omits ironmongery, clause 4.1.2 ('deemed to include all work necessary') with GB/T 50500-2024 clause 3.3.3 bars both separate listing and claims. The quota basis reads the chapter notes of the volume applied: Beijing 4.9.3 - metal doors carry their matched ironmongery, fire doors exclude locks / closers / hinges / coordinators / concealed latches; Jiangsu and Shaanxi timber-door items carry hinges only, the rest on special-ironmongery items; Shenzhen's proprietary fire doors carry all - the same project may flip conclusions between systems.
- ←
Whether the employer may refuse to pay for additional works when the actual investment in a government-funded project exceeds the approved estimate: the estimate as an administrative control instrument, who bears the duty to apply for an estimate adjustment, attribution of the causes of overruns, and risk allocation under an EPC lump-sum contract
In principle it may not. The verified investment estimate is an administrative investment-control indicator for a government-funded project, not a cap on the civil contract price nor a condition of payment. Article 23 of the Regulation on Government Investment Projects (State Council Decree No. 712) places the duty to apply for an estimate adjustment on the project unit (the employer); its failure to file the application cannot be turned against the contractor. Whether the price can be adjusted truly turns on the cause of the overrun: employer-instructed variations, raised standards, errors in basic data, and major policy, price or geological changes are payable; contractor design defects, omissions and pricing errors are borne within the lump sum. Failure of the audit or the government fiscal review likewise does not automatically ground a defence ([2008] Min Yi Ta Zi No. 4; Fa Shi [2026] No. 12 Art. 13).
- ←
Price adjustment for quantity increases caused by the contractor's construction-stage design development under an EPC lump-sum contract: no adjustment in principle; adjustment only where the difference constitutes an employer-required variation or arises from employer causes
No adjustment in principle; adjustment only by exception. Where the contractor, as required by the contract, carries out construction-stage design development of the contract drawings and the design development drawings differ from the contract drawings, the contract price shall not be adjusted unless otherwise agreed in the contract or otherwise required by the employer (GB/T 50500-2024 Clause 3.3.9); however, where the difference constitutes a variation required by the employer, the additional costs affected shall be calculated and adjusted under Clauses 7 to 9 of the standard. The construction cost expert assessment position is consistent: where the contractor carries out design development and requests adjustment of the all-in unit rate, the expert assessor generally will not adjust it, unless the contract provides that the contractor's design development drawings serve as the basis for construction payment settlement (T/ZBD 100.4-2023 Clause 4.4.6). Where the difference arises from employer causes (errors in the Employer's Requirements or in base data, changes in laws, regulations and policies, or employer-approved variations) or constitutes additional works outside the contract scope, the price may be adjusted as prescribed.
- ←
Deciding claims to adjust the contract price for omitted items in the tender BOQ (BOQ errors) during performance: risk is allocated by the contract pricing method and the BOQ section in which the omission falls - omission from the work-section bills under a unit-rate contract may rest with the employer and be adjusted under section 8.2; a lump-sum contract is in principle not adjusted (except provisional quantity items); the bill of preliminaries is always the contractor's responsibility - with judicial limits and points of procedure and proof
Whether adjustment is possible depends not on the omission itself but on the contract pricing method and the BOQ section in which the omission falls: GB/T 50500-2024 cl. 3.1.8 provides that under a unit-rate contract the accuracy and completeness of the work-section BOQ rest with the employer (adjustment by re-measurement under section 8.2 may be claimed, with a 15% increase or decrease in quantities as the divide between cl. 8.9.1 and 8.9.2); under a lump-sum contract they rest with the contractor, and save for unit-priced items in provisional quantities the contract price and contract time are not adjusted for BOQ errors (cl. 6.1.7 and 8.2.3); the bill of preliminaries compiled on a per-item basis is always the contractor's responsibility, with only statutory safety provisions and similar exceptions adjustable. Where the contract provides settlement at a fixed price and adjustment is claimed for major changes in labour cost or key material prices, the court will not support it (Article 9 of Fa Shi [2026] No. 12).
- ←
The boundary and pricing routes between BOQ errors and omissions and variations: distinguished by the two comparison benchmarks 'contract BOQ vs contract drawings' and 'contract drawings vs actual construction drawings', mapping respectively to BOQ-error price adjustment under Section 8.2 and variation valuation under Section 8.9 of GB/T 50500-2024
GB/T 50500-2024 Article 7.2.1 draws the line by benchmark: 'a discrepancy between the divisional and sub-divisional work item lists in the contract BOQ and the contract drawings constitutes an error or omission in the bill of quantities' (routed to Section 8.2 - under a re-measurable contract, re-measure under Article 8.2.1 and adjust under Articles 8.9.1/8.9.2 at the 15% threshold; under a lump-sum contract, no adjustment under Article 8.2.3), while 'a difference between the contract drawings and the actual construction drawings constitutes a variation' (quantities computed under Article 7.4.2 and priced under Section 8.9, unaffected by the lump-sum no-adjustment rule for BOQ errors). Mis-characterisation derails both the claim route and the adjustment basis; and once a BOQ error is corrected, no preliminary items other than statutory safety provisions and those under Article 7.2.1(2), and no contract period, shall be adjusted.
- ←
Preliminaries — the "lump sum, no adjustment" principle and the full landscape of adjustable exceptions (GB/T 50500-2024 cl. 3.3.7, 7.3.1)
Under GB/T 50500-2024, the China national pricing standard for BOQ (Code of Valuation with Bill of Quantities of Construction Works), preliminaries follow a lump-sum no-adjustment principle, reflected at three levels: (1) the construction method statement reported at tendering is deemed reasonable and feasible, the cost is priced as a lump sum, and the contractor bears the risk of cost increases arising from adjusting its own method statement (cl. 3.3.7); (2) preliminary items in the priced BOQ shall not be re-measured or adjusted (cl. 7.3.1); (3) preliminaries are not adjusted for changes in costs (cl. 8.7.6 item 3). Exception channels: preliminary works listed as billed (BOQ) items and items the contract requires to be measured (cl. 7.2.1, 7.2.2); statutory safety provisions (per contract); variations (measured per cl. 7.4.4, priced per cl. 8.9); errors and omissions in the BOQ (cl. 8.2.2, 8.2.3); unforeseeable works within provisional sums (cl. 7.7.2); delayed use, removal/re-installation, increase or duplicated provision of the contractor's preliminary items due to the employer, and material changes to the time for completion (costs borne by the employer, cl. 3.3.7). Under re-measurable (unit-rate) contracts, only the statutory safety provisions and BOQ-listed formwork/temporary works etc. are adjustable for BOQ errors and omissions (cl. 8.2.2). Adjustments require "submitting the method statement for confirmation before implementation" (cl. 8.9.6); late submission is deemed waiver, and the other party's late confirmation is deemed acceptance (cl. 8.9.7).
