Risk allocation for incomplete item descriptions in the BOQ (BOQ errors and omissions): employer responsible under re-measurable (unit-rate) contracts, contractor responsible under lump-sum contracts, contractor always responsible for the bill of preliminaries

Per GB/T 50500—2024, an incomplete item description is an "error or omission in the BOQ": under re-measurable (unit-rate) contracts the employer (tenderee) is responsible for the completeness of billed items, the accuracy of item descriptions and the accuracy of quantities, and at settlement the all-in unit rate is re-rated on the basis of the characteristics actually constructed to adjust the contract price; under lump-sum contracts the contractor is responsible and no adjustment is made except for provisional quantities; for the bill of preliminaries, the contractor is responsible under both re-measurable and lump-sum contracts.

Applicable Codes

  • GB/T 50500—2024 第 3.1.8、6.1.6、8.2.1、8.9.1、8.9.2、3.3.3 条
  • GB 50500—2013 第 4.1.2、9.5.1 条
  • 《建设工程造价鉴定作业指引》T/ZBD 100.4—2023 第 4.4.4 条

Topic Positioning

This card answers "when item descriptions in the BOQ are incomplete (errors and omissions in the BOQ), who bears the tender-pricing and settlement risk" — setting out the allocation of responsibility and the price adjustment rules under GB/T 50500—2024, for quick reference in tender review and in assessing settlement disputes.

Core Conclusions

  • Re-measurable (unit-rate) contracts (the mainstream in tendering): completeness of billed items, accuracy of item descriptions and accuracy of quantities are the employer's (tenderee's) responsibility; contract price adjustments arising from errors or omissions follow Section 8.2, and at settlement the all-in unit rate is re-rated on the basis of the characteristics actually constructed and the contract price is adjusted.
  • Lump-sum contracts: completeness and accuracy of the BOQ are the contractor's responsibility; except for "provisional quantities" items, the contract price is not adjusted for errors or omissions in the BOQ.
  • Bill of preliminaries: regardless of whether the contract is re-measurable or lump-sum, its completeness and accuracy are always the contractor's responsibility.
  • Bidders must review the billed items and raise doubts in writing for clarification, but whether or not doubts are raised, completeness and accuracy of the BOQ remain the tenderee's responsibility.
  • Adjustment sequence for errors or omissions under re-measurable contracts (8.9.1/8.9.2): for item additions/deletions or quantity changes ≤15%, prefer the contract unit rate → conversion by analogy to similar items → negotiated rate build-up; for the portion beyond 15%, the unit rate is reasonably reduced for added items and reasonably increased for deleted items.
  • The contractor bears its own technical and management risks and market risks within the agreed range (3.3.3), and may not mix these into claims based on "incomplete item descriptions".

Applicable Boundaries

Applies to tendering and awarding activities using pricing on a bill of quantities basis where the contract was signed after 2025-09-01 (the implementation date of GB/T 50500—2024); earlier projects follow GB 50500—2013, with the same conclusions (old Clauses 4.1.2, 9.5.1). Exceptions: errors or omissions in the bill of preliminaries, portions under lump-sum contracts already supplemented and priced by the bidder, and risks borne by the contractor itself — no adjustment for BOQ errors or omissions may be claimed for these.

Further Reading

See GB/T 50500—2024 Clause 3.1.8 (division of responsibility for BOQ completeness), Clause 6.1.6 (tender review and clarification), Clause 8.2.1 (adjustment for errors or omissions under re-measurable contracts), Clauses 8.9.1–8.9.2 (adjustment methods and the 15% deviation rule), Clause 3.3.3 (contractor's own risks); old/new comparison with GB 50500—2013 Clauses 4.1.2 and 9.5.1; for construction cost expert assessment (judicial appraisal) practice see Guideline for Construction Cost Expert Assessment T/ZBD 100.4—2023, Clause 4.4.4, Item 3.

Keywords

Cited By