Full workflow of daywork (casual labor): sign-off, measurement, pricing, and cost control
Daywork (casual labor) management hinges on "instruction first, then work, same-day signing, time-limited confirmation": first a written instruction from the owner/supervisor; sign only within allowable scope (response to unforeseeable conditions, removal of underground obstacles, quantities requiring on-site determination); four categories are prohibited. Hours count only direct workers (from arrival on site, less meal breaks; gang foremen included; labor leaders and QC excluded); unit prices follow the contract daywork schedule with quantity-price separation—no on-the-spot bargaining; cost control via four gates: ex-ante unit price schedule and approval authority, in-process same-day sign-off + ledger + imagery, total-amount alerts, and ex-post monthly reconciliation.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- DB14/T 1319-2021 公路工程标准工程量清单及计量规范
- T/SDJZXH 004.1-2022 城市轨道交通工程监理工作标准
- GB/T 51262-2017 建设工程造价鉴定规范
Topic Positioning
Answers the full workflow rules for on-site casual labor ("daywork" in cost terminology)—sign-off, measurement, pricing, cost control—for project labor sign-off management, settlement review, and dispute self-checks. Complements the "four elements of valid site approvals" card; this card focuses on daywork-specific rules.
Core Conclusions
- Sign-off precondition: daywork means odd jobs or work requested by the owner, priced at contract-agreed unit rates based on confirmed actual labor days, material quantities, and equipment shifts (GB/T 50500-2024 Article 2.0.16). The management core is "instruction first, then work, same-day signing, time-limited confirmation"—oral arrangements and after-the-fact slips may be rejected by the owner.
- Allowable scope: response measures for unforeseeable site conditions; removal and handling of unforeseeable underground obstacles; parts where the design explicitly requires on-site quantity determination; four prohibited categories—issues foreseeable by normal experience, foreseeable preliminary costs, scheme alterations without approval, and rework costs caused by the contractor itself (supervision standard Article 10.6.1).
- Measurement basis: hours run from workers' arrival on site for the assigned work until return to origin, less meals and rest; only workers directly and competently performing the assigned work are counted—accompanying gang foremen included; labor leaders (foremen) and QC/management staff excluded (DB14/T 1319-2021 A.3.2.1); signed quantities exclude the contractor's own on-site management personnel and pre-existing site equipment (GB/T 50500-2024 Article 7.5.6).
- Pricing and cost control: unit price = base labor price (wages, overtime, allowances, benefits, labor protection) + all surcharges (management fee, profit, taxes, consumables, equipment use and maintenance) (A.3.2.2); on site only quantities are signed—prices follow the contract schedule, quantity-price separation, no bargaining; control gates: ex-ante contract unit price schedule and approval authority; in-process same-day sign-off + consecutively numbered ledger + imagery trail; total-amount alert line (analyze causes upon overrun); ex-post monthly reconciliation traced back to instruction slips. Dispute appraisal: where a slip signs quantity but not unit price, price at the corresponding labor unit rate plus about 20% (GB/T 51262-2017 Article 5.9.1).
Applicable Boundaries
Applies to owner-contractor daywork/casual labor management; where the contract stipulates daywork unit prices, sign-off procedures, approval authority, or time limits, the contract prevails. Not applicable to work that can be priced normally under drawings and contract measurement rules; large-scale damage restoration is handled as a change, not daywork (Article 7.5.2).
Further Reading
See GB/T 50500-2024 Article 2.0.16 (daywork definition), Article 7.5.2 (ten applicable scenarios), Article 7.5.6 (confirmation results and sign-off basis); DB14/T 1319-2021 Appendix A daywork clauses A.3.1-A.3.2 (instruction requirements, hours basis, unit price composition); T/SDJZXH 004.1-2022 Article 10.6.1 (signable and prohibited scope, required slip contents); GB/T 51262-2017 Article 5.9.1 (appraisal rules for approval disputes).
Keywords
- dayworks
- 零星用工
- variation record / site instruction
- 计日工计量
- 计日工单价
- 工时口径
- 签证成本控制