Bases the employer must provide for disallowance / downward adjustment on review of the settlement: the review-basis checklist, type-by-type reconciliation, and burden of proof

The employer's claimed disallowance / downward adjustment on review must be "evidence-based and itemized": the bases include contract documents, tender documents, construction/as-built drawings, changes/negotiations/site instructions and variation records/claims/minutes, employer's approval of material prices, site survey and re-verification records, and pricing bases; different types of disallowance / downward adjustment (quantities, unit prices, changes/site instructions, provisional sums for specified materials / nominated works, free-issue materials (by the employer), preliminaries, unexecuted items) require different evidence; disallowance / downward adjustment opinions should be written with "amount + reason + basis document", and review conclusions must be jointly certified and signed off by employer, contractor, and consultancy; in construction cost expert assessment (judicial appraisal) the employer bears the burden of proof for the disallowance / downward adjustment — failure of proof means rejection.

Applicable Codes

  • GB/T 51095-2015 建设工程造价咨询规范 8.2.4/8.3.4/8.3.8
  • GB/T 50500-2024 建设工程工程量清单计价标准 第10.3节
  • T/ZBD 100.5-2023 建设工程结算审核作业指引 2.1.1/2.2/3.1
  • T/ZBD 100.4-2023 建设工程造价鉴定作业指引 4.2.2
  • DB42/T 823-2021 建设工程造价咨询质量控制规范 8.3.4

Topic Positioning

This card answers "what bases must the employer provide for disallowance / downward adjustment on review of the settlement": disallowance / downward adjustment must be itemized, evidence-based, written, and traceable — the contractor may refuse certification and sign-off for a disallowance / downward adjustment without basis.

Core Conclusions

Employer disallowance / downward adjustment on review rests on the review-basis checklist (GB/T 51095-2015 8.3.4; DB42/T 823-2021 8.3.4; T/ZBD 100.5-2023 2.1.1): contract documents; tender documents; construction/as-built drawings; approved project execution plans (construction methodology and site organization); changes/negotiations/site instructions and variation records/claims/minutes; employer's approval of material prices; mutually confirmed additional or downward-adjusted amounts on review; survey and re-verification records; commencement/completion reports; pricing bases, laws, and regulations. Reconcile by type: disallowance / downward adjustment of quantities relies on settlement drawings + measurement rules + concealed-acceptance records; disallowance / downward adjustment of unit prices checks against the priced BOQ; disallowance / downward adjustment for changes/site instructions requires review of legality, timeliness, authenticity, and completion-confirmation documents; disallowance / downward adjustment relating to a provisional sum for specified materials / nominated works relies on employer's approval of material prices/winning prices; disallowance / downward adjustment for free-issue materials (by the employer) relies on draw/return slips and agreed wastage rates; disallowance / downward adjustment for preliminaries/taxes and duties (VAT under the current standard) relies on approved project execution plans (construction methodology and site organization) and policy documents; disallowance / downward adjustment for unexecuted items relies on drawing/scope/acceptance comparison. Procedure: a disallowance / downward adjustment opinion = amount + reason + basis document, submitted in writing; review conclusions are jointly certified and signed off by employer, contractor, and consultancy; in construction cost expert assessment (judicial appraisal) the employer bears the burden of proof for the disallowance / downward adjustment — failure of proof means rejection.

Applicable Boundaries

Applies to employer-contractor settlement checking, consultancy review, and construction cost expert assessment (judicial appraisal); the checklist is general and adjustable per project; where the contract provides otherwise, the contract prevails.

Further Reading

GB/T 51095-2015 8.2.4/8.3.4/8.3.8; GB/T 50500-2024, Section 10.3; T/ZBD 100.5-2023, Chapter 2, Section 3.1; T/ZBD 100.4-2023, 4.2.2.