- ←
The unit-price / total-price preliminaries divide and its migration in the BOQ system: the 2013 'unit-price items / total-price items' split of GB 50500-2013 clauses 4.3.1-4.3.2 against the three pricing methods of GB/T 50500-2024 clauses 2.0.10~2.0.12 and 3.2.1
GB 50500-2013 clause 4.3.2 split preliminaries by 'whether quantities can be computed': those that cannot (site discipline, safety, temporary facilities) price 'per item' as total-price items; those that can (scaffolds, dewatering) price 'per quantity' as unit-price items, with clause 4.3.1 mandatory (preliminaries lists compiled per the current national measurement codes). GB/T 50500-2024 drops the split: pricing now runs by unit, total or rate (2.0.10~2.0.12); work items and dayworks suit unit pricing, preliminaries preferably total or rate (3.2.1 - total, per item); quantifiable specialist preliminaries such as concrete formwork have moved into the work-item list of GB/T 50854-2024 (Appendix E Table E.5.1, code 010505), and expert-reviewed specialist schemes may price by unit within the work-item list.
- ←
Pricing clash-detour increments of MEP services: the attribution boundary of detailing versus variation, the valuation entries (8.9.1 / 8.9.2 and 2013's 9.3.1), the material and labour increments of cable-tray extended metres, bends and supports, and the separate claim channel for stoppage and the site-record anchors
Three gates before pricing a detour: (1) difference nature - contract versus actual drawings = variation; refinement within one drawing set is no variation; (2) attribution - the employer's design errors and base-data faults are employer risk; the contractor's routine detailing avoidance is contractor risk, generally unadjusted (T/ZBD 100.4-2023 clause 4.4.6) save contracts settling on the contractor's detailing drawings; (3) the entry - variations with quantity moves within 15% price on the five bands of 8.9.1, beyond 15% on 8.9.2 with purchase-discount adjustments. Quantity magnitude fixes 'how to price', never 'whether to pay'. Stoppage, waiting and idle losses claim separately under 8.11.9 / 8.11.10 - never merged into variation rates.
- ←
Tender BOQ versus priced BOQ - relationship and effect compared: preparing and pricing parties, document status, content differences, accuracy responsibility (2013 edition clause 4.1.2 versus 2024 edition clause 3.1.8 split by unit-rate and lump-sum contracts), benchmark role in settlement (quantity variance under 9.6.2, variation valuation under 9.3.1), effect of unilateral amendment, and the order of precedence of contract documents
The two bills are not two documents but two stages of one bill: the tender BOQ is prepared by the tendering employer stating 'quantities and item descriptions' and issued with the tender documents as the common basis of tender pricing (GB 50500-2013 clauses 2.0.2, 4.1.2 (mandatory provision) and 4.1.3); the priced BOQ is the priced version in which the bidder enters all-in unit rates and lump sums and which becomes part of the contract documents after award (2013 edition clause 2.0.3; the 2024 edition calls it the 'contract bill of quantities', clauses 2.0.18 and 3.4.5), its all-in unit rates being the contract unit rates used for settlement and contract price adjustment. Responsibility follows the basic split 'quantities by the tendering employer (employer), prices by the bidder': clause 4.1.2 of the 2013 edition puts it on the tendering employer in all cases; GB/T 50500-2024 clause 3.1.8 changes course - under unit-rate contracts the employer answers for the measured-works bill (bidders may not alter it; defects are repriced under section 8.2), under lump-sum contracts the contractor answers, and preliminaries are always the contractor's. In settlement, quantity variance follows clause 9.6.2 of the 2013 edition (deviation beyond 15%: the all-in unit rate is lowered for the portion of quantity increase above 15%, and raised for the remaining portion after a decrease beyond 15%), and variation valuation follows the three-tier cascade of clause 9.3.1 (applicable -> analogous by reference -> a rate proposed by the contractor from the pricing methods and published price information combined with the tender price fluctuation rate, submitted to the employer for confirmation).
- ←
Full workflow for preparing the tender bill of quantities: preparing entity and object, the seven bases of preparation, itemisation with the five elements and item description, the four-part BOQ composition, deliverables and appendix forms, error liability, and the interface with the tender price ceiling
Chapter 4 of GB/T 50500-2024 provides: the bill of quantities is prepared by a tenderer with preparation capability or by a construction cost consultant commissioned by it (4.1.1); it is itemised with the contract object or a single project or individual structure as the object and forms part of the tender documents (4.1.2); the deliverables comprise the cover, signature page, explanatory notes of the estimate, notes on measurement rules, and the BOQ and pricing forms (4.1.3), in forms B.1.1, C.1.1, D.4.1, E.1.1/E.2.1/E.2.3/E.3.1/E.4.1 to E.4.5/E.5.1 and G.1.1. The BOQ is prepared and priced in four parts -- the work-item BOQ, the preliminaries BOQ, the other items BOQ and VAT (3.1.2) -- and the current edition no longer carries a statutory levies and taxes section; the all-in unit rate and the sum are fully inclusive pre-tax prices excluding VAT, tax is entered under VAT, and the provisional sum for nominated specialist subcontract works already includes VAT and must not be taxed again (3.1.6).
- ←
Determining missing items not listed in the BOQ appendices and setting supplementary items: the three-element comparison search path, the discipline-code + B coding rule (from 01B001), the five required accompanying elements, the tender-document explanation / filing requirements, and the boundary of error when fitting near-match items
Under GB/T 50854-2024 Clause 4.1.4, for items not covered in Appendices A~R the compiler may add supplementary items, coded with this standard's code 01 plus B and three Arabic numerals, numbered sequentially from 01B001, and must attach the item name, item description, unit of measurement, quantity take-off rule and work content (for preliminaries that cannot be measured: name, work content and scope of inclusion). The determination is a three-element comparison (item description + work content + unit of measurement with calculation rule): so long as any element can be carried by an existing appendix item, the existing item must be applied forward and the difference expressed in the item description, and no supplementary code may be created; work content lists only principal operations, auxiliary content such as plant movement and material transport is deemed included, and operations may not be split out and listed separately unless specifically stated. The 2024 editions (GB/T series) say 'may add' and no longer require filing; instead GB/T 50500-2024 Clause 3.1.3 requires the supplementary basis to be explained in the tender and contract documents; the 2013 compulsory national standards required 'shall add + file with the provincial or industry construction cost administration institution', and local standards may still retain the filing requirement.
- ←
Price adjustment findings for 'mismatching item descriptions' under GB 50500-2013 Section 9.4: the elements of cl. 9.4.1/9.4.2, re-determining the all-in unit rate per the as-executed item description using the cl. 9.3 method, and the clause mapping after the 2024 edition merged this event into 'errors and omissions in the BOQ'
GB 50500-2013 cl. 9.4.2 provides: where, during performance, the design drawings (including design changes) mismatch the item description of any item in the tender BOQ and that change causes an increase or decrease in the cost of the item, the all-in unit rate shall be re-determined per the item description as actually executed, under the relevant clauses of Section 9.3, and the contract price adjusted. The four findings elements are: the comparison base is the pair of tender drawings / tender BOQ; any item; a cost increase or decrease is caused; pricing per the actual description with the method borrowed from Section 9.3. The responsibility basis is cl. 4.1.2 (a mandatory provision of codes): the accuracy and completeness of the tender BOQ are the tendering employer's responsibility. The 2013 edition has been superseded by GB/T 50500-2024, which merges mismatching item descriptions, erroneous and omitted items and quantity deviations into 'errors and omissions in the BOQ' (cl. 2.0.27), entering through cl. 8.2.1 and priced through cl. 8.9.1/8.9.2.
