Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Pricing and construction cost expert assessment rules when the price is not confirmed in a site instruction and certified record (GB/T 51262-2017 5.9 tiered pricing)

Price is not a statutory mandatory element of a site instruction and certified record, but the record's completeness determines the settlement path and dispute risk: with both quantity and price, compute directly per the site instruction and certified record (strongest effect); with quantity only and no price, the labor unit price is uplifted by about 20% against the corresponding labor unit price of the appraised project (industry practice), and materials and machine-shifts are priced per the corresponding project prices; with only a total amount, price per the total amount; where the quantity of miscellaneous works does not match the actual completion, compute per the actually completed quantity. With neither quantity nor price but only the matter itself, the appraiser issues an inferential opinion if negotiation fails. Dayworks without a unit price use the contract unit price; if the contract has none, the market day-rate of the corresponding trade is uplifted; where the contract has no applicable/similar price, determine per the cost-plus-profit principle. A certified record of the price must be jointly signed by the employer, contractor, and the supervising engineer to be valid.

Applicable Codes

  • GB/T 51262-2017 建设工程造价鉴定规范
  • T/ZBD 100.4-2023 建设工程造价鉴定作业指引
  • GB/T 50319-2013 建设工程监理规范
  • T/CAEC 006-2024 建筑工程监理文件资料管理标准
  • GB/T 50500-2024 建设工程工程量清单计价标准

Topic Positioning

The standard answer to "must the price be confirmed simultaneously" in disputes over site instructions and certified records: price is not a statutory mandatory element, and the completeness of the site instruction and certified record determines the pricing path and effect level.

Core Conclusions

GB/T 51262-2017 Clause 5.9.1 tiers: (1) quantity + unit price complete -> compute directly per the site instruction and certified record, strongest effect; (2) quantity only, no price -> the labor unit price is uplifted against the corresponding project labor unit price (about 20% by practice), materials and machine-shifts priced per the corresponding project prices; (3) total amount only -> per the total amount; (4) where the quantity of miscellaneous works does not match the actually completed quantity -> per the actually completed quantity. Clause 5.9.2: where the employer only signed "received" without agreeing but the contractor has evidence of completion, the appraiser may issue an opinion listed separately; with neither quantity nor price but only the matter, the appraiser issues an inferential opinion if negotiation fails. Dayworks without a unit price use the contract unit price; where the contract is silent, the market day-rate of the corresponding trade is uplifted (T/ZBD 100.4-2023 4.5.1); where the contract has no applicable/similar price, the Engineer (chief supervising engineer under China's supervision regime) determines the unit price per cost plus profit upon failed negotiation (GB/T 50319-2013 6.3.3). A certified record of the price must be jointly signed by three parties to be valid (T/CAEC 006-2024 7.2.9).

Applicable Boundaries

Applies to disputes where the site instruction and certified record is established but the price element is missing; not applicable to variations with no signature traces; contract provisions prevail, and the 20% uplift is a practice reference value. In practice: sign the price if possible; failing that, lock the pricing principle; at worst, lock the quantity.

Further Reading

GB/T 51262-2017 Clauses 5.9.1-5.9.2; T/ZBD 100.4-2023 Clause 4.5.1; GB/T 50319-2013 Clause 6.3.3; T/CAEC 006-2024 Clauses 7.2.8-7.2.9; GB/T 50500-2024 Clauses 7.5.3-7.5.6, 8.1.1.