Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Contract price adjustment trigger events (eleven classes, GB/T 50500-2024 clause 8.1.1) and their linkage with certified site records and sign-off

GB/T 50500-2024 clause 8.1.1 lists eleven classes of contract price adjustment triggers: BOQ defects; provisional sums; provisional prices; main-contract services; dayworks; price changes; changes of laws, regulations and policies; works variations; additional works; claims; and other events agreed by the parties. Among them, for dayworks per clauses 7.5.4-7.5.6 certified dayworks records are submitted and, once jointly confirmed, serve as the pricing basis — the quantities so recorded exclude the contractor's own on-site management personnel and pre-existing site plant; variations, claims and additional works all require written instructions/signed documents — site actuals without confirmation cannot be directly measured or priced.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 第8.1.1条、第7.5.4~7.5.6条
  • DB37/T 5028-2022 建设工程监理工作规程 第6.3.2条
  • GB/T 51262-2017 建设工程造价鉴定规范 第5.9节

Topic Positioning

From the "contract price adjustment" perspective, this card answers which contractual events require site instructions and certified records: the eleven-class trigger list of GB/T 50500-2024 clause 8.1.1 and the certification calibers for dayworks etc., complementing the "six situations requiring site instructions and certified records" card.

Core Conclusions

GB/T 50500-2024 clause 8.1.1: upon the following events during performance, the parties may adjust the relevant contract price as provided — (1) BOQ defects; (2) provisional sums; (3) provisional prices; (4) main-contract services; (5) dayworks; (6) price changes; (7) changes of laws, regulations and policies; (8) works variations; (9) additional works; (10) claims; (11) other adjustment events agreed by the parties. On a trigger event, quantities are computed as required before adjusting the price. Dayworks (clauses 7.5.4-7.5.6): work not completed the same day requires a certified dayworks record (with daily-record summary) within the agreed time after completion; the jointly signed confirmation serves as the pricing basis; the recorded quantities count only the actually deployed construction personnel, materials and plant, excluding the contractor's own on-site management personnel and pre-existing site plant. Variations, claims and additional works likewise rely on written instructions/signed documents; unconfirmed site actuals cannot be directly measured or priced.

Applicable Boundaries

Applies to price adjustment and site instruction/certification management of employer-contractor works under the GB/T 50500-2024 BOQ pricing mode; special contractual agreements on procedures, submission deadlines and effectiveness requirements prevail. This card gives the "trigger list + confirmation linkage" only, not per-event computation details; the six "whether to sign" situations, the signable/prohibited negative list, the four validity elements of a certified site record and the dedicated dayworks calibers are on separate cards.

Further Reading

GB/T 50500-2024 "Standard for bill-of-quantities pricing of construction works" clause 8.1.1 (adjustment triggers), clauses 7.5.4-7.5.6 (certified dayworks records and confirmation); DB37/T 5028-2022 "Rules for supervision of construction works" clause 6.3.2 (scope of commercial (priced) variation records: temporary work outside the contract, on-site quantity changes caused by design variations, rework losses from design modification etc.); GB/T 51262-2017 section 5.9 (six situations requiring site instructions and certified records).

Keywords

Cited By