- ←
Classification basis and table numbers for soil and rock on site (soft rock / hard rock / boulders), the threshold position on measuring boulders as rock, and the price adjustment boundary where the actual class differs from the BOQ item description
BOQ item descriptions are entered per Table A.4.3-1 of GB/T 50854-2024 (soil classes 1-4, judged by soil name plus excavation method) and Table A.4.3-2 (extremely soft rock through extremely hard rock); where classes cannot be fixed precisely, describe from the geotechnical investigation report. The quota-system classes 'loose rock / sub-hard rock / ordinary hard rock / extra-hard rock' (Protodyakonov I-XVI) are not listed in the BOQ classification tables and must not be entered as item descriptions. Boulders: the building works position has only a qualitative boundary - clearance of natural obstructions 'removable together with the earthworks' is already inside the earthwork items, while boulders needing separate breaking or crushing are listed separately as rock or handled as missing items or variations; the water sector position expressly measures boulders larger than 0.7 m3 as rock excavation. Where the class differs from the BOQ description, under a unit-rate contract the all-in unit rate is re-determined on the item description actually constructed (GB 50500-2013 clause 9.4.2), with a 15% quantity deviation as the boundary for rate adjustment (clause 9.6.2).
- ←
Key points for the item description of earthworks BOQ items: how to set soil class and rock class (tables A.4.3-1 and A.4.3-2), the optional dry or wet soil supplement, the geotechnical investigation report as fallback, and the GB/T 50500-2024 compilation requirements for coding, names, descriptions, units and work content plus the itemisation principles
GB/T 50854-2024 A.4.3: soil class and rock class are set per table A.4.3-1 and table A.4.3-2, with dry or wet soil descriptions added where needed; where the class cannot be accurately determined, the description is based on the geotechnical investigation report. Item descriptions, together with coding, item names, units of measurement and work content, must be compiled per the national and industry quantity take-off standards (GB/T 50500-2024 clause 4.1.7); itemisation follows 'clear, unambiguous boundaries, easy to price and pay', with codes preferably ascending (clause 3.1.4); the description entries are governed by the exact wording of tables A.1.1, A.2.1 and A.3.1, and disposal of surplus excavated material is a separate item under table A.3.1, not an incidental entry in the excavation item's description.
- ←
Bills of quantities errors (item description mismatches, wrong or missing items, quantity deviations): determination, attribution of responsibility and the quantity-then-price adjustment sequence, including the split between unit-rate and lump-sum contracts and the 15% threshold rule
Where the BOQ and the drawings are inconsistent, the sequence is 'decide which prevails -> attribute the defect -> remeasure and adjust the price': under a unit-rate contract the BOQ prevails, under a lump-sum contract the contract drawings and specifications prevail (GB/T 50500-2024 clause 3.4.7); for unit-rate contracts, BOQ errors in the schedule of divisional work items lie with the employer - remeasure per clause 7.2.1, band the change per clause 8.2.1 at the 15% boundary (15% inclusive), and where not exceeded set the all-in unit rate adjustment per clause 8.9.1; for lump-sum contracts BOQ errors lie with the contractor, and the contract price is not adjusted except for items described as 'provisional quantities' (clauses 4.1.4, 4.1.6 and 6.1.7).
- ←
Re-measurement and price adjustment rules after quantity changes caused by variations or BOQ errors: recalculating from the variation instruction and the actual construction drawings, the separate track for BOQ errors, the 15% banded unit-rate adjustment, and the scheme-approval precondition for pricing preliminaries and new preliminary items (GB/T 50500-2024 clauses 7.4.2-7.4.4, 8.2.1, 8.9.1-8.9.2; GB 50500-2013 clauses 9.3.1, 9.3.2, 9.6.2)
Re-measurement after a variation takes as its basis the quantities recalculated from 'the variation instruction issued or confirmed by the employer and the actual construction drawings', compared with the BOQ quantities after the BOQ errors have been corrected, to determine the added or deleted variation items and their quantities; differences between the contract drawings and the contract BOQ are BOQ errors (corrected under unit-rate contracts, not adjusted under lump-sum contracts). Where the quantity difference is within 15% (15% inclusive), the unit rate is set under GB/T 50500-2024 clause 8.9.1; beyond 15% (exclusive), clause 8.9.2 adjusts downward on increase and upward on decrease in light of labour and material purchase concessions (the 2013 edition corresponds to the four tiers of clause 9.3.1 and clause 9.6.2). Preliminaries adjustment requires prior submission of the proposed scheme confirmed by the employer and the contractor; failure to submit is deemed to cause no preliminaries adjustment or a waiver of the right to adjust. New preliminary items take the added temporary works and plant machine-shifts priced from the approved scheme; the added cost of extended use of existing preliminaries and supervisory staff from variations off the critical path need not be measured.
- ←
Whether increased pipeline quantities caused by BIM coordinated layout can adjust the work quantities: determined by attribution in the deepening design (contractor's own deepening design — no adjustment; only where it constitutes a variation is adjustment made)
Whether the quantities of pipelines increased by BIM coordinated layout can be adjusted depends on attribution: differences arising from the contractor's own deepening design are generally not adjusted (GB/T 50500-2024, Clause 3.3.9; T/ZBD 100.4-2023, Clause 4.4.6), except where the contract provides for settlement on the basis of the deepened drawings; where the employer so requires, or where it constitutes a variation confirmed upon review by the original designer, adjustment is made per Chapters 7/8/9, and where the quantity difference exceeds 15%, the unit rate is adjusted per Clause 8.9.2.
- ←
Composition of the tender bill of quantities: the five parts of GB 50500-2013 (bill of divisional and elemental work items, bill of preliminaries, bill of provisional sums and other charges, bill of statutory levies, bill of taxes and duties) with the itemisation rules of each, and the composition contrast under GB/T 50500-2024
GB 50500-2013 Clause 4.1.4: the tender bill of quantities shall be compiled with the individual work (or project) as the unit and shall consist of the bill of divisional and elemental work items, the bill of preliminaries, the bill of provisional sums and other charges, and the bills of statutory levies and of taxes and duties. Under Clause 4.4.1 the bill of other charges contains provisional sums, provisional prices (provisional unit prices for materials, provisional unit prices for permanent plant, provisional prices for nominated specialist works), dayworks, and the main contractor's attendance and coordination provisions; under Clause 4.5.1 statutory levies cover social insurance contributions (old-age, unemployment, medical, work-injury and maternity), the housing provident fund, and the works pollution discharge fee; under Clause 4.6.1 taxes and duties cover business tax, city maintenance and construction tax, the education surcharge and the local education surcharge. GB/T 50500-2024 Clause 3.1.2 instead compiles and prices the bill of divisional and elemental work items, the bill of preliminaries and the bill of other charges together with value added tax (the statutory levies and tax bills are no longer set up; the tax becomes value added tax, computed per Clause 3.2.11 by multiplying the total of the three bills, after deducting the provisional prices of nominated specialist works, by the VAT rate).
