Overview of quantity take-off for construction works: basis, general rules and per-trade calculation methods
Quantity take-off rests on the four-tier basis "contract agreement -> design drawings -> approved project execution plan (construction methodology and site organization) -> appendix rules of the quota norms/measurement standards"; except where rules provide otherwise, all quantities are computed from the dimensions shown on the design drawings. General rules include: calculation per appendix rules (mandatory provisions of codes); the no-deduction threshold of single holes <=0.3 m2; significant figures of units of measurement (t/km three decimals; m/m2/m3/kg two; counts integer); and dual-track BOQ vs quota-norm quantities. Earthwork, concrete, reinforcement, formwork, masonry, waterproofing, finishes etc. each have standard algorithms.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准
- GB 50861-2013 城市轨道交通工程工程量计算规范
- GB 50860-2013 构筑物工程工程量计算规范
- GB/T 50326-2017 建设工程项目管理规范
- GB/T 51095-2015 建设工程造价咨询规范
- T/ZBD 100.4-2023 建设工程造价鉴定作业指引
Topic Positioning
The master card of quantity take-off (measurement of the works) for construction projects: answering "on what basis, under which general rules, and how each main trade is computed", stringing the calculation rules scattered across specialty codes into one map — for framework self-checks before preparing budgets/bills of quantities, settlement reviews and construction cost expert assessment (judicial appraisal).
Core Conclusions
Four-tier basis: (1) contract agreement (version of calculation rules, measurement method takes precedence) -> (2) design drawings (construction drawings at preparation stage; as-built drawings + variations + site instructions/variation records at settlement stage) -> (3) approved project execution plan (construction methodology and site organization) (where the drawings are silent) -> (4) appendix rules of the quota norms/measurement standards (the rules are the "yardstick", the drawings the "numbers"); site actuals count only once documented through site instructions/variation records or measurement sheets. Five general rules: except where the rules provide otherwise, the dimensions shown on the design drawings govern; BOQ quantities must be computed per the calculation rules set out in the appendices (mandatory provisions of codes); a unified deduction threshold — single openings with an area <=0.3 m2 are not deducted, those >0.3 m2 are deducted, hole reveals are not added, and the sides of wall-attached columns/beams/pilasters are merged; measurement precision — t and km to three decimal places, m, m2, m3, kg to two, pieces/items/roots/groups/systems as integers; BOQ versus quota-norm dual track — BOQ quantities per net dimensions, without conversion for density and excluding non-design laps and measure reinforcement, while quota-norm quantities are calculated separately under consumption quota (resource norm) rules (e.g. reinforcement other than φ10 counts one lap per 9 m) — never mix the two. Per-trade essentials: earthwork by natural in-situ (undisturbed) volume, with BOQ quantities not converted (rate build-up/haulage per conversion factors), plus working space + sloping + trench/pit determination; concrete by solid volume without deducting reinforcement, iron inserts or bolts; formwork by contact area; reinforcement = shown centerline length x theoretical mass; masonry by volume deducting door/window openings and embedded members; waterproofing by area — coving <=300 mm merged into the horizontal, >300 mm as vertical; finishes by net area under the deduction/merger rules.
Applicable Boundaries
Applies at the general level across building, municipal, rail and installation specialties; specialty-specific rules (e.g. hydraulic formwork by form-face projected area; bridge/tunnel dedicated calibers) must be referred back to the respective specialty codes/quota norms. On rule-version conflicts, handle in the order contract agreement -> national standard consistent with the contract category -> industry/local standard (for the construction cost expert assessment basis see T/ZBD 100.4-2023); the 2024 measurement standards (GB/T 50854/50857/50860/50861/50856) coexist with the 2013 calculation codes — confirm the version before use.
Further Reading
Definition of measurement of the works: GB 50860-2013 clause 2.0.1; measurement precision and mandatory provisions of codes for BOQ rules: GB 50861-2013 clauses 3.0.4, 4.2.5; preparation of the bill of quantities and contractual measurement of the works: GB/T 50500-2024 chapters 3, 4, 7; basis for settlement: GB/T 50326-2017 clause 18.3.3, GB/T 51095-2015 clause 8.2.4; rule-version disputes: T/ZBD 100.4-2023 clauses 4.3.1, 4.3.2.
Keywords
- quantity take-off (measurement)
- measurement of the works
- method of measurement
- 工程量计算依据
- 清单工程量
- 定额工程量
- 设计图示尺寸
- 计量单位有效位数
Related Cards
- →
Rebar quantity calculation: length x theoretical weight, lap/merge/deduction rules, and post-tensioning length adjustments
Rebar quantity = design-drawn rebar length (centerline length) x unit theoretical weight (t). The BOQ caliber counts only laps specified by design and codes, not construction laps; the quota caliber, where drawings/codes do not specify, counts one lap per 12 m for diameters up to 10 mm and per 9 m above 10 mm, with mechanical connections not counted separately. Post-tensioned prestressed rebar lengths are adjusted by reserved duct length and anchorage type. Embedded iron parts are measured by ton, rebar splices by number, post-installed rebar by piece.
- →
Preventing double counting of decoration quantities: deduction and inclusion rules for floors, wall/column faces, and ceilings
In decoration quantity takeoff, first draw the interfaces, then apply the "deduct/include" rules so each surface is computed on its own: openings are uniformly deducted at the single-opening 0.30 m2 threshold; the side faces of door/window openings are not added; the side faces of attached columns/beams/piers are merged into the wall face; for beamed ceilings the beam sides merge into the ceiling; plaster on the soffit of slab staircases at horizontal projection x 1.15, zigzag x 1.37; ceiling furring by the clear area between main walls, the finish layer by the room net area minus freestanding columns — the furring and finish layers differ in caliber and must not be mixed. BOQ caliber per GB/T 50854-2024 Appendices L/M/N; quota caliber per TB/T 10831-2024 Volume 10 Building Works.
- →
Earthwork excavation quantity take-off (measurement): working space width, slope coefficients, and haulage (disposal of surplus excavated material) quantities
Earthwork excavation quantity take-off (measurement) follows the three-level priority "design → project execution plan (construction methodology and site organization) → default values in standard appendix tables"; excavation and haulage are measured in the natural in-situ (undisturbed) volume before excavation, backfill in the as-completed volume; working space widths and slope coefficients are taken from tables by foundation material, soil class, and machine working position, and no slope is calculated where shoring boards are placed; the quantity for disposal of surplus (excavated) material = excavated volume − backfill reuse volume, haulage being measured in the natural-state volume with no additional bulking factor.
- →
Formwork measurement rules: contact-area basis, overlap deduction and the 0.3 m² opening threshold, special algorithms for each element type, and BOQ item characterization
Cast-in-place and precast concrete formwork is measured in m² of contact area between the concrete and the formwork (called formwork erection area in water works), with overlapping parts at connections deducted; openings in walls/slabs >0.3 m² are deducted with their reveals added, ≤0.3 m² not deducted; monolithic stairs by horizontal projected area, small elements by projected area, special-shaped precast elements by volume; precast excludes ground moulds, core moulds for hollow slab beams are included in the item, and non-removable box-girder inner forms add 0.03 m³ per m²; constructional columns count only exposed faces = (column width + toothing width) × height; BOQ characterization adds surface/customization requirements, formwork types are straight/inclined/curved/arched, and aprons/ramps are listed under blinding formwork.
- →
Basic content elements of site instruction / variation record documents: main-text checklist, attachment requirements, and sign-off formalities
Grasp the content of a site instruction / variation record along three dimensions: "main-text elements + supporting attachments + sign-off formalities". DB37/T 5028-2022 Clause 6.3.3 gives the most complete nine-item checklist (cause of the instruction; date of occurrence/completion; submission date; location, dimensions, quantity, and materials, with a logically clear calculation formula; execution basis; brief description of the fact and completion status; explanatory drawings and photos; review opinions of the supervision agency and the construction employer; signatures and seals of the contractor's handling person and project manager). T/CAEC 006-2024 distinguishes the content and attachments of quantity instructions from those of price instructions; a price instruction is valid only after joint sign-off (countersignature) by the construction employer, contractor, and supervision unit. Quantity calculation formulas, correspondence with original vouchers, a complete signature chain, and all three dates present are the gaps most easily attacked in final account review.
- →
Earthwork volume conversion coefficients and spoil haul-off disposal estimation (loose / loose-fill / natural-dense / compacted conversion)
Excavation and haul are measured by the pre-excavation natural in-situ (undisturbed) volume, backfill by the post-backfill volume, and different states are converted by coefficients (natural in-situ (undisturbed) 1.00 <-> loose 1.30 <-> loose fill 1.08 <-> compacted 0.87); total spoil disposal Ve = lambda-c x Vc - lambda-f x Vf (JGJ/T 498-2024), with lambda-c soil 1.30 / rock 1.54 / sand-rock mixture 1.07.
- →
Road structural-layer quantity calculation: BOQ and quota dual calibers, deduction rules, and compacted-volume algorithm
Road structural-layer quantities split into two calibers — BOQ quantities (GB/T 50857-2024 Appendix B) and quota quantities (local consumption quotas, e.g., Shenzhen SJG 181.1-2024) — with different deduction rules that must not be mixed: the BOQ base course is by top surface area without deducting chambers; the surface course deducts no chambers but deducts flat stones when present; the Shenzhen quota base course deducts chambers whose single internal area is > 0.6 m2, and the surface course additionally deducts flat stones, curbs, and edge stones; base-course mixed-material mixing and transport are measured in m3 by compacted volume.
- →
Concrete quantity calculation rules: cast-in-place and precast members measured by volume per design-drawn dimensions
Concrete quantities are calculated by volume (m3) per design-drawn dimensions: for cast-in-place members, the volumes of rebar, steel wire, iron parts, bolts, and reserved grouting ducts are not deducted, and for walls and slabs, holes with individual area <= 0.3 sqm are not deducted (> 0.3 sqm shall be deducted); precast members are measured by solid volume (excluding hollow parts), without deducting rebar, iron parts, or prestressing reserved ducts. Columns, beams, walls, slabs, foundations, and stairs each have interface-attribution and deduction rules; all specialty quota norms apply the same measurement basis.
- →
Quantity take-off (measurement) follows design-drawn dimensions (measurement per drawings): general principle, rule exceptions, and final account linkage
Quantities are in principle calculated from design-drawn dimensions (measurement per drawings), not from actual site dimensions; only items where the method of measurement "provides otherwise" (e.g. earthwork by natural in-situ (undisturbed) volume, depth taken from surveyed elevation) and site instruction / variation record items not specified in the design (flowing sand and silt provisionally estimated, concealed works) are measured per actual conditions / site instruction / variation record. Parts constructed beyond design dimensions without variation or site instruction / variation record support are generally not measured in the final account.
Cited By
- ←
Steel cover plates for trenches (channel troughs): quota-system attribution of steel grating covers versus chequer-plate covers, line item selection, measurement-unit conventions, whether the main material is priced separately, separate billing against the trench body, and the distinction from manhole-cover items at inspection chambers
For steel cover plates, first identify the applicable system, then pick the line item: steel covers laid continuously along a trench follow the metal-structures basis - self-fabricated covers (steel included) are measured in t for fabrication plus erection, while proprietary grating covers are measured in m2 for erection only with the main material priced separately; cast iron or composite covers at inspection chamber openings are counted per piece or per set, and the two systems must not be cross-applied. The structures BOQ bills trench base slabs, walls and cover slabs separately (the cover is a stand-alone item); masonry trench line items carry only blockwork plus joint pointing, so the cover must be billed separately, whereas the all-in trench item measured by m already includes 'trench cover fabrication and erection' in its work content and must not be re-billed. Section-steel edge frames and angle stiffening frames of covers are merged into the cover quantity in t by theoretical mass, and grating apertures with a single-opening area of no more than 0.30 m2 are not deducted.
- ←
Evidence system for a contractor claiming additional works quantities outside the contract scope: four layers of facts to be proved, expert assessment routing where no site instruction records exist, and evidence-gathering means
Claiming additional works quantities cannot rest merely on proof that the works 'were carried out'; the contractor must also prove (i) instruction or consent by the employer, (ii) actual completion of the works, and (iii) that the quantities are measurable and verifiable ((iv) price supported by evidence). Article 20 of Fa Shi [2020] No. 25 ranks site instruction records and other written documents as first-tier evidence, but also provides that 'where the contractor can prove that the employer consented to the works but fails to produce site instruction records to prove the quantities, the quantities actually incurred may be determined on the basis of other evidence provided by the parties'; where there is only a verbal instruction, the employer does not recognise it and no physical evidence exists, the construction cost expert assessment should reach a negative opinion on the ground of absence of legal evidence (GB/T 51262-2017, Clause 5.9.3).
