Measurement units for landscape plant installation (plant/m/m2/clump), plant specification terminology, and item-characteristic description essentials (GB/T 50858-2024)

Plant installation measurement units are fixed by category and planting method, not self-invented: trees/single-shrub/scattered bamboo/palms/climbers by plant (count), massed shrubs/flower ground-cover by m2, hedges by m (hedge length, not plant count), clumping bamboo/single-clump aquatics by clump (GB/T 50858-2024 Appendix A Table A.3.1, 4.2.5). Plant specification terms have unified definitions: DBH = trunk diameter at 1.3 m above ground (landscape caliber, not highway 1.2 m); crown diameter = mean of max and min vertical-projection diameters; ground diameter at 0.1 m; trunk diameter at 0.3 m; meter diameter at 1.0 m; plant height = ground to top. Item characteristics must be standard, concise, accurate, complete (4.1.2); survival rates above CJJ 82, shaping requirements, and grass-brick inlay ratios must be stated in characteristics.

Applicable Codes

  • GB/T 50858-2024 · Standard for Measurement of Quantities of Landscape and Greening Works
  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works
  • CJJ 82 · Code for Construction and Acceptance of Landscape and Greening Works

Topic Positioning

Measurement-unit selection, plant specification terminology, and item-characteristic description essentials for landscape planting BOQs — answering "are plants measured by count or by meters" and "how to write DBH, crown spread, and height into characteristics without settlement disputes". Based on the current GB/T 50858-2024 "Standard for measurement of landscape works" (replacing the 2013 edition).

Core Conclusions

  1. Measurement units are fixed by plant category and planting method (Appendix A Table A.3.1 planting, code 050103); BOQ units must not be self-invented — 4.2.5: "BOQ measurement units shall be determined per the units specified in Appendices A-C of this standard." Items:
  • Tree planting (050103001) by plant, characteristics: species; DBH/trunk diameter/meter diameter/ground diameter; height; crown diameter;
  • Single-shrub planting (050103002) by plant: species; height; crown diameter;
  • Massed shrubs (050103003) by m2: species; height; crown diameter; plants per unit area;
  • Hedge planting (050103004) by m: species; height; crown diameter; single/double row, plants per unit length per single/double row — measured in m is the design hedge length, not plant count; to price by plant, use the "single-shrub planting" item instead; the two differ in work content and must not be mixed;
  • Scattered bamboo (050103005) by plant (species; DBH); clumping bamboo (050103006) by clump (species; root-ball clump diameter);
  • Palm planting (050103007) by plant (species; height; ground diameter);
  • Climber planting (050103008) by plant (species; ground diameter/main stem (vine) length/main vine diameter);
  • Flower/ground-cover planting (050103009) by m2 (species; height/crown diameter; plants per unit area);
  • Single-stalk aquatic planting (050103010) by plant, single-clump aquatic (050103011) by clump.
  1. Plant specification terms must follow the standard definitions (Table A.1.1 note 1 — the measurement basis for acceptance and settlement): DBH is the trunk diameter 1.3 m above ground; crown diameter (spread) is the mean of the maximum and minimum diameters of the crown's vertical projection; ground diameter at 0.1 m above ground; trunk diameter at 0.3 m; meter diameter at 1.0 m; plant height from ground surface to plant top. Note: landscape DBH is at 1.3 m — do not mix with the highway caliber of 1.2 m; whichever caliber is written in characteristics is where the field measurement is taken.

  2. Item characteristic requirements (4.1.2): describe in a "standard, concise, accurate, complete" manner sufficient to determine all-in unit rates; appendix work contents list only principal construction content — auxiliary content such as machinery moves and material transport, though unlisted, is included, and processes shall not be split into separate items unless specially noted. For plants: write the Chinese plant name with deciduous/evergreen noted and container/bare-root/balled (ball diameter is the key pricing quantity); list specifications fully per the table above — density characteristics (plants per unit area for massed shrubs/flowers; plants per unit length for hedges) are decisive for m2/m-priced unit prices and must be written; prefer ranges (e.g., "DBH 8-10 cm") over single values, aligning with quota steps and reducing "does it include a given size" disputes.

  3. Boundary provisions of Table A.3.1 notes: planting work content includes on-site plant transport, digging pits/trenches, base fertilizing, setting upright and backfilling, tamping, watering basins, mulching for moisture, shaping, and waste clearing/hauling; construction-period maintenance runs from planting to completion acceptance; rooting agent and branch disinfection costs are included in the corresponding planting items; facility-greening irrigation systems are coded separately under A.4 green-space irrigation; where the employer's survival-rate requirement exceeds the industry standard CJJ 82 "Code for construction and acceptance of landscape works", it must be described in characteristics; where the employer has shaping requirements, describe them; when computing area-based quantities, single tree (pit) holes and manhole covers within 0.5 m2 each are not deducted.

Applicable Boundaries

  • Applies to the GB/T 50858-2024 caliber (2024 replaced 2013); legacy projects follow the contracted edition.
  • Units and characteristics follow Appendix A Table A.3.1; green-site preparation (Table A.1.1), irrigation systems (A.4) have their own rules — do not apply this card's planting rules to them.
  • BOQ defect liability and settlement adjustments follow GB/T 50500-2024: unit-price contract defects borne by the employer (Section 8.2), lump-sum by the contractor (4.1.4); all-in unit rates after characteristic/condition changes adjust in three tiers per 8.9.1 (retain for identical, convert for similar, negotiate for different).
  • This card covers only planting measurement and characteristics; quota steps and survival acceptance standards (CJJ 82) require the companion quota and acceptance code.

Further Reading

  • GB/T 50858-2024 Appendix A Table A.3.1 planting (code 050103) with notes 1-8, Table A.1.1 note 1 (specification definitions), 4.1.2 (characteristics), 4.2.5 (units).
  • Settlement linkage: GB/T 50500-2024, 4.1.4 (defect liability), 8.2.1 (price adjustment for defects), 8.9.1 (variation all-in unit rates).
  • Survival and acceptance: CJJ 82 "Code for construction and acceptance of landscape works".