- ←
The source definition, pricing basis and final account aggregation of the three kinds of quantities (contract BOQ quantities / variation quantities / dayworks record quantities), including the comparison baselines for BOQ errors - variation - additional works and the one-gateway-only rule against double measurement (GB/T 50500-2024 clauses 7.2, 7.3, 7.4, 7.5, 8.2, 8.6, 8.9, 8.10, 8.11, 10.3; compared with GB 50500-2013 clauses 9.3, 9.14, 11.2)
Clause 7.4.1 of GB/T 50500-2024 draws the boundary with three comparison baselines: the difference between the contract drawings and the contract BOQ = errors and omissions in the BOQ (corrected under unit-rate contracts, not adjusted under lump-sum contracts); the difference between the contract drawings and 'variation instructions + as-executed drawings' = variation; work outside the contractual scope of works completed at the employer's request = additional works (8.10.1); sundry items and events not attributable to the contractor are measured on dayworks vouchers (7.5.3 to 7.5.6). In-contract quantities are re-measured under 7.2.1 (BOQ items priced per item are not re-measured or adjusted); deviations within 15% (inclusive) go to 8.9.1 and beyond 15% to 8.9.2, the rate progressing 'contract rate -> converted similar rate -> negotiated market-reasonable all-in unit rate'; dayworks take the contract dayworks all-in unit rate under 8.6.2, or where no such BOQ item or no applicable rate exists the published price information under 8.6.3 and, failing that, the contractor's purchase price as confirmed by both parties, the rate already covering the sporadic extra costs and preliminaries of dayworks (8.6.4). Settlement aggregates in the 13-item order of 10.3.2, with preliminaries and the main contractor's attendance and coordination provisions recalculated at final account (10.3.3). No double measurement: variation quantities are determined only after comparison with 'the BOQ items and quantities as corrected for BOQ errors' (7.4.2), and what has already been adjusted under 8.2 to 8.10 may not be claimed again under the claims provisions (8.11.1).
- ←
Rate build-up basis and confirmation procedure when a BOQ omission or new item has neither an applicable nor an analogous rate: GB 50500-2013 Section 9.5 (citing the four tiers of cl. 9.3.1) mapped against GB/T 50500-2024 Sections 8.2/8.9/8.10, plus the time limits for adjustment reports
GB 50500-2013 cl. 9.5.1 provides that 'where, during performance, new divisional and sub-divisional works BOQ items arise because of omissions in the tender BOQ, the unit rates shall be determined per cl. 9.3.1 of this code and the contract price adjusted'. Tier 3 of cl. 9.3.1 reads 'where the priced BOQ contains neither an applicable nor an analogous item for the varied work, the contractor shall propose a unit rate for the varied work based on the variation documents, the measurement rules and pricing methods, the published price information issued by the government construction cost administration and the contractor's price fluctuation rate, and adjustment follows employer confirmation'; tier 4 switches, where the published price information lists no price, to a rate based on 'market prices with a lawful basis obtained through market enquiry and other means', again subject to employer confirmation -- so published price information comes first and a lawful market price only fills gaps, and tier 3 must carry the contractor's price fluctuation rate. GB/T 50500-2024 no longer has a stand-alone 'omission' section: erroneous and omitted items are folded into 'errors and omissions in the BOQ' (cl. 8.2.1 -> cl. 8.9.1/8.9.2), additional works outside the contract scope follow Section 8.10 (cl. 8.10.2 requires the contractor to submit the project execution plan or execution scheme, the programme and the priced offer to the employer for review and approval before executing the additional works), the adjustment procedure is unified as 'submission, checking, re-checking, review and confirmation' (cl. 8.1.2 to 8.1.4), and employer silence past the time limit counts as deemed approval of the contractor's report.
- ←
Handling the mismatch between construction-drawing quantities and tender BOQ quantities: measurement of actually completed quantities under GB 50500-2013 Chapter 8 and the 15% deviation price adjustment of Section 9.6 (including the divergence between the two lump-sum contract regimes of Clauses 8.3.1/8.3.2), against GB/T 50500-2024 Sections 7.2/8.2/8.9 routing the rules by contract type
GB 50500-2013 Clause 8.2.1 (a mandatory provision) requires that 'quantities shall be determined by the quantities of the contract works that the contractor has completed and that are to be measured'; the quantities stated in the tender BOQ are only estimated quantities and the common basis for tender pricing, and the final account quantities are determined by the quantities actually completed and to be measured, calculated by the contractor under the calculation rules of the current national measurement standards, not by the BOQ quantities. Clause 8.3.1 provides that for lump-sum contracts formed by tendering on a bill of quantities basis the quantities are still calculated under Section 8.2 (i.e. quantity differences remain adjustable), which diverges from Clause 8.3.2: for lump-sum contracts formed by letting the works on the basis of construction drawings and budgets examined and approved, except for variations, the BOQ quantities are the final settlement quantities. GB/T 50500-2024 instead routes the rules by contract type: for unit-rate contracts the employer bears the BOQ defects, the works are re-measured under Clause 7.2.1 and the price adjusted via Clause 8.2.1 (15% as the boundary) and then Clauses 8.9.1/8.9.2; for lump-sum contracts Clause 7.2.2 allows no re-measurement, and Clause 8.2.3 provides that 'the contract price and the time for completion shall not be adjusted for defects in the contract bill of quantities' (except items priced at provisional quantities). Directional rule for quantity deviations beyond 15%: where the increase exceeds 15%, the all-in unit rate of the increased portion is adjusted downwards; where the decrease exceeds 15%, the all-in unit rate of the remaining portion after the decrease is adjusted upwards.
- ←
Boundary determination and clause routing among quantity deviation, variation and omitted BOQ items: sections 9.4/9.5/9.6 of the 2013 edition are merged into 'BOQ errors' in GB/T 50500-2024, sorted by three comparison tests (contract drawings vs contract BOQ; contract drawings vs actual construction drawings; inside vs outside the contract works scope), with an anti-double-counting rule that one matter goes through one route only
The routing test is unique: a difference between the contract drawings (including the contract specifications) and the priced BOQ equals BOQ errors; a difference between the contract drawings and the actual construction drawings (including variation instructions issued or confirmed by the employer) equals a variation; physical works outside the contract works scope and the completion delivery requirements are additional works. GB/T 50500-2024 has merged 2013 edition Section 9.4 (item description mismatch), Section 9.5 (omitted BOQ items) and Section 9.6 (quantity deviation) into 'BOQ errors' (Clause 2.0.27), with quantity differences tiered at 15%: up to and including 15% goes to Clause 8.9.1, above 15% (exclusive) goes to Clause 8.9.2. The key anti-duplication procedure: varied quantities must be determined by comparison with the BOQ items and quantities 'after the BOQ errors have been corrected' -- the same quantity difference must not be adjusted once as an error correction and again as a variation increase or decrease.