- ←
Full workflow for preparing the tender bill of quantities: preparing entity and object, the seven bases of preparation, itemisation with the five elements and item description, the four-part BOQ composition, deliverables and appendix forms, error liability, and the interface with the tender price ceiling
Chapter 4 of GB/T 50500-2024 provides: the bill of quantities is prepared by a tenderer with preparation capability or by a construction cost consultant commissioned by it (4.1.1); it is itemised with the contract object or a single project or individual structure as the object and forms part of the tender documents (4.1.2); the deliverables comprise the cover, signature page, explanatory notes of the estimate, notes on measurement rules, and the BOQ and pricing forms (4.1.3), in forms B.1.1, C.1.1, D.4.1, E.1.1/E.2.1/E.2.3/E.3.1/E.4.1 to E.4.5/E.5.1 and G.1.1. The BOQ is prepared and priced in four parts -- the work-item BOQ, the preliminaries BOQ, the other items BOQ and VAT (3.1.2) -- and the current edition no longer carries a statutory levies and taxes section; the all-in unit rate and the sum are fully inclusive pre-tax prices excluding VAT, tax is entered under VAT, and the provisional sum for nominated specialist subcontract works already includes VAT and must not be taxed again (3.1.6).
- ←
Determining missing items not listed in the BOQ appendices and setting supplementary items: the three-element comparison search path, the discipline-code + B coding rule (from 01B001), the five required accompanying elements, the tender-document explanation / filing requirements, and the boundary of error when fitting near-match items
Under GB/T 50854-2024 Clause 4.1.4, for items not covered in Appendices A~R the compiler may add supplementary items, coded with this standard's code 01 plus B and three Arabic numerals, numbered sequentially from 01B001, and must attach the item name, item description, unit of measurement, quantity take-off rule and work content (for preliminaries that cannot be measured: name, work content and scope of inclusion). The determination is a three-element comparison (item description + work content + unit of measurement with calculation rule): so long as any element can be carried by an existing appendix item, the existing item must be applied forward and the difference expressed in the item description, and no supplementary code may be created; work content lists only principal operations, auxiliary content such as plant movement and material transport is deemed included, and operations may not be split out and listed separately unless specifically stated. The 2024 editions (GB/T series) say 'may add' and no longer require filing; instead GB/T 50500-2024 Clause 3.1.3 requires the supplementary basis to be explained in the tender and contract documents; the 2013 compulsory national standards required 'shall add + file with the provincial or industry construction cost administration institution', and local standards may still retain the filing requirement.
- ←
The dual measurement boundary of composite slabs and composite beams: the precast soffit plank itemised as a precast concrete component for prefabricated construction (010504), the post-cast composite topping merged into post-cast concrete of composite beams and slabs, and the attribution of its rebar (010506) and formwork (010505)
Composite members must be measured on two sides: the precast soffit plank is measured in m3 as a precast concrete component for prefabricated construction (010504), with no deduction for grout sleeves, post-cast keyways or plank joints, and the joint grouting layer and bedding mortar layer are merged into the component volume; the post-cast concrete strips between precast planks are, per item 4 of GB/T 50854-2024 Annex E.7.7, 'measured within post-cast concrete of composite beams and slabs' and are not added to the plank volume; rebar of the post-cast layer goes to 010506 and formwork to 010505 (by contact area), and none of the three may duplicate the measurement of the precast plank.
- ←
Recasting the concrete volume increment and the formwork contact-area increment after section-size changes to concrete members, why the two move out of step (volume is quadratic in size, formwork linear), the layered order of computation for linked rebar costs, and the tie-in with the 15% quantity-deviation clauses
Concrete is measured by design volume (m3) and formwork by contact area with the concrete (m2) - two independent BOQ items and two geometric functions, so they cannot move in step. With length unchanged, the concrete increment dV = (A_c1 - A_c0) x L; the formwork increment dA = (C1 - C0) x L + (A_b1 - A_b0). The section area b.h is homogeneous of degree 2 in the sizes while the section perimeter 2(b+h) is degree 1: scale the section by k on both sides and volume grows by k^2 but formwork by k - a column with both sides enlarged 5% gains about 10.25% volume but only 5% formwork. After the change, measurement = original BOQ quantity plus or minus the increment; whether the quantity change triggers rate renegotiation follows the 15% bands of GB/T 50500-2024 clauses 8.9.1/8.9.2.
- ←
Member boundary rules for measuring cast-in-place concrete columns, beams, slabs and walls: the levels to which column height and beam length run, the merge and split boundaries for slabs, the deduction thresholds for walls, the attribution of crossover nodes such as column caps, corbels, concealed beams and wall columns, and the differences among three parallel scopes - the BOQ measurement standard (GB/T 50854-2024), local consumption standards and traditional quota manuals
Cast-in-place concrete columns, beams, slabs and walls are all measured by volume (m3) on the dimensions shown on the design drawings, but the 'member boundaries' differ by governing scope. Building quota scope - with ribbed-slab (beam-and-slab) floors, column height runs from the top of the column base (or the top of the floor slab) to the top of the floor slab above; with beamless (flat-slab) floors, to the underside of the column cap; frame columns run to the column top; constructional columns run from the top of the member they root in to the underside of the member they anchor into, the wall-embedded toothing portions being merged into the column body. Beam length runs to the side face of columns; secondary beams run to the side face of primary beams; ribbed slabs take the sum of beam and slab volumes, beamless slabs take slab + column caps, plain slabs take the solid slab volume (this three-way split applies only to local consumption standards and traditional quota scopes). GB/T 50854-2024 Appendix E shows no merged 'ribbed / beamless / plain slab' items in its BOQ scope: slabs are itemised separately as solid floor slabs, sloped roof slabs, hollow floor slabs and other slabs, beams and slabs carry separate codes, and it expressly provides that 'where a wall meets a column, the wall is measured to the column face; where a wall meets a beam, the wall is measured to the beam underside; where a wall meets a slab, the slab is measured to the wall side'; special-shaped columns (section height-to-thickness ratio over 4 in every direction) are itemised as 'reinforced concrete walls'; walls deduct door and window openings and individual holes over 0.3m2, with wall pilasters and projections merged in. The rail-transit underground scope is the opposite: columns run to the underside of beams / slabs, beam-column overlaps go to the beam, and column caps merge into the column body.
- ←
What to deduct and what not to deduct in concrete quantities: rebar / bolts / embedded steel items / tensioning ducts not deducted, rigid-skeleton structural steel deducted, the 0.3m2 single-opening threshold and the distinction from door and window openings (criteria compared across building GB/T 50854, municipal GB/T 50857, rail transit GB/T 50861, railway TB/T 10831 and local consumption standards)
Concrete quantities are measured by design-shown dimensions in volume (m3): the volumes occupied by rebar, bolts, embedded steel items and tensioning ducts in cast-in-place members are never deducted; openings of no more than 0.3m2 each are not deducted (over 0.3m2 is deducted); but the volume of rigid-skeleton structural steel is deducted. The 0.3m2 test is on the area of each single (single-hole) opening, not on cumulative area; door and window openings are always deducted from walls, and the concept does not apply to slabs.
- ←
Work-item quantity take-off for pile foundation (bored pile) rebar cages: the three formulas for main bars, helical links and stiffening rings with their variable definitions, the convention for taking the centreline diameter D of helical links, the BOQ itemisation code for the 'rebar cage' item, and the measurement boundary of laps and non-design reinforcement
The billed quantity of a pile rebar cage = the design-drawn rebar length (centreline) x the unit theoretical mass (tonnes): main bars G_main = (L_cage + L_anchor + L_end) x n_main x w; helical links L_helix = sum over i of (Hi / si) x sqrt((pi x D)^2 + si^2), with D = diameter over the outside of the main bars + link diameter, i.e. pile diameter - 2 x cover + d_link; stiffening rings G_stiff = (pi x D_stiff + lap) x n_stiff x w. GB/T 50854-2024 Table E.6.1 (code 010506) requires the rebar of bored piles and diaphragm walls to be coded and listed under the 'rebar cage' item; laps and anchorage marked on the design (including those required by codes) are absorbed, while stock-length laps and non-design chair bars, raking prop bars, anti-floating bars, spacers and the like are not measured; sonic tubes are not merged into the cage and are listed separately.
- ←
Preventing double counting of earthworks where trench, manhole pit and spread foundation pit overlap: physical overlap versus intersection of battered faces, assigning the manhole-length section by the larger cross-section, the pit deepening increment, pipe-joint working pits already included, and one trench width taken once for multi-pipe runs
Three tests prevent double counting: (1) physical overlap (the same space excavated twice) is counted once, and battered-face intersections are expressly 'not deducted' by most quota manuals (Hunan 2025 IV.4; SJG 111.1-2022 table 1.2.3-1 note 2; SJG 84-2020 table 7.2.9 note 1); (2) the BOQ quantity (GB/T 50857-2024, drawn dimensions plus working space, no batter) and the quota quantity (working space plus batter) are computed independently - never mix then deduct; (3) the manhole-length section is assigned by section size: if A-pit is no less than A-trench the section counts as pit and the trench length is reduced by that section, if A-pit is smaller the manhole length merges into the trench and no pit is listed, the total taking the max, not the sum; where the pit floor lies below the trench floor, the deepening increment delta V = A-pit x (H-pit - H-trench) is added; pipe-joint working pits and manholes along the line are covered by 2.5% of the trench earth and rock quantity (1.5% for wells and joint pits in the railway volume 12), not listed separately.
- ←
BOQ itemisation and measurement wording for earthworks under GB/T 50854-2024 Appendix A: item setting and codes for excavation, backfill, disposal of surplus material, borrowed-soil backfill and site levelling; the two ledgers of natural in-situ volume versus compacted volume; the balance formula; pricing splits; and the listing boundary of vertical cut-and-fill
GB/T 50854-2024 Appendix A splits earthworks into three sections: standalone earthworks (010101), foundation earthworks (010102), and site levelling plus others (010103), with disposal of surplus material and site levelling sitting in 010103. A.4.10 provides that excavation and backfill quantities take no account of conversion between compaction states, so excavation is the natural in-situ geometric volume before cutting and backfill is the compacted (as-formed) volume shown on the design, both in m3, and the two can be subtracted directly - disposal of surplus material = excavation BOQ quantity - reusable backfill BOQ quantity; the backfill quantity must deduct the volumes of buried members such as foundations, bedding and pipes; borrowed-soil backfill still lists a single backfill item, with its pricing split into borrowing (soil purchase) + off-site haulage + placement and compaction; A.4.13 makes disposal of surplus material cover loading, haulage and disposal-compliance requirements to the designated tip, with the haul distance and tipping fees inside its all-in unit rate; A.4.12 defines site levelling as in-place cut, fill, haul and level within +/-300 mm of the site datum, measured in m2 (first-floor gross floor area), while vertical cut-and-fill beyond +/-300 mm is listed under standalone earthworks in m3.
- ←
Quantity demarcation and length measurement between risers and branch pipes in water supply and drainage (heating, gas) piping: risers accumulated segment by segment by design level difference (storey-height accumulation only as a check), the tee/cross intersection on the riser centreline as the demarcation point, branch pipes measured from that centre to the fixture inlet, vertical segments measured on isometric drawings and horizontal segments on plans, same-floor versus floor-through drainage branch differences, and parallel risers in one shaft listed pipe by pipe
Riser length is accumulated segment by segment along the pipeline centreline shown on the design as upper level minus lower level; storey-height accumulation is only a check value and never a measurement basis. The demarcation between riser and branch is the tee or cross intersection on the riser centreline; the branch runs from that centre point to the centre of the farthest fixture or equipment connection, and the length of the tee fitting itself is neither deducted nor added (fitting installation is already inside the piping item). Parallel risers sharing one shaft must be itemised pipe by pipe by material, connection form and specification, never merged into one measurement.
- ←
Water supply and drainage pipeline quantities are computed by the centerline length shown on the design drawings: lengths occupied by fittings, valves and chambers are not deducted; construction wastage is not counted additionally
Water supply and drainage pipeline quantities are computed by the pipeline centerline length shown on the design drawings (linear meters), not by the actual installed length; the lengths occupied by valves, pressure reducers, steam traps, water meters, expansion joints and other fittings, and by the various chambers, are not deducted; the length occupied by square expansion compensators is added into the pipeline quantity; the additional lengths laid during construction for obstacle avoidance and bending are construction wastage and are not counted again. Municipal drainage follows a separate basis — "manhole centre to manhole centre, deducting the clear space of each inspection chamber" — and the applicable basis depends on the quota manual being executed for the project.
