Final account deliverables composition, archiving scope, dual-track electronic file requirements, and cost consultants' quality liability (GB/T 50500-2024 Chapter 12 + GB/T 51095-2015 Chapter 8)
Final account deliverables composition per GB/T 51095-2015 8.2.2 (cover, signature page, contents, explanatory notes of the estimate, final account summary table, single-project/unit-work final account summary tables); review deliverables per 8.3.1 (final account review cover, signature page, final account review report, final account approval certification and sign-off form, summary comparison tables). Archiving per GB/T 50500-2024 Section 12.3: deliverables must be archived dual-track as paper originals + electronic files, with electronic files meeting standard data-interface requirements; archiving may be phased or after the final account is completed; handover requires a transfer list signed and sealed by both parties. Consultant quality liability per 1.0.5's three-tier system: the consultant is responsible to the client, and after client confirmation the deliverable counts as the client's toward the other party; deliverables must be prepared by cost professionals and reviewed/signed with the practice seal by Grade-1 registered cost engineers (1.0.4); final account review conclusions are jointly certified and signed off by the employer, contractor, and consultant (GB/T 51095-2015 8.3.8).
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准(第1.0.4、1.0.5、10.3.4、12.3节)
- GB/T 51095-2015 建设工程造价咨询规范(第3.3.6、8.2.2、8.3.1、8.3.8条)
Topic Positioning
This card compiles the key provisions of GB/T 50500-2024 China national pricing standard for BOQ, Chapter 12 'Pricing deliverables and archive management' (with 1.0.4, 1.0.5, 10.3.4) and GB/T 51095-2015 'Code for construction cost consultancy' Chapter 8 'Completion stage' on the composition of final account deliverables, archiving scope and electronic file requirements, and cost consultants' quality liability — for cross-checking when preparing, reviewing, and archiving final account documents.
Core Conclusions
1. Final account deliverables composition
- Final account documents (GB/T 51095-2015 8.2.2) shall include: cover, signature page, contents, explanatory notes of the estimate, final account summary table, single-project final account summary, unit-work final account summary, etc.; final account deliverables priced on a bill of quantities basis may follow that code's Appendix F.
- Final account review deliverables (8.3.1) shall include: final account review cover, signature page, final account review report, final account approval certification and sign-off form, final account review summary comparison tables (overall/single-project/unit-work), etc.; those priced on a bill of quantities basis may follow Appendix G.
- Basis of preparation (GB/T 50500-2024 10.3.4): after completion, the contractor shall, on the basis of the interim settlement by construction stage confirmed by both parties, supplement quality acceptance certificates and other materials, and compile and submit complete final account documents in accordance with the contract and relevant provisions.
2. Archiving scope and electronic file requirements (GB/T 50500-2024 Section 12.3)
- 12.3.1: the employer, the contractor, and cost consultants shall collect all pricing documents of archival value in any medium, organize them into volumes, and archive them.
- 12.3.2: establish sound construction pricing archive management systems meeting state and departmental archive requirements.
- 12.3.4: archived construction pricing deliverables shall include paper originals AND electronic files; other archived documents and bases may be paper originals, photocopies, or electronic files; archived electronic deliverables shall meet the standard data-interface requirements — i.e., deliverables are archived dual-track (paper original + electronic), bases may relax to photocopies, and electronic files carry data-interface compliance requirements.
- 12.3.5: archived files shall be sorted per requirements into compliant archive volumes.
- 12.3.6: archiving may proceed in phases during implementation or after the final account is completed.
- 12.3.7: when transferring archives to the receiving unit, prepare a transfer list; both parties shall sign and seal before handover.
3. Cost consultants' quality liability for deliverables
- Three-tier liability (GB/T 50500-2024 1.0.5): (1) either the employer or the contractor is responsible to the other for the quality of the construction cost deliverables it issues; (2) the commissioned cost consultant and its practitioners are responsible to the client for their deliverables' quality; (3) either the employer or the contractor is responsible to the other for the quality of deliverables prepared and verified by its commissioned and confirmed cost consultant. I.e., consultant deliverables confirmed by the client count as the client's toward the other party (10.3.4 commentary same position).
- Preparation and signature requirements (1.0.4): bills of quantities, tender price ceilings, tenders (priced offers), measurement of the works, adjustment of the contract price and interim payments, construction payment settlement and payment, and other construction cost deliverables issued by consultants shall be prepared by cost professionals and reviewed and signed by Grade-1 registered cost engineers with their practice seal affixed.
- Certification and sign-off of review conclusions (GB/T 51095-2015 8.3.8): when a cost consultancy enterprise completes a final account review, the conclusion shall be jointly certified and signed off by the employer, the contractor, and the cost consultancy enterprise (signing the 'final account approval certification and sign-off form'); absent substantive grounds, if the three cannot jointly certify and sign off due to disagreement, the cost consultancy enterprise may, after failed coordination, submit the final account review report separately and bear the corresponding responsibility.
Applicable Boundaries
- Applies to employer-contractor pricing activities carried out on a bill of quantities basis; GB/T 50500-2024 is a recommended national standard whose provisions become contractual obligations upon contract citation.
- The deliverables composition and review certification and sign-off provisions come from GB/T 51095-2015 'Code for construction cost consultancy', mainly binding cost consultancy enterprises' practice.
- Dual-track 'paper original + electronic file' archiving applies only to the construction pricing deliverables themselves; other archived documents and bases may relax to paper originals, photocopies, or electronic files.
- This card does not cover retention periods (per state archive regulations) or the specific receiving unit of transfers (per contract).
Further Reading
- GB/T 50500-2024 China national pricing standard for BOQ, Chapter 12, 12.3.1-12.3.7 (construction pricing deliverables and archive management), 1.0.4/1.0.5 (preparation signature and quality liability), 10.3.4 (final account compilation); title-page signature chain in 12.1.3.
- GB/T 51095-2015: 8.2.2 (final account documents composition, Appendix F), 8.3.1 (final account review deliverables, Appendix G), 8.3.8 (joint certification and sign-off of the final account approval certification and sign-off form), 3.3.6 (enterprise and preparer/reviewer/approver seal requirements).