The five-dimension method for systematically checking design changes at final account: four-way reconciliation across ledger, drawings, settlement, and site
Checking design changes at final account uses "ledger - drawings - settlement - site" four-way reconciliation, verified layer by layer across five dimensions: completeness -> truthfulness -> compliance -> accuracy -> correlation. Two-way reconciliation between the change ledger and the settlement prevents omissions and duplication (no pricing without supporting documents; no concealing of deductions); four-party certification and sign-off establishes authenticity; procedural compliance looks to designer issuance and the Engineer's release; pricing is verified on the same/similar/rate build-up ladder and the 15% boundary rule; as-built drawings, certifications, and claims are cross-proved.
Applicable Codes
- T/ZBD 100.5-2023 建设工程结算审核作业指引
- DB37/T 5130-2018 建设工程造价咨询服务规范
- GB/T 50500-2024 建设工程工程量清单计价标准
- DB11/T 1745-2020 建筑工程施工技术管理规程
Topic Positioning
The method for checking design changes at final account: "ledger - drawings - settlement - site" four-way reconciliation, verified across five dimensions — completeness -> truthfulness -> compliance -> accuracy -> correlation — preventing omission, duplication, fraud, and error.
Core Conclusions
(1) Completeness: two-way reconciliation between the change ledger and the settlement — every change must have a corresponding amount in the settlement (including reductions) and every cost a supporting document; check the continuous numbering of design change orders, preventing the same item from being charged twice as both a design change and a certification, and preventing reporting only increases while concealing reductions. (2) Truthfulness: four-party certification and sign-off (employer, designer, contractor, supervision) with complete seals — incomplete certification and sign-off bars use in the works; check the logic of the change, construction, sign-off, and completion dates against backdating; changes require completion confirmation, with site verification where necessary. (3) Compliance: design changes issued by the designer; major modifications reported to the original approving authority for approval; those touching structure, fire protection, civil air defence, energy saving, or environmental protection re-reviewed; no construction without the Engineer's (chief supervising engineer under China's supervision regime) release. (4) Accuracy: the rate build-up ladder — same items at contract prices, similar items converted, neither same nor similar priced at reasonable cost plus management and profit percentage rates; quantity deviations beyond 15% adjust unit prices; preliminaries adjusted per approved schemes, late submission deemed waiver. (5) Correlation: as-built drawings, certifications, and claims cross-proved; every amount traceable to the contract clause, BOQ item, drawing, and design change order.
Applicable Boundaries
For final account review and cost consultancy in building, municipal, and rail works; document intake inspection precedes checking — defects listed in writing for timed correction, no checking until the documents are complete; railways have separate change-classification procedures; pricing follows the contract agreement and local pricing bases.
Further Reading
T/ZBD 100.5-2023 Clauses 2.1.8, 2.2.3, 3.1.8; DB37/T 5130-2018 Clauses 8.3.3, 8.3.8; GB/T 50500-2024 Section 8.9; DB11/T 1745-2020 Clauses 5.2.1-5.2.4.