- ←
How to look up 'no deduction / deduction' threshold clauses in the measurement rules (enumerated item by item in the appendix rule column, judged by the area of a single opening at 0.3m2), with a threshold comparison table for concrete, formwork, masonry and flooring
'No deduction' clauses are written item by item in the 'quantity measurement rule' column of the appendix tables of the measurement standards, and the determination rests on three elements: the comparison object is the area of a single opening (not the total opening area, not the share of member volume); the direction is 'no more than 0.30m2 (within) - no deduction, above 0.30m2 (beyond) - deduct' (equal to the threshold counts as no deduction); and the measurement form distinguishes volume from area (formwork by contact area). Reinforcement, bolts, embedded plates and grouting ducts inside members are never deducted, but the structural steel of steel skeletons is deducted; cast-in-place walls and slabs and cast-in-place members of municipal bridges, culverts and pipeline networks all take the single opening of 0.3m2 as the boundary; in masonry, beam heads, slab ends and the like and other single openings no more than 0.30m2 are not deducted, and waistbands, cantilevered eaves and door and window linings projecting from the wall face are not added; monolithic flooring does not deduct partition walls, columns and pilasters no more than 0.3m2, attached chimney flues and openings, and openings at doorways and voids are not added, while for tile and stone finishes the openings are merged in. Net quantity = quantity by drawn dimensions - deductible items + items to be merged in; missing the companion sentence 'the sides of openings are likewise not added / the projecting part is merged in' makes the quantity wrong.
- ←
Bills of quantities errors (item description mismatches, wrong or missing items, quantity deviations): determination, attribution of responsibility and the quantity-then-price adjustment sequence, including the split between unit-rate and lump-sum contracts and the 15% threshold rule
Where the BOQ and the drawings are inconsistent, the sequence is 'decide which prevails -> attribute the defect -> remeasure and adjust the price': under a unit-rate contract the BOQ prevails, under a lump-sum contract the contract drawings and specifications prevail (GB/T 50500-2024 clause 3.4.7); for unit-rate contracts, BOQ errors in the schedule of divisional work items lie with the employer - remeasure per clause 7.2.1, band the change per clause 8.2.1 at the 15% boundary (15% inclusive), and where not exceeded set the all-in unit rate adjustment per clause 8.9.1; for lump-sum contracts BOQ errors lie with the contractor, and the contract price is not adjusted except for items described as 'provisional quantities' (clauses 4.1.4, 4.1.6 and 6.1.7).
- ←
Attribution of quantity gaps between BOQ quantities and quota quantities, and the rate conversion: all-in unit rate P = Sum(Tn) / Q, four destinations of quantity gaps (into the BOQ quantity / into the rate / into quota consumption / into the risk allowance), and conversion points for typical work items
BOQ quantities and quota quantities must be kept on two separate tracks and never swapped: first attribute each quantity gap to one of four classes - content already built into the measurement rules (working space for earthworks) goes into the BOQ quantity; content listed under 'work content' but given no quantity (battering, shoring boards, base trimming and clearing) goes only into the ancillary-works cost or risk allowance inside the all-in unit rate; content carried by the quota through wastage rates or contents (material wastage, rebar wastage plus construction bars at 5%, permissible overbreak in rock works, 0.50m over-concreting of bored piles) goes into the numerator, the quota line-item totals; whatever neither the BOQ nor the quota provides can only go into the rate risk allowance. The conversion formula is P = Sum(Tn) / Q (P rounded to 2 decimal places, Tn kept at full precision without rounding, Q rounded to 3 decimal places). Quoting with quota quantities passed off as BOQ quantities is an explicit error: the dimensional bases differ, the all-in unit rate is understated (omission ratio = 1 - quota rate / all-in rate), and it blurs the parties' respective responsibilities for BOQ accuracy.
- ←
Calculation rules and values of reserved (additional) lengths in cable laying quantities
Cable quantity = the single-cable laying length shown on the design + various reserved (additional) lengths; where the design stipulates, follow the design, otherwise take the standard values: slack/bending/crossing add 2.5% (on the base of the drawn length plus the sum of reservations); terminations 0.5 m, joints 0.5 m, entry to distribution panels 1 m, power distribution boards 1.5 m, control panels 2 m, plant transformers 3 m, main transformers 5 m, etc. (GB 50217-2018 Appendix G); directly buried cables entering buildings may take 5% of the route length.
- ←
Separating conduit, trunking wiring and cable laying in the BOQ: GB/T 50856-2024 Annex D codes (030412/030409) against the 2013 old codes (030411/030408), a three-column comparison of object measured x unit x item description, the tests for splitting conduit and cable segments of one circuit, and the quota chapter mapping
Under the 2024 edition, 'electrical conduits and trunking' are itemised under 030412 (Table D.12.1) and 'cable laying' under 030409 (Table D.9.1); the 2013 old codes 030411 (conduit and wiring) and 030408 (cable installation) have been rearranged - 030411 is now overhead power distribution lines of 10kV and below and 030408 is trolley conductor rail installation - so retaining the old codes is a BOQ error. All three are measured in 'm' but on different bases: conduit by conduit length (no deduction for junction boxes, luminaire boxes, switch boxes, socket boxes and pull boxes along the run), wiring by single-wire length including reserves, and cable by single-cable length including reserved and additional lengths; the dividing criterion is the conductor form (insulated wires in conduit or trunking versus the cable itself), not the routing.
- ←
Measurement of the works rules in Chapter 8 of GB 50500-2013: measurement basis and mandatory provisions, verification of completed-works quantity reports and deemed approval upon lapse of the period, notice procedure for on-site measurement and consequences of absence, and review of objections to measurement results
Chapter 8 of GB 50500-2013: quantities must be calculated under the rules of measurement of the current national measurement codes and determined by the quantities of the work the contractor has actually completed and that are to be measured (clauses 8.1.1 and 8.2.1 are mandatory provisions; tender BOQ quantities are only estimates). The contractor submits the completed-works quantity report each agreed period; the employer verifies within 7 days of receipt and notifies the contractor; where verification is not done within the agreed time, the quantities in the report are deemed the quantities actually completed by the contractor (8.2.3). On-site measurement verification requires notice to the contractor 24 hours before measurement; if the contractor is absent it is deemed to approve the employer's verification result, and if the employer fails to notify as agreed so that the contractor cannot attend, the verification result is invalid (8.2.4). A contractor disputing the verified result must raise written objections within 7 days of notice with calculation records attached, and the employer reviews within 7 days; continuing disputes follow the contract's dispute resolution (8.2.5). Under the current GB/T 50500-2024, clauses 7.1.7 and 7.1.8: measurement results signed and confirmed by both parties serve as the basis for contract price adjustment and settlement.
- ←
The three rebar quantities (drawing quantity -> cutting quantity -> procurement quantity): stage-by-stage measurement bases, the quota chapter where the wastage rate is taken, and the conversion procurement quantity = budget quantity x (1 + wastage rate)
Drawing quantity = design centreline length x theoretical unit mass (includes anchorage and design laps; excludes construction laps / auxiliary bars / wastage); cutting quantity = drawing quantity + end hook growth values, bend deduction values (elongation as a deduction), stock-length laps and splice lengths, auxiliary bars and the inclined length of bent-up bars; procurement quantity = budget quantity x (1 + wastage rate), the wastage rate being taken item by item by bar type and splice method. In the railway system the reinforcement wastage rate is taken uniformly from Chapter 10 'on-site material handling and operation wastage rates' of the 'Railway basic quota manual' TB/T 10821-2024 (welding 1.5%, mechanical splices 1%, prestressing tendons 4% excluding the external-tensioning working length), not from the concrete chapter or the reinforcement fabrication chapter.
- ←
Aggregating rebar quantities by size and the measurement boundaries: grouping by bar type / diameter band / member; hooks, design laps and anchorage included; construction laps and measures bars not measured; mechanical couplers counted as units without laps; in t to three decimal places
Rebar quantity W(t) = Sum(ni x Li x wi) / 1000, with lengths taken as the centre-line lengths of the bars shown on the design drawings (GB/T 50860-2024 Annex A.15.6), aggregated at three levels: bar type / grade, diameter band (quota manuals commonly d10 and below / above d10) and member location (cast-in-place, rebar cages, secondary structure, sundry members, mesh). Included in the BOQ quantity: anchorage bars projecting from members as designed (GB/T 50854-2024 Annex E note 10) and laps marked in the design or required by the code (lap length ll corrected for the splice-area percentage and no less than 300mm, GB 50010-2010 Clause 8.4.4). Excluded: construction laps such as stock-length laps, non-designed chair bars, diagonal brace bars, anti-floating bars and spacers, and non-designed post-installed bars; rebar at post-cast strips is not itemised separately. Where the drawings require mechanical connection, the straight-thread sleeve coupler item applies and no lap quantity is calculated; couplers are counted as units by the number shown on the design. Rounding of totals: quantities in t are stated to three decimal places, the fourth being rounded (GB/T 50861-2024 Clause 3.0.3).
- ←
Developed area formulas for ducts (ventilation ductwork): rectangular F = 2(a+b) x L, circular F = pi x D x L, tapers by average diameter / average perimeter; lock seam overlap not added; elbows, tees and reducers merged by centreline length; component lengths deducted, not merged
Duct developed area is uniformly calculated as 'developed perimeter x design centreline computation length': rectangular ducts F = 2(a+b) x L, circular ducts F = pi x D x L (pi taken as 3.1416); circular tapers by average diameter, rectangular by average perimeter; metal ducts take the internal diameter (internal perimeter), GRP and composite ducts the external diameter. Lock seam overlap (folded edges) neither enters the developed area nor adds quantity (already included in the quota). Elbows, tees, reducers and round-to-rectangular transitions merge their lengths into the centreline length and their areas into the m2 totals of the connected duct at the section perimeter; lengths occupied by dampers, outlets and other components are deducted and the components are listed separately under 030703; opening areas of access doors, test holes, supply and return outlets are not deducted. The BOQ item 030702 is measured in m2.
- ←
Quantity take-off of electrical conduit: GB/T 50856-2024 table D.12.1 (code 030412) measures by design-drawn length; the horizontal plus vertical segment method, attribution of reserved lengths, and listing rules for exposed versus concealed installation
Under GB/T 50856-2024, conduit and wiring form table D.12.1 with code 030412 (the 2013 edition's table D.11 / code 030411 is superseded; in the 2024 edition 030411 now designates overhead distribution lines of 10kV and below). Conduit is measured in m, calculated as length from the design drawings, without deducting the lengths occupied by junction boxes, luminaire boxes, switch boxes, socket boxes and wiring cabinets within the run. The quantity is L = sum of L_h,i + sum of L_v,j: horizontal segments follow the drawn path of the conduit centreline on the plan (not the straight-line distance between two points), and vertical segments are L_v = upper installation level minus lower installation level. This formula is a take-off decomposition method, not standard text; the reserved length for entering cabinets and panels belongs to the wiring (table D.17.3-8) and must not also be counted into the conduit itself, to avoid double counting.
- ←
Rules on the significant decimal places of the summarised quantity of each item when measuring the works: t and km keep three decimal places, m, m2, m3 and kg keep two, count units such as number, piece, bar, seat and set are taken whole, plus the clause numbers and unit-group differences across the 2013 and 2024 editions of each sector volume
When measuring the works, the significant decimal places of the summarised quantity of each item follow the sector volume: quantities in 't' (plus 'km' for urban rail transit) keep three decimal places, the fourth rounded off; quantities in 'm', 'm2' and 'm3' (plus 'kg' in the 2013 building volume and the 2024 urban rail volume) keep two decimal places, the third rounded off; quantities in natural count units such as number, piece, bar, seat, set, group or system are whole numbers. Clauses: GB 50854-2013 clause 3.0.4, GB/T 50854-2024 clause 3.0.3, GB/T 50861-2024 clause 3.0.3.
- ←
Stages and charging of landscape greenery maintenance: the start points of construction-period, establishment and conservation (routine) maintenance, the period adjustment factors and the quantity measurement objects
Greenery maintenance divides into three non-overlapping stages: construction-period maintenance (planting to completion acceptance) is inside the planting items, never charged again; establishment maintenance runs in 'months', quantities by plant counts for trees, shrubs, climbers, standards and bamboos, length for hedges, area for lawns, flowers, colour bands, perennials and aquatics - Beijing counts from completion of planting, part months as whole months, and the part beyond one year at x 0.85 (Hunan: within one year of the planting unit works' passing acceptance - months 1-3 on establishment items, months 4-12 labour-material-plant x 0.8); conservation (routine) maintenance runs in 'years' from passing completion acceptance, its term per design or contract. Hence aquatics etc. 'plant by count, maintain by area'.
- ←
Curtain boxes and curtain tracks (rods): BOQ itemisation, quota item selection and units - proprietary erection and site fabrication listed apart, measurement by extended metres, tracks never merged with boxes
Curtains, curtain boxes and tracks are itemised per GB/T 50854-2024 Table H.10.1 (code 010810), measured by length (extended metres) from the drawings, never developed area; proprietary boxes take 'proprietary erection' items and site-made boxes 'fabrication and erection' items, the proprietary box entering as an unpriced main material; curtain tracks and rods are not inside the box items - every quota volume sets separate items, and they must be listed apart.