- ←
Adjusting all-in unit rates at the +/-15% quantity boundary: GB/T 50500-2024 Clauses 8.9.1-8.9.3 and the reading of the wording change from repealed GB 50500-2013 Clause 9.6.2's "tiered pricing"
Under GB/T 50500-2024 (unit-price contracts): within 15% (inclusive) per 8.9.1's five tiers (same characteristics + same conditions -> contract rate; similar -> converted; different -> negotiated market rate); beyond 15% per 8.9.2, "accounting for the purchase-price discounts gained by increased quantities (or lost when decreased), reasonably lower (or raise) the contract rate and new composite rates" - more quantity lowers the rate, less raises it. The repealed 2013 Clause 9.6.2 explicitly said "the rate of the increased portion shall be lowered; the rate of the remaining portion after decrease shall be raised" (tiered: within +/-15% unchanged); 2024 drops "portion" and does not say whether the tiered or whole-quantity repricing applies - a genuine ambiguity; being a recommended standard, contract terms govern - lock the tiered basis in the special conditions.
- ←
The depth standard for describing item descriptions in the bill of quantities: describe item by item per the appendices, satisfy the needs of fixing the all-in unit rate, and never substitute the quota work content (trades)
The item description is the pricing parameter that fixes the all-in unit rate; the depth floor is 'describe item by item per the item descriptions prescribed in the appendices of the corresponding discipline measurement standard + satisfy the needs of fixing the all-in unit rate' (GB/T 50854-2024 clauses 4.2.4, 4.1.2). Citing a standard drawing collection or drawing number covers only 'the part it can satisfy' - the rest still needs words (GB 50860-2013 clause 4.2.4 commentary). Copying the work content (trades) of the quota / appendices replaces no item description: work content defines the included scope of the offer and the trade boundaries, and trades must not be split into separate items - copying produces no pricing parameters such as material, grade or strength class, and invites trade-splitting double pricing.
- ←
Defining and selecting construction contract price forms: unit-rate, lump-sum and cost-plus contracts chosen by design depth, technical difficulty, time and pricing risk
GB/T 50500-2024 clause 3.4.1 fixes the selection: clear requirements, controllable measurement and pricing and small price-fluctuation risk suit the lump-sum contract; requirements not yet clear, high technical difficulty, many uncontrollable pricing factors and large price risk suit the unit-rate contract; extreme urgency precluding detailed planning and full negotiation, or specially complex works with large pricing risk, suits cost-plus - clause 3.4.3 adds emergency rescue, disaster relief or specially complex works. The statutory definitions are clauses 2.0.6~2.0.8 (unit-rate: quantities as executed, rates fixed within agreement; lump-sum: price fixed within agreement, no adjustment for quantity changes while drawings and conditions stand; cost-plus = cost + agreed fee). The choice also binds the BOQ-error liability (3.1.8), risk allocation (3.3.2/3.3.3) and settlement treatment (GB/T 51095-2015 clause 8.2.5).
- ←
Determining the all-in unit rate of additional works (outside the contract-agreed scope of works) (GB/T 50500-2024 Section 8.10)
The all-in unit rate of additional works follows the dual path of 'contract unit rates first, negotiated rate build-up as fallback': (1) list and measure per the contract-agreed measurement and pricing rules, and price by combining contract unit rates and tender price levels; (2) where no applicable unit rate exists, the employer and contractor renegotiate the measurement and pricing rules. Conversion of contract unit rates must consider four factor groups: labour/material/machinery price differences, bulk-procurement effects, correction of under/over-priced items, and differences between competition-formed and negotiated rates; before implementation, submit the quotation for review and sign a supplementary agreement before proceeding; further variations to additional works are priced per Section 8.9, and Clauses 8.2.2/8.2.3 (BOQ errors/omissions) should not apply. Construction cost expert assessment (judicial appraisal) position: works outside the contract are not necessarily bound by the original contract; the contractor bears the burden of proof.
- ←
Choice criteria for re-measurable / lump-sum / cost-plus contracts under GB/T 50500-2024, the coverage of lump sums, and the precedence between contract drawings and the BOQ on inconsistency (Articles 3.4.2, 3.4.6)
Per GB/T 50500-2024 Article 3.4.2, the employer chooses the pricing mode per the design depth of tender drawings, technical difficulty, scale, implementation plan, BOQ compilation time and pricing risk: works with clear requirements, controllable measurement and pricing and low fluctuation risk suit lump-sum contracts; unclear requirements, high difficulty and many uncontrollables suit re-measurable (unit-rate) contracts; particularly urgent or complex, high-risk works suit cost-plus. Article 3.4.6: the lump sum covers all costs of completing the contract works per the drawings and specification under the tender documents; the priced BOQ merely reflects the price build-up, BOQ-defect prices deemed included, its unit rates usable for pricing variations and additional works, provisional-quantity items priced under re-measurable rules; on inconsistency during performance, the re-measurable contract follows the BOQ, the lump-sum contract the drawings and specification.
- ←
Double-counting test for BOQ items of anti-corrosion coating and fireproofing coating in steel structures: duplicate item-description wording is not double counting; the test is whether both point to the same coating operation / the same coat
Repetition of item-description wording is not in itself double counting - anti-corrosion paint and fireproofing coating are brushed onto the same member surfaces, so similar descriptions are normal. The test is whether the two point to the same coating operation / the same coat: coats in different systems (primer / intermediate coat / topcoat vs fireproofing coating) are independent items settled as executed; only where the same operation is described in two line items, or where one line item's quota work content already covers the other's operation (e.g. a fireproofing coating item whose work content already includes surface rust removal and primer), is the duplicated portion disallowed. Basis: GB/T 50854-2024 Appendix F.10.11 and GB 50205-2020 Appendix J.0.4 (two independent measurement bases), and GB/T 50854-2024 Article 4.1.2 (necessary work already included in the work content must not be split out as a separate item).
- ←
Quantity basis for cost estimation when BOQ quantities are overstated: costs follow actual quantities (taken off from the drawings) rather than BOQ quantities, and the effect of overstated BOQ quantities on the contract price (re-measurement and adjustment under re-measurable contracts / no adjustment under lump-sum contracts)
Cost estimation must be based on actual quantities (the drawing-based quantities calculated from the dimensions shown on the design drawings under the measurement rules agreed in the contract), not on the bill of quantities (BOQ) quantities - BOQ quantities are provisional (estimated) figures on the revenue/tendering basis, whereas cost follows actual resource consumption; the two sets of accounts must be kept separately, with the difference carried as a separate quantity variance. This rests on Article 17 of the Cost Management Regulations for State-Owned Enterprises (Guo Fa [1984] No. 34) - costs must be accounted for from actual consumption and actual prices, and enterprises must not substitute planned cost, estimated cost or norm-based cost for actual cost - and on Article 4.1.5 of GB/T 50500-2024, under which quantities of work-item BOQ entries under a re-measurable (unit-rate) contract are provisional quantities to be determined by re-measurement. The effect of overstated BOQ quantities on revenue depends on the contract type: under a re-measurable (unit-rate) contract the works are re-measured against the actual construction drawings, so the inflated portion earns no payment (it is an error in the BOQ, rectified and repriced under Articles 7.2.1 and 8.2.1, with 15% as the threshold); under a lump-sum contract the work-item BOQ need not be re-measured and BOQ errors are not adjusted (Articles 7.2.2, 4.1.6 and 8.2.3), so an overstated BOQ quantity against less work actually done yields a quantity variance gain. The only opening is BOQ entries whose item description states a provisional quantity: under both contract types they are re-measured and adjusted under the re-measurable-contract rules.
