Timing of site instructions and certified records: sign before work in advance, record as events occur during work, and complete retrospective certification within time limits afterwards

Site instructions and certified records are not a binary "before construction / after construction" choice but fall into three timing categories: foreseeable items are signed in advance (sign-first principle, quantities verified afterwards); continuous or non-pre-quantifiable items such as dayworks and work stoppage/idle time are promptly recorded and measured as they occur, with photographic and video evidence kept; verbal instructions must be confirmed in writing promptly, and for claim-type matters, where the contract is silent, a Notice of Claim must be issued within 28 days followed by a claim report within a further 28 days, failing which the claim is deemed waived. Deferring retrospective certification to the settlement stage is the worst choice.

Applicable Codes

  • GB/T 51262-2017 建设工程造价鉴定规范
  • GB/T 50500-2024 建设工程工程量清单计价标准
  • T/SDJZXH 004.1-2022 城市轨道交通工程监理工作标准
  • DBJ41/T 208-2018 建设工程监理工作标准

Topic Positioning

When site instructions and certified records should be handled — the classification criteria, applicable situations, and code basis for the three timing categories of in advance, during work, and after the event; used to guide instruction and record management during construction and prevent settlement disputes.

Core Conclusions

Timing falls into three categories, not a "before/after construction" binary:

  1. In advance (sign before executing): foreseeable, plannable items — temporary/miscellaneous/added work outside the contract scope, responses to unforeseeable conditions and removal of underground obstacles, obvious mismatches between the bill of quantities (BOQ) and actual conditions (e.g., soil classification, flowing sand), employer's approval of material prices, etc. Before implementation, a site survey should be made and the original condition measured and recorded (T/SDJZXH 004.1-2022 Clause 10.6.3); for items whose quantities cannot be fixed in advance, at least the "handling principle + unit price" should be signed first, with quantities verified against actual occurrence.
  2. During work (sign as it occurs): continuous or non-pre-quantifiable items — dayworks record labour/materials/machinery by the day; continuous work requires a certified dayworks report within the agreed time after completion (GB/T 50500-2024 Clauses 7.5.4, 7.5.6); work stoppage and idle-time events must be measured and recorded promptly when they occur, with photographic evidence kept.
  3. After the event, within time limits: the employer's verbal instruction (to be confirmed in writing) must be promptly converted into a written certified record (GB/T 51262-2017 Section 5.9); for claim-type events, where the contract is silent, a written Notice of Claim must be submitted within 28 days and a claim report within a further 28 days, failing which the claim is deemed waived (GB/T 50500-2024 Clause 8.11.3; DBJ41/T 208-2018 Clause 9.4.4). General principle: sign in advance whenever possible, record quantities promptly during work, and complete formalities within 28 days after the event; executing first and signing later, or deferring retrospective certification to settlement, is the worst choice.

Applicable Boundaries

Applies to instruction/claim management in construction contract performance; where the contract stipulates time limits, the contract prevails — 28 days is the fallback where the contract is silent. Not applicable to: foreseeable problems that should have been raised promptly before construction (rework or extra costs from failure to raise them may not be certified), costs of scheme changes that did not go through the review and approval formalities, and extra costs caused by the contractor itself (prohibited scope per T/SDJZXH 004.1-2022 Clause 10.6.1); pure design changes (designer-issued variations) are technical-level changes, and the certified record is the means of confirming their economic consequences.

Further Reading

GB/T 51262-2017 Code for construction cost expert assessment (judicial appraisal) of construction projects, Section 5.9 (six situations for certified records and putting verbal instructions in writing); GB/T 50500-2024 China national pricing standard for BOQ, Clauses 7.5.4 and 7.5.6 (certified dayworks records) and Clause 8.11.3 (the 28-day twin deadlines for claims); T/SDJZXH 004.1-2022 Work standard for supervision of urban rail transit projects, Clauses 10.6.1 and 10.6.3 (scope and procedure for certified records); DBJ41/T 208-2018 Work standard for construction supervision, Clause 9.4.4 (cost claim handling procedure).