- ←
Measurement split for steel members versus cladding sheets: columns, beams, roof trusses, monitor frames, wall frames and wind frames by mass (t); profiled steel floor decking and steel wall sheeting by area (m2); coatings charged separately
Steel space trusses, roof trusses / bracket trusses / lattice trusses, steel columns, steel beams, monitor frames, wall frames, wind frames and similar metal members are computed by mass (t) from the dimensions shown on the drawings - the mass of holes is not deducted, electrodes, rivets and bolts are not added; corbels, cantilever beams, gusset plates, stiffening rings, liner pipes, braking beams, stoppers and other attached members are merged in. Steel floor decking is computed by laid horizontal projected area and steel wall sheeting by hung developed area (m2), with no deduction for individual holes up to 0.30m2, and corner and edge trims add no area. Consumption of metal members excludes paint and fire-protection coatings - where required by design they are computed separately under clause 4.15 (except surfaces already coated ex-works).
- ←
The building repair works quota (railway 2024 building volume): scope of application, auxiliary work already included (30m haul, vertical transport, propping and watch), and the quantity rules of demolition and strengthening items
The 'repair works' section of the railway 2024 building quota applies to piecemeal demolition and structural strengthening of buildings - not to whole-building demolition. The items already include propping and strengthening of the building and adjoining parts, site watching, hauling reusable material and debris to designated points within 30m, vertical transport, and clearing, stacking and tidying. Demolition always measures 'as actually removed': roofing by removed area; masonry by removed volume (holes up to 0.03m2 not deducted); ceilings by horizontal projected area (interior columns not deducted); floors by horizontal projected area (skirtings merged in); concrete and reinforced members by removed volume. Static cutting measures the cut face area; where cut blocks need breaking, the concrete demolition item applies x 0.80. Steel demolition measures mass from the drawings (no deduction for holes, cropped limbs or edges; electrodes, rivets and bolts add no mass); steel-plate and carbon-fibre strengthening measure the actually bonded area (laps included).
- ←
Spatial-volume calculation rules for full-framing steel-pipe falsework in municipal and bridge/culvert works: the formula, the datum surface, the beam-body deduction issue and a cross-standard comparison (Shenzhen SJG 181.2-2024, Hunan 2025 edition, railway TB/T 10823-2024, highway JTG/T 3832-2018, Beijing DB11/T 2382-2024)
Full-framing steel-pipe falsework and assembled steel falsework are measured by spatial volume in m3: spatial volume = height (the longitudinal average height from the structure soffit/beam soffit to the original ground surface or the top of the working platform) x longitudinal distance x width (bridge width + 1.5 m; the Hunan basis uses +2 m). The beam body lies above the falsework space and is inherently excluded from the spatial volume; no standard contains any provision for "deducting the beam volume". The only express deduction is that falsework for cast-in-place bent caps deducts the volume occupied by the columns. Rental fees are calculated separately in tonne-months as spatial-volume weight x rental time (in the absence of a basis: 50 kg/m3 for the full-framing type, 125 kg/m3 for the assembled type, and 184 kg/m2 for the upper part of steel-pipe falsework); surcharge preloading is calculated separately as the design volume of the beam x 1.10 (railway: design beam weight x 1.2).
- ←
Classifying and measuring slope treatment works by protection type: plant protection by slope area, masonry protection by masonry volume, anchoring and facing listed apart (anchor length / mass + facing area), SNS flexible nets by laid area with anchors and posts separate
Slope treatment pricing first fixes the sector system (railway / highway / municipal) and the protection type, then itemises on the measurement line: (1) plant protection (grass seeding, hydro-seeding, geotextile mats, planting bags) by laid slope area; (2) masonry protection (mortared rubble slope protection, skeleton (rib) protection, protection walls) by solid masonry volume, rendering and pointing extra by area; (3) anchoring + facing (anchor-mesh hydro-seeding, shot-seed-mix, anchor-mesh shotcrete) split with anchors by design length / mass and facings by area / volume; (4) SNS flexible protection nets by design laid area, with anchors and post foundations / posts listed separately. What the work content already includes (meshing, scaffolds, energy dissipators etc.) is never listed again.
- ←
The twelve-digit rule for BOQ item codes: digits 1-9 unified per the appendices, digits 10-12 set by the compiler, the 01B supplementary code for gaps, the duplicate-check scope, and 2013 versus 2024 differences
BOQ item codes are twelve Arabic digits in five levels: discipline code (1-2), appendix class code (3-4), section code (5-6), work-item code (7-9), item-name code (10-12). Digits 1-9 must follow the appendices (national, no self-coding); 10-12 are set by the compiler from the item name and item description and may not duplicate within the same tendered works (GB 50854-2013 clause 4.2.2, mandatory; GB/T 50854-2024 clause 4.2.2 narrows to 'within the same single project of the tendered works'). Items absent from the appendices take supplementary codes 01B + three digits from 01B001 (the 2013 edition required filing with the provincial or industry cost authority; 2024 no longer requires it).
- ←
Measurement unit rules for landscape greening maintenance: trees and single shrubs per plant, massed shrubs, ground cover, flowers and lawns by area, single and double hedges by extended metres, with item units as plant-months / 10 plants per month / 100 plants and the like
Maintenance measures by plant class: trees (evergreen / deciduous), single shrubs, palms and climbing plants count per plant on drawn quantity, items often converted to 100 plants, 10 plants / month or plant-months (railway LY-339 / 340 tree upkeep per 100 plants; Beijing E-2-547 establishment upkeep of evergreen trees in plant-months; Shaanxi 1-542 to 1-545 evergreen tree upkeep per 10 plants / month); massed shrubs, ground cover, open-ground flowers, lawns and vertical-wall greening by drawn area (massed shrubs often per 10 m2); single and double hedge upkeep by drawn extended metres (railway LY-343 / 344 per 100 m); water-truck watering by water volume or plant size.
- ←
Pricing and member-wise itemisation of stone balustrades (granite balustrades): the basis test, the post / panel / sill items and their measurement rules
Stone balustrades route by works basis first: landscape / scenic and antique-style balustrades (posts + panels + continuous sill as grouped stonework) take Beijing 2024 antique volume B.2 stonework (B-2-15 to B-2-19) or landscape volume E.3.3-10 / 11; modern stone panels of stairs, corridors and outdoor platforms take building volume A.15.3-7. Member-wise measurement: sill stones by length m (landscape) or volume m3 (antique); posts by size per piece; Xunzhang and Luohan panels by drawn height x base length in m2; drum-end stones by base length x mean height in m2. BOQ itemisation per GB/T 50855-2024 Table B.2.1 (code 020202) or GB/T 50854-2024 Table Q.3.1 (code 011503).
- ←
Measuring and pricing drainage (discharge) pipes: fixing the measurement basis and quota items by scenario - roofs, urban rail transit, municipal bridges and culverts, railway bridge decks
Drainage pipe measurement splits by scenario: pipe bodies (downpipes / drainage pipes / the discharge pipes themselves) by drawn length in m (extended metres), and finished parts - discharge outlets, rainwater heads, hoppers, drain inlets - by count (per set / per piece). Building roofs follow DB11/T 2382-2024 Articles 4.10.21 to 4.10.23 (downpipes by length; hoppers, bends and drain inlets by count; roof drain (drip) pipes and vent pipes by count); urban rail follows Article 10.1.90 of the same standard (discharge pipes by length); municipal bridges follow SJG 181.2-2024 Article 7.2.4 (drainage pipes and weep holes by length in metres); railway bridge-deck drainage quotas count per 10 extended metres. The same member carries different units across industry quotas - apply the volume the project executes.
- ←
Deduction basis for cast-in-place concrete of steel-reinforced concrete (SRC) columns: embedded steel sections (rigid skeletons) deducted, shear studs and other bolt-type connectors not, with two algorithms - by drawn volume and by tonne conversion
The cast concrete quantity of SRC columns deducts the volume of the embedded steel sections (rigid skeleton) and does not deduct shear studs and other bolt-type connectors. Basis: GB/T 50854-2024 Appendix E general notes on cast components - cast reinforced concrete does not deduct rebar, bolts, embedments or post-tensioning ducts, but does deduct the steel sections of rigid skeletons - the sole exception to the no-deduction list. Deduction, one of two ways: 1 by the actual drawn volume of the sections; 2 by the simplified 0.127 m3 per tonne of sections (i.e. converted at 7850 kg/m3, expressly per Beijing DB11/T 2382-2024 Article 4.6.6). The sections themselves itemise separately in t under Appendix F metal structure works; shear studs neither join the concrete deduction nor the steel quantities, itemised separately per piece / set.
- ←
Choosing the pricing route and item attribution for electrical handholes / manholes under quotas (power cable chambers, street-lighting pull pits, telecom manholes / handholes, precast vs cast-in-place)
Pricing a cable working chamber first chooses between two routes: (1) whole-chamber comprehensive items (unit per chamber, work content covering the base, masonry or casting, rendered and waterproofed walls, covers and frames, even pit excavation and backfill outside - no further sub-items covered by them); (2) split combined items (blinding / masonry base / formwork / rendering / cover fabrication and installation / cover and seat listed separately, units m3 / m2 / set). Power (electric cable) chambers go to the power / cable line chapters (e.g. TB/T 10829-2024 Volume 8 DY-341 to DY-349 cable manhole fabrication); street-lighting pull pits and telecom manholes / handholes go to the telecommunications / ducting chapters (e.g. TB/T 10826-2024 Volume 5 TY-60 to TY-69 masonry manholes / handholes). Whether precast concrete chambers can be applied depends on the item's workmanship: DB11/T 2382-2024 Table F.1.5-2.3 standard concrete cable chambers is a cast-in-place work content and cannot be applied as precast; precast members and shafts are measured by volume / length per Articles 7.4.15 / 7.4.16, and where no precast chamber item exists it is a gap requiring a supplementary quota and approval.
- ←
Pricing basis and settlement recognition rules for the over-concreting (additional pour) length of bored piles (comparison of values across quota and consumption standards)
Priced quantity of bored pile concrete = design pile cross-sectional area x [design pile length (including pile tip) + over-pour (additional pour) length]; where the design specifies the over-pour length, follow the design; only where the design is silent does the quota default apply - 0.50 m in the railway buildings volume and Shenzhen SJG 111.1-2022; Hunan 2025 uses 0.80 m for underwater (tremie) concrete piles and 0.50 m for non-underwater piles; Shaanxi uses 1 m for rotary-drilled, rotary-excavated, percussion, percussion-drilled and enlarged-hole piles and 0.5 m for tube-driven and screw piles; the railway bridges and culverts volume uses design pile length + 1 m, with no allowance for hole enlargement and no over-consumption coefficient applied. The over-poured portion must be cropped off: pile head cropping (cut-off) is a separate line item measured in volume as over-pour length x design cross-sectional area of the pile shaft; at settlement the over-consumption coefficient adjusts the material content against the piling records, while labour and plant are not adjusted.
- ←
Double-counting test for BOQ items of anti-corrosion coating and fireproofing coating in steel structures: duplicate item-description wording is not double counting; the test is whether both point to the same coating operation / the same coat
Repetition of item-description wording is not in itself double counting - anti-corrosion paint and fireproofing coating are brushed onto the same member surfaces, so similar descriptions are normal. The test is whether the two point to the same coating operation / the same coat: coats in different systems (primer / intermediate coat / topcoat vs fireproofing coating) are independent items settled as executed; only where the same operation is described in two line items, or where one line item's quota work content already covers the other's operation (e.g. a fireproofing coating item whose work content already includes surface rust removal and primer), is the duplicated portion disallowed. Basis: GB/T 50854-2024 Appendix F.10.11 and GB 50205-2020 Appendix J.0.4 (two independent measurement bases), and GB/T 50854-2024 Article 4.1.2 (necessary work already included in the work content must not be split out as a separate item).
- ←
Formwork quantity measurement basis for concrete inspection chambers and structures: by formwork-to-concrete contact area in m2, counting both inner and outer faces of chamber walls, with base side forms and the base flow channel calculated separately; standardised chambers are comprehensively priced per chamber with formwork included and not separately charged, while non-standardised concrete chambers use water-treatment structure tank base slab / wall / cover slab items (labour x 1.1); single holes up to 0.3 m2 are not deducted with no hole side forms added, holes over 0.3 m2 are deducted and their side forms added
Formwork for concrete inspection chambers is invariably measured by the area of formwork in contact with concrete, in m2 (not by volume or projected area). First distinguish scenarios: standardised inspection chambers (per the 07MS101/06MS201 standard drawings) are comprehensively priced per chamber, the items already including formwork erection and removal, so the formwork contact area is not calculated separately; only non-standardised cast-in-place concrete chambers are measured by contact area across walls, base (base slab / flow channel), risers and cover slabs, using the water-treatment works Chapter 6 cast-in-place reinforced concrete tank base slab, wall and cover slab and the related preliminary items, with labour multiplied by 1.1. Chamber walls are formed on both inner and outer faces and both faces count; holes follow the 0.3 m2 single-hole threshold (up to 0.3 m2 not deducted and hole side forms not added; over 0.3 m2 deducted and hole side forms added); the base flow channel is measured separately by the contact area of the cast flow channel with the formwork.