- ←
May quantities cut by design variation be listed as negative BOQ items: the contract BOQ itself never goes negative - increases and decreases fall to the "variation increase-and-decrease price" item at final account; under lump-sum (fixed-price) contracts BOQ defects do not adjust, only differences between as-built and contract drawings form priceable variations (GB/T 50500-2024)
Quantity cuts from design variations must never be written as negative quantities in the original contract BOQ - BOQ quantities compute on design-shown dimensions and, under lump-sum contracts, divisional BOQ quantities need no re-measurement (clause 7.2.2); the cuts land at the settlement adjustment layer, item 9 of GB/T 50500-2024 clause 10.3.2, "variation increase-and-decrease price" (which may be negative), the contract-BOQ-total line standing unchanged. Under lump-sum contracts only the difference between as-built and contract drawings constitutes a priceable variation (clause 7.4.3); contract-drawing versus contract-BOQ differences are BOQ defects and never adjust (7.4.2, 8.2.3). Variation pricing splits on whether contract rates apply: applying, adjust under 8.9.1 (quantity change within 15%, inclusive) or 8.9.2 (over 15%, exclusive - cuts reasonably raise rates); not applying, the parties negotiate the all-in rates (8.9.3).
- ←
Deciding the pricing type of a contract silent on its price form (colloquially the "fully open contract") and the corresponding scope of quantity and price review
"Fully open contract" is not a legal concept; at normative level only fixed price / adjustable price / cost-plus-fee (Order No. 107 of the Ministry of Construction, Article 12) or unit-rate contract / lump-sum contract / cost-plus-fee contract (GB/T 50500-2024 clauses 2.0.6 to 2.0.8) exist. Where the contract is silent on its price form, classify by pricing mechanism (the basis on which the contract price forms, who answers for quantities, whether drawings or the BOQ prevail in conflict) - never by the contract's name alone. Classified as a re-measurable (unit-rate) contract, quantities are re-verified as executed and all-in unit rates stay fixed within the agreed risk band; classified as a lump-sum contract, only adjustable content and out-of-band risk factors adjust on top of the lump sum and, absent special agreement, re-measurement is inappropriate.
- ←
Reviewing tender bills of quantities: methods and criteria for detecting omissions, errors, and duplications
Check the BOQ against four baselines—tender documents, construction drawings, measurement standards, and the pricing standard: omissions via drawing cross-check + standard appendix tick-off + item description derivation + preliminaries check; errors via codes (twelve digits, no duplicate codes within one project), item descriptions (standard, concise, accurate, complete), units and quantities, and work-content attribution (operations must not be split); duplications via duplicate codes, substantively identical items, split-out operations, and overlaps between work items and preliminaries. Per GB/T 50500-2024 Article 4.1.4: BOQ defects are borne by the employer under unit-rate contracts (adjusted per Section 8.2) and by the contractor under lump-sum contracts (not adjusted per Article 6.1.7).
- ←
Overview of bills of quantities: composition, compilation, item descriptions and handling of errors/omissions (GB/T 50500-2024)
A bill of quantities comprises four sections — trade items, preliminaries, other items and VAT; the five BOQ elements (code/name/item description/unit of measurement/quantity) are compiled per the national and industry measurement standards. Division of responsibility: under unit-rate contracts the trade-items BOQ is the employer's responsibility, under lump-sum contracts the contractor's, and the bill of preliminaries is always the contractor's. BOQ defects are per definition 2.0.27; unit-rate contracts re-measure under section 8.2 with price adjustment at the 15% boundary; lump-sum contracts are generally not adjusted except provisional-quantity items.
- ←
Checking drawing-BOQ contradictions (bill of quantities defects) before bid pricing, and responsibility boundaries (GB/T 50500-2024)
Drawing-BOQ contradictions are "BOQ defects" (extra items/omissions/mismatched characteristics/quantity deviations, Article 2.0.27). Responsibility by pricing mode: unit-rate contracts—work-item BOQ by the tenderer (Article 6.1.6, defects adjusted at settlement per Section 8.2); lump-sum contracts—by the bidder (Article 6.1.7, may supplement the priced BOQ and bears the difference); preliminaries always the bidder's (Article 6.1.5); per-item pricing is lump sum, unadjusted at settlement (Article 6.2.3). Check by risk order: item characteristics, quantities, completeness of items, units and measurement rules, work-content interfaces, drawing versions, preliminaries, provisional sums.
- ←
Grounds for reducing over-graded quota items in decoration works: plaster grade determination (GB 50210-2018 4.1.1/4.2.5), repricing for errors and omissions in the BOQ (GB/T 50500-2024 8.2.1/8.9.1), and construction cost expert assessment (judicial appraisal) basis (T/ZBD 100.4-2023 4.4.4)
Core grounds for reducing over-graded quota items in decoration works: quota line items must match actual work, judged by the 'three-way comparison' (actual work vs quota line item work content vs chapter notes/calculation rules). Grade determination rests directly on GB 50210-2018 4.1.1 — 'general plastering works are divided into ordinary plastering and high-grade plastering; where the design has no requirement, acceptance is as ordinary plastering' — applying a high-grade quota line item where the design states no grade constitutes over-grading; the surface-quality provisions in 4.2.5 provide counter-evidence on whether actual work meets high-grade standards. Under BOQ-based pricing, per GB/T 50500-2024 8.2.1, item description (work item specification) mismatches are characterised as errors and omissions in the BOQ and re-measured, with all-in unit rates adjusted at the 15% boundary per 8.9.1; the construction cost expert assessment (judicial appraisal) basis is in T/ZBD 100.4-2023 4.4.4. Reductions take the form of price-difference reductions and corresponding downward adjustments to the fees charged on the work-item base.
