Linking the five document types — contract, drawings, BOQ, site instructions / variation records, settlement — and managing the settlement chain of evidence

Using unified codes as the bond, lineage relations attached via linking fields, on-the-spot linkage in the workflow, and a basis for settlement ledger as the master index, build contract, drawings, BOQ, site instructions / variation records, and settlement into a traceable chain of evidence: every settlement amount must be able to state which contract clause it relies on, which BOQ item it corresponds to, which drawing it comes from, and which site instruction / variation record triggered it; only when the four elements are complete and certification and sign-off are complete is it included in settlement.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • T/ZBD 100.5-2023 建设工程结算审核作业指引
  • GB/T 51095-2015 建设工程造价咨询规范
  • DB37/T 5164-2020 建筑施工现场管理标准
  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准
  • GB/T 50326-2017 建设工程项目管理规范

Topic Positioning

This card covers how to build contract, drawings, BOQ, site instructions / variation records, and settlement into a traceable chain of evidence: unified codes as the bond, lineage relations attached through linking fields, and a ledger as the master index, ensuring every settlement amount can answer "which contract clause it relies on, which BOQ item it corresponds to, which drawing it comes from, and which site instruction / variation record triggered it".

Core Conclusions

(1) Unified coding: each document gets one unique code (e.g., [project no.]-[type code]-[discipline/position]-[sequence no.]-[version], with HT/TZ/QD/QZ/JS standing for contract/drawings/BOQ/site instruction/variation record/settlement); BOQ items directly use the national BOQ codes; version changes produce a new number — overwriting is strictly forbidden. (2) Four lineage relations: contract clause <-> BOQ-based pricing rules (price adjustment (for fluctuation) and risk provisions attached to the corresponding BOQ items); each BOQ item carries "basis drawing no. + position", answering where the quantity comes from; each site instruction / variation record states the triggering contract clause, affected BOQ items, and basis drawing version, answering where the price comes from; every settlement amount is back-linked to the contract clause + BOQ item + drawing + site instruction / variation record number. (3) Link on the spot in the workflow, not patched up at settlement: when a change or site instruction / variation record occurs, register the links immediately and obtain written certification and sign-off; the confirmed adjusted price is paid together with progress payments or payments for stage settlement during construction. (4) At settlement, use the "basis for settlement ledger" as the master index to check line by line; only items complete with all four elements — contract, BOQ, drawings, site instruction / variation record — and complete certification and sign-off are included; missing links are flagged "incomplete basis" and listed separately, never mixed into the normal settlement amount.

Applicable Boundaries

Applies to settlement management and document archiving of construction contracting; the coding rules are a methodological example — projects may customize them but must ensure uniqueness and no version overwriting; this card does not expand on appraisal rules for changes without site instructions / variation records or settlement price-basis priority (see the cited cards); the specific content of the basis of preparation for settlement follows the ten-item list of GB/T 51095-2015, Clause 8.2.4.

Further Reading

Measurement of variations per the contract-agreed method of measurement and applicable national/industry measurement standards (GB/T 50500-2024, Clause 7.4.1); valuation of variations follows the sequence "identical contract items -> analogous items -> reasonable cost + agreed percentage rate for derivation of new (built-up) rates" (T/ZBD 100.5-2023, Clause 3.1.8); price-adjustment results signed by both parties are paid together with progress payments or payments for stage settlement during construction (GB/T 50500-2024, Clause 8.1.6); basis of preparation for the final account (GB/T 51095-2015, Clause 8.2.4; GB/T 50326-2017, Clause 18.3.3); BOQ item description (work item specification) requirements (GB/T 50854-2024, Clause 4.1.2).