- ←
Quantity basis for cost estimation when BOQ quantities are overstated: costs follow actual quantities (taken off from the drawings) rather than BOQ quantities, and the effect of overstated BOQ quantities on the contract price (re-measurement and adjustment under re-measurable contracts / no adjustment under lump-sum contracts)
Cost estimation must be based on actual quantities (the drawing-based quantities calculated from the dimensions shown on the design drawings under the measurement rules agreed in the contract), not on the bill of quantities (BOQ) quantities - BOQ quantities are provisional (estimated) figures on the revenue/tendering basis, whereas cost follows actual resource consumption; the two sets of accounts must be kept separately, with the difference carried as a separate quantity variance. This rests on Article 17 of the Cost Management Regulations for State-Owned Enterprises (Guo Fa [1984] No. 34) - costs must be accounted for from actual consumption and actual prices, and enterprises must not substitute planned cost, estimated cost or norm-based cost for actual cost - and on Article 4.1.5 of GB/T 50500-2024, under which quantities of work-item BOQ entries under a re-measurable (unit-rate) contract are provisional quantities to be determined by re-measurement. The effect of overstated BOQ quantities on revenue depends on the contract type: under a re-measurable (unit-rate) contract the works are re-measured against the actual construction drawings, so the inflated portion earns no payment (it is an error in the BOQ, rectified and repriced under Articles 7.2.1 and 8.2.1, with 15% as the threshold); under a lump-sum contract the work-item BOQ need not be re-measured and BOQ errors are not adjusted (Articles 7.2.2, 4.1.6 and 8.2.3), so an overstated BOQ quantity against less work actually done yields a quantity variance gain. The only opening is BOQ entries whose item description states a provisional quantity: under both contract types they are re-measured and adjusted under the re-measurable-contract rules.
- ←
Luminaire classes and listing notes for the lighting installation bill (code 030413) of GB/T 50856-2024
Per GB/T 50856-2024 Annex D table D.13.1 (lighting installation, code 030413) notes: luminaires divide into ordinary lamps, decorative lamps, factory lamps, high-point (obstruction) lamps, medical lamps, neon, campus street lamps, landscape lamps and lighting switches; neon covers tubes, strips, transformers, controllers, relays, timers and control boxes - all components; mid-mast lamps mount on poles 19 m high or less, high-mast lamps on poles over 19 m; where measured in "m" the item description shall state the lamp width, in "m2" the lamp size.
- ←
When site levelling may be charged as a bill / quota item: in-place grading within plus/minus 300 mm qualifies; vertical-layout excavation (earth or rock) is excluded and measures as general earthworks
Site levelling is an "area-basis yard grading" item, not an earthwork: defined as the in-place cut, fill, haul and grading within plus/minus 300 mm of the building's site level before foundation earthworks (GB/T 50854-2024 clause A.4.12), measured on the building's first-floor floor area at design-shown dimensions, the area of basement structure projecting beyond the first floor merging in (table A.3.1, code 010103). Within plus/minus 30 cm, list as site levelling; vertical-layout excavation (or hillside cutting) beyond plus/minus 30 cm lists as excavation; rock likewise - vertical rock cuts or hillside hewing over 300 mm execute as general rock excavation - plus/minus 300 mm is the mutually exclusive line between "site levelling" and "general earth (rock) works"; one section takes one only.
- ←
Pricing the core filling of hollow blocks (core-column concrete): never merged into the block-wall items - apply the cast-in-place concrete column "core column" item, quantities on hole section area times design-shown height
Block-wall items cover only "mixing mortar, cutting, laying and the like" - core filling is outside; apply the "core column" item among the cast-in-place concrete columns (Beijing DB11/T 2382-2024 A-5-13; 2021 edition 5-13), unit m3; quantities on the hole cross-section area times the design-shown height by volume. Plain and reinforced core columns take the same item; the bars, ties and inserts within them execute under the concrete and reinforced concrete rules. Regions differ (Shaanxi, e.g., already counts the core mortar of vertically laid blocks at opening jambs inside the walling mortar) - apply per the local quota notes.
- ←
When bill and quota measurement units mismatch (m2 bill against m3 quota): no unit conversion - bill and quota quantities run on separate tracks, bridged by the all-in rate P = sum of item prices over Q
Bill units are locked - never rewrite a bill to m3 because the quota runs m3: GB/T 50500-2024 clauses 3.1.4 and 4.1.7 require units per the national and sector measurement standards, and GB 50861-2013 clause 4.2.6 (mandatory) "bill units shall follow the units in the appendix". The right handling is neither unit conversion nor a conversion factor on the quota rate, but: bill quantities on bill rules (keeping the appendix m2 unit), quota quantities converted on quota rules (m3), independent; then bridged per DBJ/T 15-145-2018 clause 6.1.4 - the all-in rate of a bill item equals the sum of the quota item prices under it divided by the bill item quantity.
- ←
Quantity calculation and consumption-standard sub-item application for grooved-connection fittings of sprinkler pipes (mechanical tees, grooved fittings, couplings/clamps) - mainly Beijing DB11/T 2382-2024
Sprinkler pipes are calculated by the centre-line length shown on the design, without deducting the lengths of fittings and components; mechanical tees/crosses (hole-cut type) apply the "steel pipe (grooved connection) hole-cut fittings" sub-items, finished elbows/tees/crosses apply the "steel pipe (grooved connection) grooved fittings" sub-items - both measured per "set" by the design quantities, each set including the clamp and gasket (material content 1.0050 set/set); couplings are not itemized separately - butt joints of straight pipes are included in the pipe sub-items (grooved coupling 0.1667 set/m, about one per 6 m), and couplings at fittings are included in the fitting sub-items. GB 50261-2017 Clause 5.1.11: mains (risers) and horizontal pipes shall not be connected by mechanical tees; the hole spacing of mechanical tees shall not be less than 500 mm and of mechanical crosses not less than 1000 mm.
- ←
Measurement caliber for municipal drainage pipes and rainwater-inlet connectors: by design centerline length without deducting manholes and inlets (Beijing/national), versus regional manhole-deducting calibers
Beijing DB11/T 2382-2024 matches GB/T 50857-2024: drainage pipes (including inlet connectors) are computed by design centerline length, without deducting manholes, inlets, and other auxiliary structures — there is no "center or edge" datum question; some cities (e.g., Shenzhen SJG 181.4-2024 Clause 1.2.3) deduct each manhole's length from center-to-center lengths — a regional difference; confirm local rules before cross-region compilation.
- ←
Pricing pavement removal: selection criteria between milling and demolition sub-items, with corresponding Beijing DB11/T 2382-2024 Appendix D municipal sub-items and consumptions
Pavement removal is not a binary choice but split by construction essence: asphalt course shaving (maintenance/overlay, milling machine, milled material loaded and recycled) applies milling sub-items; wholesale pavement excavation (structure abolition, pipeline trenching) applies demolition sub-items; full-depth cement-concrete removal can only apply demolition (the milling group has only a "texturing within 1 cm" tier); pre-overlay surface texturing applies milling - texturing. Criteria: material, depth, and the approved method-statement process — all three indispensable. Beijing 2024: milling group D1-6-14-19 (100 m2), demolition group D1-6-1-6, 8-9, 10-11, 26-29 (pneumatic-pick type per 10 m2, mechanical per 100 m2); milling work content already includes loading (do not double-count loading), demolition only "piling old material" without loading/haul — count separately; demolition of pavement/base courses is computed by area.
- ←
Priority order when methods of measurement of different disciplines/versions conflict: contractual agreement -> national standard for measurement of the works matching the contract category -> industry/local standard -> fallback chain for version disputes
On conflict, determine the applicable methods of measurement by the order 'contractual agreement (including version) -> current national standard for measurement of the works consistent with the contract category -> industry/local standard' (GB/T 51262-2017 Clause 5.5.1, T/ZBD 100.4-2023 Clause 4.3.1); with multiple disciplines coexisting, attribute each billed (BOQ) item by the first two digits of its item code (01 building construction and decoration ... 09 blasting), and once attributed, measurement must follow that standard's appendix rules (GB 50861-2013 Clause 4.2.5, mandatory provision of codes) with no cross-discipline mixing; where no version is agreed, follow the method of measurement explicit in the document prevailing under the contract interpretation order -> re-measurable (unit-rate) contracts fall back on the tender bill of quantities (BOQ) and the method of measurement used for the tender price ceiling, and lump-sum contracts on the method of measurement used in the tender price, and if still undeterminable the appraiser measures by professional judgment with explanation (T/ZBD 100.4-2023 Clause 4.3.2).
- ←
Waterproof protective layer (protection over membrane waterproofing): quantity calculation, BOQ itemization, and norm application — roof, floor, and foundation positions
Protective layers are computed by design-shown area (m2) (DB11/T 2382-2024, 4.10.27): roofs follow the roofing caliber (flat roofs by horizontal projection, sloped by slope area; upturns and gutters merge, 4.10.20); floors do not deduct partition walls and single <= 0.30 m2 columns/piers/holes, upturns <= 300mm merge (4.10.25); > 300mm executes wall waterproofing (4.10.16); foundation upturned beams merge by developed area (4.10.26). In BOQs, roof protection uses "rigid roofing layer" with its function described (GB/T 50854-2024, J.6.5); foundation/floor fine-stone concrete protection uses "fine-stone concrete floor" (J.6.11); reinforcement mesh listed separately (J.6.12); Beijing lists protective-layer items separately (2021: 9-265~267; 2024: A-9-264~267), all in m2.
- ←
Quantity calculation rules for roofing and waterproofing works: tiled roofs by sloped area, waterproofing upturns merged, drainage components by length/count (Beijing DB11/T 2382-2024 Clauses 4.10.19 to 4.10.28 + GB/T 50854-2024 Appendix J)
Tiled and profiled-sheet roofs are measured by the sloped area of the design dimensions, without deducting roof chimneys, vent-cowl bases, flues, small dormer windows and valley gutters (the dormer-window overhang is not added); sloped-roof waterproofing by the sloped area and flat roofs (including slope-forming) by horizontal projection; the upturned parts at parapets, expansion joints and skylights, and the developed areas of valley gutters, eaves gutters, overhanging eaves and canopies, are merged into the roof quantity; downpipes by length, and hoppers, drainage outlets, vent cowls etc. by count; floor waterproofing with upturns not exceeding 300 mm merged into the floor quantity, above 300 mm executed as wall waterproofing; movement joints, joint sealing and waterstops by length, pile heads by count, protective layers by area.
- ←
Norm items and measurement for shear-wall concealed columns, concealed beams, and coupling beams (Beijing DB11/T 2382-2024: concealed members merge into the wall; shear walls route by section height-to-thickness ratio into short-leg walls/columns/straight walls)
Per Beijing DB11/T 2382-2024: concealed columns and beams integral with the wall execute the wall items (quantities merge into the wall, no separate column/beam items); shear walls route by section form — thickness <= 300mm with max limb height/thickness ratio > 4 and <= 8 take short-leg wall items, <= 4 may take column items, the rest straight walls (e.g., A-5-24); Beijing sets no separate coupling-beam entry — practice merges them into the wall. Wall-beam interface: beam length to the wall face, wall height to the beam soffit.
- ←
Septic tank pricing by applying quota line items (Beijing DB11/T 2382-2024 structures works): line-item selection along the three construction routes of cast-in-place concrete / masonry / GRP factory-made tanks, work content already included, and measurement adjustment rules
Under the Beijing DB11/T 2382-2024 system a septic tank belongs to the structures works and is priced by a composite line item per tank ("zuo"): cast-in-place concrete tanks use Table F.1.5-2.4 (F-1-57 to F-1-79, selecting size number / effective volume / with or without groundwater / H+h earth cover), masonry tanks use Table F.2.3-2.1 (F-2-10 to F-2-23), and GRP factory-made tanks use F.3.2 (from F-3-107, further selecting trafficable / non-trafficable); the items already include earthworks, rebar, waterproofing and covers (factory-made tanks also include the riser and vent pipe) and must not be double counted; formwork is billed separately under the preliminary (measures) items; where the riser height differs from the standard atlas, adjust by the number of risers using the "riser, for each 0.10 m increase or decrease" items; integral precast concrete tanks delivered and installed on site are work items not covered by the quota manuals and are handled through supplementary quota items.