- ←
Adjustment of the contract price (GB/T 50500-2024 Chapter 8): eleven triggering events, mechanism by section, and FIDIC mapping
Adjustment of the contract price is the mechanism for changing the contract price during performance. GB/T 50500-2024 Cl. 8.1.1 lists eleven triggering events: BOQ errors, provisional sums, PC sums (provisional estimates), contractor's services, dayworks, changes in costs, changes in laws and policies, variations, additional works, claims, and other events agreed by the parties; the procedure runs submit, check, re-check, review and confirm (8.1.2). Key mechanics: BOQ errors and variations share one re-rating ladder (identical items at contract rates; analogous items converted; different items negotiated), with a 15% quantity boundary for re-rating (8.2/8.9); provisional sums are controlled by the employer and any unused balance reverts at final account (8.3); PC-sum items are replaced by tender prices — materials pre-VAT, specialist works VAT-inclusive (8.4); dayworks are measured under 7.5 (certified dayworks records) and priced at the BOQ daywork rates (8.6, with deemed approval if verification is overdue, 7.5.5); changes in costs are adjusted beyond the agreed band — 5% by default — by index-based (formula) adjustment or adjustment based on published price information (8.7 + Annex A), the differential carrying VAT only; changes in laws pivot on the base date, adjusting price and/or time for enactments, amendments, repeals or new interpretations after it, with no upward adjustment during contractor-caused delay (8.8); additional works may follow contract rates or freshly negotiated rules under a supplementary agreement (8.10); claims cover events outside 8.2-8.10 — compensatory, not punitive, and mutual, with profit added for eight categories of employer-risk events (8.11). FIDIC counterparts sit scattered across Clause 13 (variation valuation 13.3, provisional sums 13.4, changes in laws 13.6, changes in cost 13.7 — 2017 numbering) and Clause 20 claims (28-day hard time bar): adjacent institutions, not chapter-for-chapter equivalents.
- ←
Measurement units for landscape plant installation (plant/m/m2/clump), plant specification terminology, and item-characteristic description essentials (GB/T 50858-2024)
Plant installation measurement units are fixed by category and planting method, not self-invented: trees/single-shrub/scattered bamboo/palms/climbers by plant (count), massed shrubs/flower ground-cover by m2, hedges by m (hedge length, not plant count), clumping bamboo/single-clump aquatics by clump (GB/T 50858-2024 Appendix A Table A.3.1, 4.2.5). Plant specification terms have unified definitions: DBH = trunk diameter at 1.3 m above ground (landscape caliber, not highway 1.2 m); crown diameter = mean of max and min vertical-projection diameters; ground diameter at 0.1 m; trunk diameter at 0.3 m; meter diameter at 1.0 m; plant height = ground to top. Item characteristics must be standard, concise, accurate, complete (4.1.2); survival rates above CJJ 82, shaping requirements, and grass-brick inlay ratios must be stated in characteristics.
- ←
Four-tier progressive identification of high-risk bid-pricing clauses in tender documents (rejection clauses -> substantive requirements -> price locking -> performance funding)
Read tender documents as risk-allocation contracts: (1) rejection clauses (the seven statutory grounds of Implementation Regulations Article 51 as baseline, sector measures expand with catch-all clauses; below-cost is the hidden trap); (2) substantive requirement clauses ("must/shall/shall not" wording + deviation tables—non-response is statutory rejection); (3) price-locking clauses (GB/T 50500-2024: risk-scope clarification, three elements of price adjustment, lump-sum by total, lump-sum per item, preliminaries responsibility, unbalanced bidding); (4) performance funding clauses (Article 3.4.8 14-item checklist, performance deposit <=10%, seven quality-reserve agreements).
- ←
Determining quantities where drawing dimensions are incomplete: three-tier fallback plus provisional quantities at the tender/preparation stage; re-measurement plus five-tier progressive determination at the settlement stage
Where drawings are incomplete, quantities are determined along two tracks. At the preparation stage, values are taken by the three-tier fallback "design documents -> approved project execution plan (construction methodology and site organization) -> code/quota norm measurement rules"; where accurate measurement remains impossible, the item description (work item specification) notes "provisional quantities" and an estimated quantity is provided (GB/T 50500-2024 clauses 4.1.4, 4.1.6). At the settlement/dispute stage, re-measurable (unit-rate) contracts are re-measured against the final construction drawings (not the as-built drawings); where the drawings cannot reflect the work, determination follows the five-tier progression from certification and sign-off to site inspection (T/ZBD 100.4-2023 clauses 4.3.5, 4.3.6).
- ←
Avoiding mispricing when material names are similar but specifications differ: three lines of specification-checking defense across preparation, pricing, and audit
The three forms of mispricing (specifications missing from item characteristics, near-name mismatches, missing specification/unit dimensions) can be intercepted by three lines of defense: at preparation, write full specifications and models into the item characteristics (GB/T 50500-2024 Clause 4.2.2); at pricing, check the quota item's bracketed specification against the drawings + match material price on three fields simultaneously — name/specification/unit (do not pick the published price directly; mark conversions with "换"); at audit, use same-name specification gradients (C30>C25, DN32>DN25) to back-detect mismatches.
- ←
Risk allocation and adjustment rules for preliminaries (measure) costs: GB 50500-2013 vs GB/T 50500-2024 (omitted items, scheme changes, lump sum plus exceptions)
The 2024 edition restructures preliminaries as "lump sum plus exceptions": completeness/accuracy of the preliminaries list is the contractor's responsibility under both unit-price and lump-sum contracts (3.1.8); omitted items are no longer adjustable except the safety-measures cost and formwork/temporary works listed in the work-item list (8.2.2/8.2.3), whereas under 2013 list omissions were the tenderer's liability (4.1.2, mandatory) and missing preliminaries could be added via an approved scheme (9.5.3). "All preliminaries risk on the contractor" is inaccurate - exceptions like variations, unforeseen provisional-sum works, and employer causes still cost the employer (3.3.7), but only via "submit scheme before execution + mutual confirmation" (8.9.6/8.9.7), failing which the right is forfeited.
- ←
GB/T 50500-2024 list of measurement and pricing risk allocation: Clause 3.3.2 seven employer-borne risks, Clause 3.3.3 eight items for the contractor's tender, and the Clause 6.1.8 tender link
Under GB/T 50500-2024, Clause 3.3.2 lists 7 employer-borne risks (errors and omissions in the BOQ of a re-measurable contract, errors in the employer's original data and datum, approved variations, directed acceleration/early completion/suspension or slowing of the works, changes in laws, regulations and policies, cost fluctuation beyond the agreed range, others), which the contractor's tender need not consider; Clause 3.3.3 lists 8 items the contractor shall consider in its tender (accuracy and completeness of the bill of preliminaries, errors and omissions in the BOQ of a lump-sum contract, the cost of completing all work per the contract drawings, specifications and measurement standards, changes to the contractor's own scheme, causes attributable to the contractor's own plant, technique or management, the contractor's own acceleration or suspension, cost fluctuation within the agreed band, others). The contractor bears its own technical and management risks (e.g. management fees) and a certain market risk, but not the risk of changes in laws, regulations and policies; the tender price shall include the risk costs within the agreed ranges (6.1.8), and where the tender documents are silent, bidders shall seek written clarification from the employer within the prescribed time.
- ←
Item description vs method of measurement in the BOQ: the item description column must not stipulate the method of measurement; supplementary rules belong in the BOQ calculation-rules statement and apply as contractual agreement
Item description and method of measurement are two parallel, independent elements of the bill of quantities (BOQ): the item description must be drafted in accordance with the annexes to the measurement standard and the actual works, its function being to fix the all-in unit rate; quantities must be computed under the method of measurement prescribed in the annexes (mandatory provisions of codes) — the item description column must not stipulate the method of measurement. Where supplementary rules are genuinely required, they must be set out in the BOQ calculation-rules statement (naming the national and industry standards adopted, with their titles and numbers, or setting out the detailed supplementary rules) and made part of the tender documents/contract documents, applying as "contractual agreement". Hierarchy of measurement bases: contractual agreement -> national standard matching the contract type -> industry/local standard.
