Basic content elements of site instruction / variation record documents: main-text checklist, attachment requirements, and sign-off formalities

Grasp the content of a site instruction / variation record along three dimensions: "main-text elements + supporting attachments + sign-off formalities". DB37/T 5028-2022 Clause 6.3.3 gives the most complete nine-item checklist (cause of the instruction; date of occurrence/completion; submission date; location, dimensions, quantity, and materials, with a logically clear calculation formula; execution basis; brief description of the fact and completion status; explanatory drawings and photos; review opinions of the supervision agency and the construction employer; signatures and seals of the contractor's handling person and project manager). T/CAEC 006-2024 distinguishes the content and attachments of quantity instructions from those of price instructions; a price instruction is valid only after joint sign-off (countersignature) by the construction employer, contractor, and supervision unit. Quantity calculation formulas, correspondence with original vouchers, a complete signature chain, and all three dates present are the gaps most easily attacked in final account review.

Applicable Codes

  • DB37/T 5028-2022 建设工程监理工作规程
  • T/CAEC 006-2024 建筑工程监理文件资料管理标准
  • T/SDJZXH 004.1-2022 城市轨道交通工程监理工作标准(通用篇)
  • DB37/T 5130-2018 建设工程造价咨询服务规范
  • GB/T 51262-2017 建设工程造价鉴定规范

Topic Positioning

What basic content elements a site instruction / variation record document should contain — an actionable content checklist drawn from supervision working rules, supervision document management standards, and cost consultancy service specifications, for checking completeness when compiling and reviewing site instruction / variation record sheets and when examining such records as evidence in construction cost expert assessment (judicial appraisal).

Core Conclusions

Grasp the content of a site instruction / variation record along three dimensions: "main-text elements + supporting attachments + sign-off formalities":

  1. The most complete nine-item checklist (DB37/T 5028-2022 Clause 6.3.3): cause of the instruction; date the fact occurred or was completed; submission date; location, dimensions, quantities, and materials (quantities should have a logically clear calculation formula); basis for executing the fact (written documents should be attached); brief description of the fact and completion status; attached explanatory drawings and photos; review opinions of the project supervision agency and the construction employer; signatures and seals of the contractor's handling person and project manager.
  2. The supervision industry's minimal four elements (T/SDJZXH 004.1-2022 Clause 10.6.1): the item, the basis, the calculation process and result, with measurement data, sketches, and site photos or video attached when necessary.
  3. Type-specific refinement (T/CAEC 006-2024): a quantity instruction contains the cause, basis, calculation rules and details, and the review opinions and joint sign-off (countersignature) of all parties; attachments should include quantity take-off (measurement) details, approved design change (designer-issued variation) orders or claim submission documents, site measurement video, and acceptance certificates. A price instruction contains the cause, basis, price content and quantity, and review opinions of all parties, and is valid only after joint sign-off (countersignature) by the construction employer, contractor, and supervision unit.
  4. Cost consultancy perspective (DB37/T 5130-2018 Clause 7.6.4): date, cause, and reason of the occurrence, with attached drawings, video material, and calculation formulas, plus the confirmation formalities and date.

Practical points: the calculation formula is the vital gate (an instruction with only conclusions and no process is the most likely to be returned); original vouchers must be numbered to correspond to the instruction sheet; any missing link in the signature chain (handling person -> project manager -> discipline supervisor -> chief supervision engineer -> construction employer) weakens its validity; the three dates — occurrence, submission, and confirmation — must all be present, and late submission may be deemed a waiver of rights.

Applicable Boundaries

Applies to compiling, reviewing, and completeness-checking site instruction / variation record sheets during the construction stage, and to examining such records as evidence in settlement and construction cost expert assessment (judicial appraisal). The local/association standard clauses (DB37/T, T/CAEC 006) apply directly in their respective regions/industries and serve as reference elsewhere. Procedures for design change (designer-issued variation) orders and claim reports follow their respective clauses and are outside this card's scope.

Further Reading

See DB37/T 5028-2022 "Working rules for construction project supervision" Clause 6.3.3 (nine items) and Clause 6.3.2 (scope of application of commercial (priced) variation records); T/CAEC 006-2024 "Standard for management of construction supervision documents" Clauses 7.2.8 and 7.2.9 (quantity instructions and price instructions); T/SDJZXH 004.1-2022 "Working standard for urban rail transit engineering supervision (general part)" Clauses 10.6.1 and 10.6.3 (four elements and the site instruction / certification procedure); DB37/T 5130-2018 "Specification for construction cost consultancy services" Clause 7.6.4; related: GB/T 51262-2017 "Code for construction cost expert assessment" Section 5.9 (assessment of disputes over site instructions and certified records).