- ←
Scaffolding calculation for water tanks (structures): measurement bases for the inner face of tank walls, the tank floor and birdcage (full-area) scaffolding for the roof slab, and the fee-route determination
First determine the route for tank scaffolding: where the water tank is located inside a building, the scaffolding cost is calculated as comprehensive scaffolding by gross floor area and must not be charged separately; where the tank is an independent work outside the building, the corresponding quota sub-items are applied per the approved scaffolding method statement. For an independent tank, measure part by part: tank walls (inner-face access scaffolding) by the wall area or the vertical projected area of the working face; the tank floor is generally not itemized separately (scaffolding with an erection height not exceeding 3.6 m is already included in the all-in unit rates of the divisional work items); the working-type birdcage scaffolding for the roof slab by the horizontal projected area of the erected zone (in some regions by spatial volume), with the basic lift for clear heights of 3.6 m < H <= 5.2 m and one additional lift per extra 1.2 m above 5.2 m; load-bearing formwork supports for the roof slab are measured separately by contact area, with formwork heights over 3.6 m adjusted "per additional 1 m".
- ←
Pricing steel ladders and the built-in ladders (steps) of inspection chambers: quantities by mass at design-shown dimensions, quota item attribution, and the "already inside the chamber item, not charged again" test
Steel ladders are measured by mass (t) at design-shown dimensions, without deducting holes and without adding welding rods, rivets or bolts (DB11/T 2382-2024 clause 4.7.17 item 1; municipal networks clause 7.4.17); steel ladders execute as "stepped steel ladders", embedded or welded-to-insert rolled-angle treads may execute as sundry steel members (clause 4.7.10). The steps / ladders inside inspection chambers are mostly already in the standard-chamber items' work content (e.g. D4-6-178 "chamber step and cover installation"; railway LY-441 "rung installation") and may not be listed again; where a separate item is truly needed, count in kg by design-shown weight (SJG 111.2-2022 clause 3.2.4); finished steps count by design-shown number (DB11/T 2382-2024 clause 9.3.5 item 6). Standard-chamber ladders are compiled in plastic-steel - differing designs convert the ladder material only, all else unchanged (SJG 181.4-2024 clause 3.1.3).
- ←
Measurement boundaries and bill split of profiled-sheet composite floors (floor decking / rebar-truss decking): the steel sheet floor by horizontal projected area, the concrete above as solid slabs less the sheet volume
The profiled sheet / rebar-truss decking itself takes Annex F "steel sheet floors" (010605001) in m2 on the design-shown laid horizontal projection (no deduction for single columns, piers or holes of 0.3 m2 or less); the cast-in-place concrete above lists separately under Annex E "solid slabs" in m3, deducting the volume occupied by the sheeting and computing the concrete volume changes caused by the sheet profile; slab rebars take the Annex E rebar items in t; shear studs and high-strength bolts stay out of the steel member quantities and list under separate codes.
- ←
Deciding deductions for reserved bolt holes under the two measurement bases of concrete and formwork (including raft / foundation member classification, the 0.30 m2 hole threshold, and the equipment-foundation pocket exception)
Reserved bolt holes in cast-in-place reinforced concrete members are generally deducted under neither basis: concrete per "no deduction for the volume of rebar, bolts, embedded parts or ducts within the member" (GB/T 50854-2024 Annex E E.7.1); formwork per "holes of individual area 0.30 m2 or less in walls and slabs are not deducted, and the formwork to the hole reveals is not added". Reserved bolt hole diameters usually sit far below 0.30 m2, so nothing is deducted. Exceptions: where the individual hole area exceeds 0.30 m2, concrete (on the slab / wall basis) deducts the hole volume and formwork deducts the hole area while adding the reveal formwork; the reserved pockets of equipment foundations (railway and like systems) are deducted in volume.
- ←
Classifying earthworks: separate earthworks (010101) versus foundation earthworks (010102) split by the "preset level", and how large-area replacement fill is classified (GB/T 50854-2024 Annexes A / B)
The single dividing line of earthworks classes is the "preset level" (design outdoor level / soffit level of the external ground build-up / level nominated by the client), regardless of how large the replacement area is: above the line, separate earthworks (010101) bringing the site to the preset level; below the line, foundation earthworks (010102) executed for the foundations. Large-area replacement fill sorts three ways: site-fill type - separate earthworks backfill (010101003, by volume on the cut-and-fill dimensions between the original ground and the preset level, table A.1.1); replacement cushions at or within pits for ground improvement - Annex B ground treatment (010201001, by volume at design-shown dimensions); if counted merely as earthworks, foundation earthworks; site levelling within plus/minus 300 mm of the level - by area.
- ←
Sorting out the measurement of underfloor heating coils (floor radiant heating pipes): the bill measures the net area of heated rooms (m2), the quota measures the design-shown pipe length (m), and the boundary between heating pipes and manifolds
Bill (measurement) basis: GB/T 50856 Annex K table K.4.1 "heating appliances" (code 031004) measures floor radiant heating by net heated-room area in m2. Quota (consumption) basis: floor radiant heating pipe laying is computed by design-shown length in m (e.g. Beijing DB11/T 2382-2024 clause 6.10.76); the two are bridged by the net-area-to-pipe-length contents of table 6.10.76 (pipe OD 16 mm = 6.300, 20 mm = 5.775, in m per m2 of net area). The boundary with manifolds sits at the branch-pipe connections off the distributor: on the heating-pipe side, from the distributor outlet to the collector connection (including the riser from floor level to the connecting fitting); the heat-medium distribution and collection unit (manifold) is listed separately per "set".
- ←
Measurement of metal-surface rust removal (and painting, anti-corrosion): routed by object - plant and piping by area m2, metal structures by theoretical mass t/kg - with the companion rule of matching the unit of the quota item applied
Rust-removal quantities route by the OBJECT treated, not an either-or: plant and piping rust removal is computed by area (m2) on the design-shown surface, metal-structure rust removal by the theoretical mass of the structure (DB11/T 2382-2024 clauses 6.12.8, 6.12.9), and the outcome must match the unit of the quota item applied. Within metal structures a further split applies: general steelwork (hangers, supports, brackets, ladders, railings, platforms) and pipe-rack steelwork measure in kg; steelwork of sections over 300 mm and H sections over 300 mm measure by developed area in m2 (GB/T 50856-2024 Annex M table M.1.1 note 8); pipe surface S = pi x D x L, with fittings, valves, flanges, manholes and nozzle irregularities comprehended and not added. The municipal basis agrees (DB11/T 2382-2024 clause 7.4.51: pipe rust removal and painting on pipe surface area; steelwork rust removal and metal-structure painting on theoretical mass).
- ←
Beijing DB11/T 2382-2024 consumption standard: quantity rules for cast-in-place concrete columns and the setting of column heights (including constructional columns, corbels, concrete-filled steel tube columns, raking columns and core columns)
Per DB11/T 2382-2024 Construction Works Consumption Quota Standard, clause 4.6.6 item 3: cast-in-place concrete columns are computed by volume (m3) at design-shown dimensions, without deducting the volume of rebar and embedded parts. Column heights - beam-and-slab columns from the column base top (or slab top) to the next floor slab top; flat-slab (beamless) columns to the column capital soffit; frame columns from base top to column top; constructional columns from the top of their rooting member to the soffit of their anchoring member, with the wall-toothing part merged into the column body. Corbels attached to columns merge into the column volume; concrete-filled steel tube columns are computed on the internal section area of the tube times the design-shown tube height; raking columns on the column section area times the design-shown inclined centreline length; core columns on the hole section area times the design-shown height.
- ←
Quantity calculation for lightning-protection grounding devices and determination of the number of "groups": grounding electrodes counted by "piece", commissioning of independent grounding devices (up to 6 electrodes) counted by "group", grounding-grid testing counted by "system"
Fabrication and installation of grounding electrodes is counted by "piece" (2.5 m per electrode where the design does not specify); "group" appears only in electrical adjustment and testing: commissioning of an independent grounding device is counted by "group" (applicable ceiling of up to 6 grounding electrodes), and grounding-grid testing by "system". One independent grounding device = 1 group; the number of groups follows the number of "locations", not "total electrodes / 6"; where there are more than 6 electrodes or a grid has formed, count by "system" instead, and electrodes within the grid may not be counted again for testing.
- ←
Prestressed rebar (wire strand) quantity calculation: pre-tensioning vs post-tensioning calibers, curved segments by true length not projection, anchorage adjustments, and railway/highway/municipal differences
Prestressed rebar mass = design length x theoretical unit mass (t): pre-tensioning by member-dimension length; post-tensioning by design duct length adjusted per anchorage type (screw anchors -0.35m; bearing-plate bars +0.15/+0.30m; self-anchoring +0.35m; conical and JM/XM/OVM/QM anchors <=20m +1.0m, >20m +1.8m); curved segments by true arc length, not projection; field cutting length generally does not enter quantities (railway uses design cutting length; highway estimate caliber includes working lengths) — apply each sector's caliber separately.
- ←
Railway 2024 budget quota: item application and quantity rules for driven cast-in-place pile follower (送桩) and splicing of precast piles (TB/T 10823-2024 bridge/culvert volume vs TB/T 10831-2024 housing volume)
In the railway 2024 quotas, whether pile followers (sending piles below grade) and pile splices get their own items differs by volume: (1) In the bridge/culvert volume (TB/T 10823-2024 Volume 2), the pipe-pile sinking items' work content already includes "splice/disconnect and follower driving" — neither follower nor splice books a separate item; square-pile driving items include splicing and follower work, but square-pile joints must be listed separately by count (QY-245 sulphur mastic / QY-246 flange, unit 10 joints). (2) In the housing volume (TB/T 10831-2024 Volume 10), the follower books FY-141 square-pile follower / FY-142 pipe-pile follower (unit 10 m3), and splicing books arc-welding splice items (FY-138/139 square piles, FY-140 pipe piles, unit 10). Follower length runs from the design pile-top elevation to the natural ground level before driving plus 0.50 m; welded splices are counted by the number of pile-head splices required by the design.
- ←
Rebar quantity take-off: outer-surface or centreline length - the 2024 measurement standards expressly adopt the centreline, quota manuals old and new coexist, and how to resolve the difference
Current state of the rebar measurement convention: the 2024 BOQ measurement standards expressly adopt the centreline (GB/T 50854-2024 Table E.6.1; GB/T 50860-2024 Annex A.15.6); quota manuals coexist in old and new editions - Jiangsu 2026 and the new Shaanxi consumption quota adopt the centreline, Hunan 2025 consumption standard computes bent-up bars by outer-surface length without deducting elongation, while Beijing DB11/T 2382-2024 clause 4.6.9 and the like are silent. Resolution principles: BOQ quantities and quota quantities run on two separate tracks and must not be mixed; where the quota is silent, lock "outer surface or centreline" in the explanatory notes or the contract first; the summary-convention setting of the take-off software is a tool-level matter that does not change the applicable rule.
- ←
Bases for determining final account quantities: completed qualifying quantities + measurement certification and sign-off lock-in + measurement method by contract type
The final account quantity (in FIDIC contexts, the Final Statement plus discharge) = the qualifying quantities actually completed by the contractor in accordance with the contract and to be measured, calculated under the contract-agreed national and industry quantity take-off (measurement) standards and supplementary calculation rules; the measurement results certified and signed off by both parties (including documents for interim settlement by construction stage (China's 2020 node-based interim settlement system; no exact international equivalent)) serve as the basis for settlement (GB/T 50500-2024 Clauses 7.1.1, 7.1.8, 10.3.1). Lump-sum contracts adjust only the agreed adjustable contents; re-measurable (unit-rate) contracts measure actual completed quantities; cost-plus contracts calculate cost, fee, and taxes per the agreed method; as-built drawings, changes, site instructions/variation records, and concealed-acceptance records form the chain of evidence for 'actual completion'.
- ←
The "length" value for pile-head cutting/chiseling quantities and comparison of measurement calibers across quota systems (40d, over-cast height, by count)
The "length" of pile-head cutting/chiseling means the height to be cut/chiseled between the as-cast pile top (top of the over-cast/sludge layer) and the design pile-top level; only sub-items measured by volume (m3) require the length (quantity = design pile section area x length); sub-items measured by "count" do not. Design provisions govern; absent design provisions: the railway buildings quota takes chiseled precast pile heads at 40d (d = main bar diameter, the larger where they differ) and bored piles at 0.50 m; provincial consumption quotas take bored piles at 1 m and driven/screw piles at 0.5 m; railway bridge culverts count ring-cut pile heads by pile count tiered by diameter (not by volume). First fix the applicable quota system, then check the sub-item's measurement unit; calibers must not be mixed across systems.