- ←
Framework for distinguishing quantity risk from price risk in contracts: risk objects, responsible parties, and quantified trigger lines (GB/T 50500-2024)
Quantity risk governs "how much is built" (BOQ defects, quantity changes and item additions/deletions from changes); price risk governs "how much per unit" (input prices and all-in unit-rate levels). On allocation, Article 3.3.2 lists owner risks (unit-rate BOQ defects, erroneous source data, approved changes, legislative changes, beyond-band fluctuations); Article 3.3.3 lists contractor risks (preliminaries lists, total-price BOQ defects, own technical/management risks, within-band fluctuations). Quantified triggers: quantity change 15% (8.9.1/8.9.2); price fluctuation 5% or the contract-agreed band (8.7.2/8.7.6).
- ←
Methods and liability basis for ensuring completeness of the bill of preliminaries at construction main (general) contracting tender stage (GB/T 50500-2024)
Per GB/T 50500-2024 clause 6.1.5, whether a re-measurable (unit-rate) or lump-sum contract is used, the completeness and accuracy of the bill of preliminaries are the bidder's (contractor's) responsibility, and the bidder bears the risk of the reasonableness of its tender price; preliminary items not priced as required may be deemed included in the all-in unit rates, totals and tender total of other billed (BOQ) items, with no re-pricing or adjustment at construction payment settlement (3.5.4). The contractor should guard against omissions via the six-category 'including but not limited to' framework in 3.2.6 + three cross-checks (bill of preliminaries vs project execution plan (construction methodology and site organization)/tender documents/similar projects) + site inspection + written clarification; statutory safety provisions are non-competitive (3.2.5) and must not be omitted or priced at zero.
- ←
BOQ item selection for cast-in-place concrete drainage ditches: structures channel (trough) 070109 vs structures pool 070101 vs building floor trench 010507003
A drainage ditch is a long, linear water-carrying structure — first exclude "structures pool" (070101 suits integral enclosed-wall structures like storage/water tanks and septic tanks); then choose by independence from buildings: an independent external channel (plant/site) -> GB/T 50860-2024 Appendix A.9 channel (trough) 070109 (subdivided into base slab / slab rebar / slab formwork); an internal or attached floor trench (workshop cable trench / equipment trench) -> GB 50854-2013 Table E.7 "cable trench, floor trench" 010507003 (measured in m by centerline length). Basis: the structures standard's note "channel (trough) means a channel or trough independent of and external to buildings".
- ←
Can a practice omitted from the BOQ (missing item) but mandatorily required by codes be deducted at the final account? - the judgment chain of contract type x pricing classification (GB/T 50500-2024) and the judicial approach to missing-item risk
A practice omitted from the BOQ but mandatorily required by codes is not automatically deductible: under a unit-rate contract the completeness of the divisional-item BOQ is the client's responsibility (GB/T 50500-2024 Clauses 3.1.8, 6.1.6) - a genuine omission already constructed is adjusted as a BOQ defect under 8.2.1 and repriced per 8.9.1 at up to the 15% boundary; under a lump-sum contract the priced divisional-item BOQ is the contractor's responsibility and, in principle, the contract price is not adjusted for BOQ defects (6.1.7, 8.2.3); practices that are per-item measures items, or already contained in the work content of BOQ items such as doors/windows and curtain walls, are deductible (3.1.8, 6.1.5, 8.2.2); where the contractor failed to perform a mandatory obligation, rectification comes first (at its own cost) and deduction at the final account is well-founded (10.3.13). Judicially, where missing items exceed a reasonable range and both parties are at fault, the loss may be apportioned per fault and the principle of good faith.
- ←
No price adjustment for BOQ defects in lump-sum contracts (BOQ quantities below drawings): the four-layer rule of GB/T 50500-2024 and the reversal of the 2013 edition's Clause 8.3.1 measure-and-value rule
Under GB/T 50500-2024 (effective 2025-09-01; GB 50500-2013 simultaneously repealed), BOQ quantities in lump-sum contracts below the drawings constitute a "BOQ defect" and are not adjusted during performance: 2.0.7 bars using changes in BOQ items/quantities as an adjustment basis; 3.4.6 deems defect prices included in the lump sum with contract drawings and specifications governing; 4.1.6 disallows adjustment for defect-induced price changes; 7.2.2 allows no re-measurement of the BOQ; 7.4.1 defines drawing-vs-BOQ differences as defects not adjustable. The 2013 Clause 8.3.1 (an ordinary clause, not among that edition's 15 mandatory ones) allowing measure-and-value for BOQ-tendered lump-sum contracts has been deleted and reversed. Only two openings remain: (1) items marked "provisional quantities" re-measured per unit-price rules (4.1.6, 7.2.2 item 2); (2) differences between contract drawings and as-built drawings are variations measured under 7.4.3 (7.2.2 item 3) - unchanged drawings with undercounted BOQs are no variation.
- ←
GB/T 50500-2024, China's BOQ pricing standard: positioning, 2024-vs-2013 changes, chapter map and card-group navigation
GB/T 50500-2024, the China national pricing standard for BOQ-based pricing (MOHURD Announcement No. 212 of 2024, approved 26 November 2024), came into force on 1 September 2025 and repealed GB 50500-2013. Its status shifted from a partly mandatory code to a recommended national standard (GB to GB/T), aiming to regularise pricing rules and let the market form construction costs. It governs pricing activity in tendering, contracting and execution for construction works; EPC and other general-contracting models apply it by reference, and the requirement that state-funded projects use BOQ pricing is carried by a MOHURD ministerial order. Nine headline revisions (per the foreword): risk scope and allocation rules by contract form; a new bid clarification mechanism; revised pricing of preliminaries; the 'contract price agreement' chapter replaced by contract selection and requirements; revised measurement and adjustment rules; site visas abolished and additional-works pricing introduced; interim settlement by construction stage added; dispute resolution revised; the cost-expert-assessment chapter deleted. The structure was rebuilt from 16 chapters into 12 chapters plus annexes: 'tender control price' renamed tender price ceiling; completion settlement and contract-termination settlement merged into 'works settlement and payment' (absorbing stage settlement); dispute resolution and expert assessment merged; pricing tables moved to annexes (with a new Annex G, schedule of price-adjustable key materials).
- ←
A seven-step process for systematically checking BOQ errors and omissions (BOQ defects) and defect-liability handling
With tender drawings, the calculation-standard appendices, and the tender documents as three benchmarks, check in seven steps: "procedure check -> five-element verification -> item completeness -> preliminary items -> other items -> data format -> check records": prevent omissions using drawing back-check + construction-process walk-through + appendix comparison; any item listed without a drawing basis is a surplus item. After finding defects: clarify and correct via tender query and clarification at the compilation stage; under re-measurable (unit-rate) contracts the employer bears liability and adjusts per GB/T 50500-2024 Section 8.2; under lump-sum contracts the contractor bears liability and no adjustment is made.