- ←
JTG/T 3832-2018 highway budget quota: suspension-bridge main cables and steel box girders measured by mass in t, and measurement units of suspension-bridge work items
Per Section 10 steel structures (lower volume) of JTG/T 3832-2018 "Highway works budget quota": the main cable (parallel-wire strands, hangers, ties, strand bundles, etc.) and the steel box girder are both measured by mass in t, quota tables compiled per 10 t; the cable mass excludes anchorages and PE/sleeve protection materials (their costs are in the finished-product price); steel box girder mass = box girder (incl. internal diaphragms) + deck plates (incl. transverse ribs) + cross beams + steel anchor boxes; within the suspension-bridge system cable clamps/saddles/cable casings/anchorages are in t, hauling/catwalk/wrapping in m (single-side length), saddle housings per set (1 set per main saddle) — each item must be distinguished when compiling.
- ←
Measurement caliber for drainage pipes and rainwater-inlet connectors: computed by design centerline length (to centers, no deduction of auxiliary structures), contrasted with "manhole-deducting" local calibers and with workmanship provisions
Under the current national standard (GB/T 50857-2024) and Beijing (DB11/T 2382-2024), drainage pipes and inlet connectors are computed by design centerline length, without deducting the lengths occupied by rainwater inlets, manholes, and other auxiliary structures — measured to centers; there is no "measure to inner face (edge) then deduct" method; only under "manhole-deducting" calibers such as Shenzhen SJG 181.4-2024 is the length "manhole-center to manhole-center minus the per-manhole tabulated deduction", and even there the datum is center-to-center with tabulated values, not edge measurement. The workmanship rule "pipe end flush with inlet inner wall" is an installation requirement, not a takeoff datum.
- ←
Difference between grounding electrodes and grounding busbars, and their BOQ listing, measurement, and pricing calibers (GB/T 50856-2024 lightning protection and grounding devices, Table D.10.1)
The grounding electrode is the current-dispersing element, measured by design quantity in "pieces (blocks, sets)"; the grounding busbar is the connecting conductor, measured in "m" by total design length plus reserve (additional) length — separate items with different units, not interchangeable in pricing. Additional lengths of busbars, down-conductors, and lightning networks per Table D.17.3-6; TB/T 10829-2024 (per 10 m) and SJG 181.7-2024 (per linear meter) both add 3.9% to design length (turns, undulations, obstacle avoidance, splices).
- ←
Whether pipe-trench backfill quantities deduct the pipe volume: the 500 mm diameter demarcation rule and comparison of standards' calibers
Whether trench backfill deducts the pipe volume is demarcated at (nominal) diameter / pipe structural width 500 mm in most systems: <=500 mm no deduction; >500 mm deduct per the quota appendix table (m3/m) or the actual volume of pipe and base/cushion, with some systems (Shenzhen) also including chambers and other auxiliary structures; Hunan 2025 requires deducting the full pipe volume when backfilled with purchased sand/gravel; Beijing DB11/T 2382-2024 municipal/landscape caliber is "minus pipes and structures" with no 500 mm exemption. The text of the standard volume adopted governs.
- ←
Bill-of-quantities listing of railings, panels and handrails (GB/T 50854-2024 Annex Q table Q.3.1, code 011503) and mapping to the Beijing 2024 consumption standard quota items: glass panels, finished railings and cast-iron scroll railings, dual measurement by area and by length, and the rule that bend lengths enter the centreline length
Railing, panel and handrail decoration lists under GB/T 50854-2024 Annex Q table Q.3.1 (code 011503); material and post-cap differences go into the item description, not separate codes. Under Beijing DB11/T 2382-2024, railings (panels) are measured by area m2 at design-shown dimensions and handrails and accessibility railings by handrail centreline length m (bends included), with no addition for parts embedded in the structure; where railing / panel and handrail are installed as one unit, the railing / panel items execute and the handrail item does not. Item mapping: metal stair railings (panels) A-15-52 to A-15-61 mostly m2 (only A-15-60 accessibility railings by m), metal stair handrails A-15-62 to A-15-64 by m, hardwood handrails in the hardwood railing table A-15-67 to A-15-69 by m.
- ←
Sonic logging pipe (cross-hole sonic test tube) quantities for bored piles: tubes per pile banded by diameter (JGJ 106-2014 / TB 10218-2019) and embedment length caliber (pre-driving natural ground to pile tip plus 0.5m, no extra overpour)
Tube counts per pile take the code minimums banded by diameter: d <= 800mm at least 2; 800 < d <= 1600mm at least 3; d > 1600mm at least 4; d > 2500mm preferably more (Guangdong requires >= 5). Embedment length per the common norm caliber runs from "natural ground level before driving" to "design pile tip level plus 0.50m" (mass caliber converts to t by the pipe's theoretical mass per meter, excluding embedded plates and other fixings); the overpour and empty-hole sections above the design pile top are already included — no additional overpour length.
- ←
Measurement units for landscape plant installation (plant/m/m2/clump), plant specification terminology, and item-characteristic description essentials (GB/T 50858-2024)
Plant installation measurement units are fixed by category and planting method, not self-invented: trees/single-shrub/scattered bamboo/palms/climbers by plant (count), massed shrubs/flower ground-cover by m2, hedges by m (hedge length, not plant count), clumping bamboo/single-clump aquatics by clump (GB/T 50858-2024 Appendix A Table A.3.1, 4.2.5). Plant specification terms have unified definitions: DBH = trunk diameter at 1.3 m above ground (landscape caliber, not highway 1.2 m); crown diameter = mean of max and min vertical-projection diameters; ground diameter at 0.1 m; trunk diameter at 0.3 m; meter diameter at 1.0 m; plant height = ground to top. Item characteristics must be standard, concise, accurate, complete (4.1.2); survival rates above CJJ 82, shaping requirements, and grass-brick inlay ratios must be stated in characteristics.
- ←
Quantity-calculation caliber for aluminum (metal) panel curtain walls: computed by the design outer surface / frame-perimeter area, not by the developed fabrication area of the aluminum sheet; projected area is the unitized-curtain-wall caliber, and developed area applies only to rib-stiffened full-glass walls (BOQ and quota calibers compared)
Component-type metal-panel (aluminum) curtain walls are computed by the design-shown outer surface area (for vertical planes, the frame-perimeter area), not by the developed fabrication area of the aluminum sheet; unitized curtain walls by the design frame-perimeter projected area; developed area applies only to rib-stiffened full-glass walls (TB/T 10831-2024 Vol. 10 notes). The folding allowance of aluminum panels is considered in material price/loss, not added to area (Jiangsu 2026 sub-item note); special-shape (curved/faceted/respirating) walls adjust labor consumption rather than recomputing developed area (DB11/T 2382-2024 Clause 4.13.14). The BOQ (GB/T 50854-2024 Table M.6.1) and quota (e.g., DB11/T 2382-2024 Clause 4.13.26) calibers are computed separately and must not be mixed.
- ←
Measurement units of highway subgrade site-clearing items: JTG/T 3832-2018 budget quota 1-1-1 tree felling and stump removal (10 trees), topsoil stripping (100 m3), and BOQ calibers
JTG/T 3832-2018 "Highway works budget quota", Chapter 1 Section 1, item 1-1-1 "tree felling, stump removal, grassing, topsoil stripping": felling/stump removal measured per 10 trees; topsoil stripping per 100 m3 (dozer power bands within 90 kW / within 135 kW); shrub clearing per 1000 m2 (under 220 shrubs per 1000 m2 sparse, above dense); grassing per 1000 m2; bamboo-root digging per 10 m3 (by pit volume). Section notes: topsoil stripping and grassing quotas must not be applied together; haul of stripped topsoil follows the earthwork haulage quota. BOQ measurement per the contract; DB14/T 1319-2021 Section 202 Table 202: 202-1-a site clearing (incl. topsoil) lump-sum, 202-1-b tree felling (breast-height diameter over 10 cm) per tree.
- ←
Measurement linkage between GB/T 50500-2024 and the nine measurement standards GB/T 50854-50862-2024: responsibilities, cycles, and the division of procedures (procedures to the pricing standard, quantity take-off to the measurement standards)
GB/T 50500-2024 and the nine measurement standards (GB/T 50854-50862-2024) interlock by mutual delegation on measurement: 50500 7.1.1 states quantities "shall be calculated per the national and industry measurement standards and supplementary rules agreed by the parties" (take-off to the measurement standards); 50854 3.0.2 reciprocally requires measurement during implementation to also comply with GB/T 50500 (procedures to the pricing standard). Measurement responsibilities (contractor written submission -> employer written verification -> mutual deemed acceptance, 7.1.5/7.1.6; per-cycle summary sign-off 9.4.13), measurement cycles (cycle aligned with payment cycle, monthly fallback when unclear, 9.4.1; milestone measurement 7.1.2; price-adjustment segmented measurement 7.1.3) are all governed by 50500 Chapter 7 and Section 9.4; the nine standards cover only item classification, units, and appendix calculation rules (50854 4.2.6: per Appendices A-Q).
- ←
Brick permanent formwork (brick mold / brick side form): quantity calculation and pricing calibers — by volume, priced under brick-foundation items, plastering separate, with regional preliminaries differences
Brick formwork quantities are computed by design-shown volume (m3): centerline length around the wrapped member x masonry height x design thickness, with brick-foundation rules (no deduction of spread-footing T-joint overlaps or single holes <= 0.30 m2). The mainstream pricing applies the "brick foundation" item — expressly in railway TB/T 10831-2024, Shenzhen SJG 111.2-2022, and Shaanxi's new draft; inner-face plastering prices separately under interior general plaster (Shenzhen: labor x 0.90); positions with brick formwork take no concrete side formwork. Regional difference: Shenzhen's building system lists brick formwork and its plastering under measures — concrete/reinforced formwork (SJG 77-2020, 5.5.3).
- ←
GB/T 50854-2024 removes "beam-and-slab": beams and slabs are coded and listed separately (combined application for solid slabs)
GB/T 50854-2024 has removed the "beam-and-slab" BOQ item (the 2013 edition's 010505001, by the sum of beam and slab volumes, repealed); beams list under "cast-in-place concrete beams" and ordinary floor slabs under "solid slabs", coded separately; at beam-slab intersections the slab counts to the beam's side face and the beam at full depth — the total is unchanged but the BOQ structure is split.
- ←
Quantity rules for smoke barriers (GB/T 50854-2024 Table N.3.1, m2) and compliance check of the droop depth against the smoke reservoir (GB 51251-2017)
Smoke barriers are a "other ceiling decoration" BOQ item (code 011303003), unit m2, computed by area per design dimensions: area = arrangement length x droop depth (e.g., 1.7 m x 1.3 m -> 2.21 m2; identical units accumulate by count). The droop depth shall not be less than the smoke-reservoir depth — natural smoke exhaust >= 20% of clear height and >= 500 mm; mechanical smoke exhaust >= 10% and >= 500 mm (GB 51251-2017 Clauses 4.2.2, 4.6.2).
- ←
Applying TB/T 10823-2024 for double-wall steel cofferdam wall infill and bottom-seal concrete (QY-64) and the quantity boundary against pile-cap concrete
Double-wall steel cofferdam (floating steel caisson) wall infill and bottom-seal concrete uses item QY-64 (unit 10 m3, work content: concreting), belonging to cofferdam and island-building auxiliary works; the volume notes state the double-wall cofferdam sinking quota excludes wall-infill concrete, which must be booked separately. Wall infill (cofferdam cavity), bottom seal (below the cap underside), and the pile cap (above the seal top) occupy non-overlapping spaces; the cap volume is measured from the seal top — no double counting.
- ←
Municipal road surface course quantity calculation: manhole and rain-inlet areas not deducted; surface with curb stones deducts curb stones (GB/T 50857-2024 Table B.3.1)
Per GB/T 50857-2024 "Standard for measurement of municipal works" Appendix B Table B.3.1 "Road surface course (code 040203)", cement concrete (040203007) and asphalt concrete (040203006) share the same rule: computed by area per design dimensions, without deducting areas occupied by various manholes; surface courses with curb stones shall deduct the curb-stone areas (unit m2). That is, manhole and rain-inlet areas are never deducted; the old GB 50857-2013 Table B.3 rule was identical (that edition is abolished) — no change between editions.
- ←
Item-selection determination for graded-gravel replacement fill in excavation pits: the distinction among replacement-fill ground treatment (A-2-4 gravel spreading), foundation backfill and bedding layers, and quantity calculation (Beijing DB11/T 2382-2024 basis)
Under the Beijing DB11/T 2382-2024 "Construction Consumption Standard": the strengthening of soft or non-uniform soil layers after pit excavation is itemized as "replacement-fill ground treatment" (Appendix A, Table A.2.1-1); graded gravel uses A-2-4 "spreading, gravel" (m3; work content: spreading in layers, leveling, compaction), and sand/stone-chip replacement uses A-2-3. The replacement-fill sub-items exclude excavation of the in-situ soil (executed separately under Clauses 4.2.1 to 4.2.27); quantities are calculated by volume per the design dimensions (4.3.16). The distinction from backfill and bedding lies in position and design intent, not in material: foundation/room backfill uses backfill sub-items (e.g. A-1-38 graded sand-gravel; quantities calculated under 4.2.21/4.2.22), and bedding layers are itemized under the bedding tables A.4.5 and A.5.1-1 - the three must not be interchanged.
- ←
Steel sheet pile quantities and pricing calibers: driving/extraction by design pile-length mass (t); where area applies; usage fees and guide-frame install/removal across norm systems
In the main domestic systems (municipal/building/railway/highway), driven-and-extracted (retaining) steel sheet pile quantities are computed by the mass of the design pile length (effective length) in tons, not by area; usage fee = quantity (t) x duration x unit time price, with ton-day, ton-month, and per-quarter time calibers; guide frames are installed/removed per design horizontal length in linear meters. Area applies only in three cases: area-to-mass conversion, cofferdam internal-strut conversion (railway: 870kg per 10 m2 of single-layer struts), and international measurement (RICS NRM by total surface area of pile length).
- ←
TB/T 10831-2024 railway housing works quota: classification of cast-in-place slabs into beam-slab / flat-slab / plain-slab and the pricing rule of monolithic beams and slabs (FY-503~516)
Per TB/T 10831-2024 "Railway works budget quota, Volume 10: housing works", volume notes "10. Quantity calculation rules" item (7): beam-slab = slab cast integrally with primary and secondary beams, "computed as the sum of beam and slab volumes" — with monolithic casting the beam volume is merged into the beam-slab item and the beam is not applied separately; flat-slab = slab bearing directly on columns (with drop panels), "computed as the sum of slab and drop-panel volumes"; plain slab = slab bearing on walls (or ring beams), "computed as the solid volume of the slab". Corresponding items: FY-503~507 beam-slab, FY-508~512 flat-slab (both in five thickness steps <=100/<=150/<=200/<=300/>300 mm, unit 10 m3), FY-513 plain slab, FY-514/515 sloped roof slabs (with beams / without beams), FY-516 arch slab.
- ←
Quantity-calculation rules and itemizing method for busways (low-voltage enclosed plug-in busway / common-enclosure busway): by centre-line length, supports included, accessories listed separately by count - distinct from strip busbars
Common-enclosure busway and low-voltage enclosed plug-in busway installation quantities are calculated by the centre-line length of the dimensions shown on the design (m); support installation is included in the installation consumptions and not listed separately; tap-off (plug-in) boxes, end (staring) boxes, copper-busbar expansion joints, supporting insulators etc. are listed separately by the design quantities, and flexible copper connections are calculated per "phase/unit". Strip busbars follow different rules: calculated by per-phase length (including reservations) - 0.30 m/end for busbar terminations and 0.50 m/end for terminations to branch lines or equipment. Basis: DB11/T 2382-2024 Clauses 6.4.21-6.4.24 and Table 6.4.23; the BOQ basis is GB/T 50856-2024 Appendix D, Table D.3.1 (code 030403).
- ←
Item description vs method of measurement in the BOQ: the item description column must not stipulate the method of measurement; supplementary rules belong in the BOQ calculation-rules statement and apply as contractual agreement
Item description and method of measurement are two parallel, independent elements of the bill of quantities (BOQ): the item description must be drafted in accordance with the annexes to the measurement standard and the actual works, its function being to fix the all-in unit rate; quantities must be computed under the method of measurement prescribed in the annexes (mandatory provisions of codes) — the item description column must not stipulate the method of measurement. Where supplementary rules are genuinely required, they must be set out in the BOQ calculation-rules statement (naming the national and industry standards adopted, with their titles and numbers, or setting out the detailed supplementary rules) and made part of the tender documents/contract documents, applying as "contractual agreement". Hierarchy of measurement bases: contractual agreement -> national standard matching the contract type -> industry/local standard.
- ←
Cable-tray support (bearing frame) quantity calculation: measured in kg, count by support/hanger spacing, unit mass by section-steel theoretical mass
Cable-tray supports are measured by design finished mass in kg and itemized separately (GB/T 50856-2024, 3.0.10; SJG 181.7-2024, SJG 111.4-2022); counts follow support spacing — 1.5-3m horizontal, <= 2m vertical, densified at bends/branches/panel entries/expansion joints (GB 50397-2007, GB 50606-2010, GB/T 51239-2017, DB11/T 1832.17/19, etc.); unit mass = sum(member net length x unit theoretical mass), unit mass (kg/m) = section area (mm2) x 0.00785; factory supports (incl. seismic) count per piece/set without mass conversion.
- ←
Building automation system (BAS) / HVAC automatic control - BOQ item setting and appendix attribution under GB/T 50856-2024 Appendix E (code 030503)
HVAC automatic control / building automation (BAS) corresponds to the "building automation system" (code 030503) in GB/T 50856-2024 and is listed under Appendix E Building Intelligentization Engineering; items are set per Table E.3.1 (communication network control equipment 030503001, controllers 030503002, etc.; the unit of measurement is "unit (set)" and quantities are calculated as the numbers shown on the design drawings). Civil building automation systems apply Appendix E, while industrial automation systems shall be itemized under Appendix F Automation Control Instrument Installation Engineering; conduit, raceways, cable trays, junction boxes and electrical equipment associated with the intelligentization works shall be itemized under Appendix D Electrical Equipment Installation Engineering and must not be double-counted in the intelligentization BOQ.
- ←
Ventilation duct quantity calculation and classified measurement: whether supply / exhaust / fresh-air ducts are computed separately, the developed (unfolded) area rules, BOQ listing, and quota-norm tiering basis
Ducts are computed from design dimensions as developed (unfolded) area (m2): no deduction is made for inspection ports, measuring ports, supply openings or suction openings; length is taken along the design centreline (main and branch ducts divided at their centreline intersections), including the length of elbows, tees, reducers and rectangular-to-round adapters, but excluding the length occupied by components. Supply, exhaust and fresh-air systems are governed by one and the same rule set — there are no per-system differences in the calculation method; "separation" is expressed at the BOQ listing and rate build-up levels — listed by item description (use/name, material, shape, size, plate thickness, joint form), and split when quota line items are applied according to tiering factors such as joint form and size; the system itself is not a tiering factor.
- ←
GB 50205-2020 Annex J steel structure measurement: design-quantity rules (J.0.2), quantity = design quantity x wastage adjustment factor (J.0.3), and two-decimal rounding
Design quantities per GB 50205-2020 Annex J.0.2: sections/pipes/tendons by design length x unit mass per product standards; plates by area (volume) x unit mass; bolts/studs by count (sets) or converted mass (high-strength hex: 1 bolt + 1 nut + 2 washers; torshear: 1 + 1 + 1); welds by deposited metal; gusset plates by design area, irregular plates by circumscribed rectangle; bolt holes/bevels/segmental notches/beam-column gaps not deducted (equipment-pipe openings < 0.1 m2 also not). Quantity = design quantity x wastage factor (J.0.3, per table; complex structures negotiable); values to two decimals, rounded.
- ←
Pricing position for post-cast strip formwork under Beijing DB11/T 2382-2024: measurement on contact area, dedicated items by position (never the beam-and-slab item), and treatment of the formwork height exceedance
Post-cast strip formwork and supports are measured on the contact area with the strip (clause 4.17.6 item 6); dedicated items apply by position - foundation strip A-16-41/42, wall strip A-16-43, slab-type strip A-16-44 - and the beam-and-slab, flat slab and flat plate items (A-16-33) must not be used. The quick-closure expanded-metal mesh for the side stop-ends is already contained in the post-cast strip concrete items (foundation slab, beams, walls 4.2 m/m3; floor slabs 2.1 m/m3) and is not priced separately. The height-exceeding part follows its host member under the "each additional 1 m above 3.60 m" items, computed on the whole area of the exceeding part; an exceeding part under 1 m still executes the per-additional-1 m item (clause 4.17.1 item 4).
- ←
Quantity measurement of chair bars (iron horses, support rebar): the position that auxiliary rebar not required by the design is not measured separately, the setting method when no construction method statement exists (diameter / spacing / height), and per-piece weight conversion (theoretical mass 0.00617d2)
Chair bars, diagonal bracing bars, anti-floating bars, packing steel and other auxiliary rebar not required by the design are excluded from bill-of-quantities measurement (GB/T 50854-2024 Annex E, GB/T 50857-2024 Annex J.2.1, GB/T 50860-2024 Annex A.15.8); support rebar fixing positions where required by the design (including by code) is merged into the rebar quantities. Beijing DB11/T 2382-2024 absorbs chairs, supports and positioning bars into the rebar fabrication consumption (where data is unavailable, taken comprehensively at rebar wastage plus auxiliary rebar together equal to 5% of total rebar). Without a method statement, convert weight per piece: single-piece length about 2 x slab thickness + 0.2 m (120 mm slab = 0.44 m/piece), theoretical mass 0.00617d2 (d8 = 0.395, d10 = 0.617, d12 = 0.888 kg/m); at 1 piece/m2 with d8 about 0.174 kg/m2 (a 5000 m2 example totals 868.736 kg, about 0.869 t).
- ←
Work-item BOQ listing for pools/chimneys in structures works: GB 50860-2013 Table A.1 pools (070101) and Table A.6 chimneys (070106) — codes, characteristics, and measurement boundary rules
Pools per GB 50860-2013 Appendix A Table A.1 (code 070101) have 5 BOQ items (floor slab/wall/roof slab/internal columns/partition walls); chimneys per Table A.6 (070106) have 4 items (foundation/shaft/insulation/lining); concrete parts measured in m3 by design dimensions, without deducting reinforcement, embedded parts, and holes <= 0.3 m2 each; table-note boundary rules (wall-base-beam boundary, splayed footing, column capital/pedestal merging, shaft-seat attribution) must be executed verbatim; reinforcement borrows GB 50854 items; formwork per 4.2.7 chooses once per bid section between merging into concrete unit prices and separate preliminary items (m2).
- ←
Appendix D “Pricing Statements” of GB/T 50500-2024: required contents of the four statement tables and dispute risks of omissions (tender price ceiling / tender (priced offer) / final account statement + method of measurement statement for the bill of quantities (BOQ))
GB/T 50500-2024 Appendix D has four statement tables: D.1.1 tender price ceiling preparation (review) statement must include project overview, scope, basis of preparation (review), special requirements (if any), and other issues to be explained; D.2.1 tender (priced offer) statement must include scope, item description (work item specification), planned duration, site conditions, project execution plan (construction methodology and site organization) features, and other issues to be explained; D.3.1 final account (interim) preparation (review) statement must include project overview, scope, basis of preparation (review), and other issues; D.4.1 statement of method of measurement for the BOQ must specify the names and numbers of the national/industry measurement standards adopted and list supplementary rules of measurement (with 4.1.3). Omitting basis details, scope delimitation, supplementary rules of measurement, and explanations of price and percentage rate determination (GB/T 51095-2015 8.2.3) are high-frequency final account dispute triggers.
- ←
Quantity measurement of high-pressure jet grouting cut-off walls: holing by design pile length, grouting by design cross-section area times pile length in volume, cement dosage being a material consumption parameter only; overlaps, secant interlocking and re-jetting between piles are never measured twice
Quantities of high-pressure jet grouting cut-off walls follow the dual position of "holing by length, grouting by volume": holing is computed in m on the design effective pile length plus the designed additional grouting length; grouting is computed in m3 on the design pile cross-section area times the pile length plus the designed additional grouting length. Cement dosage is a quota material consumption parameter (used for the "per 1% increase or decrease" adjustment), not a quantity measurement basis. Overlaps, secant interlocking and joint re-jetting of jet grout piles between retaining piles are neither deducted from nor added to the quantities (GB/T 50854-2024 B.3.11, GB/T 50857-2024 B.6.4).
- ←
Railway 2024 quotas: station-yard volume machinery travel-track laying (ZY-112/113) vs the track volume's laying quotas (GY series) — differences and measurement calibers
Laying travel tracks for freight-yard handling machinery uses Chapter 5 "machinery travel-track laying" of TB/T 10834-2024 Volume 13: ZY-112 (50 kg/m) and ZY-113 (60 kg/m), unit 100 m, base prices 49,511.72 / 57,313.30 yuan, all rail materials included; laying railway track uses Chapter 1 of TB/T 10825-2024 Volume 4, items such as GY-100~105, unit km, quotas excluding rail materials — pair with material quotas. In the estimate summary per TB 10801-2024 Appendix A, "handling machinery foundations and travel tracks" counts in single-track km (1 single-track km = 10 x the 100 m quota unit).