Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Bases for determining final account quantities: completed qualifying quantities + measurement certification and sign-off lock-in + measurement method by contract type

The final account quantity (in FIDIC contexts, the Final Statement plus discharge) = the qualifying quantities actually completed by the contractor in accordance with the contract and to be measured, calculated under the contract-agreed national and industry quantity take-off (measurement) standards and supplementary calculation rules; the measurement results certified and signed off by both parties (including documents for interim settlement by construction stage (China's 2020 node-based interim settlement system; no exact international equivalent)) serve as the basis for settlement (GB/T 50500-2024 Clauses 7.1.1, 7.1.8, 10.3.1). Lump-sum contracts adjust only the agreed adjustable contents; re-measurable (unit-rate) contracts measure actual completed quantities; cost-plus contracts calculate cost, fee, and taxes per the agreed method; as-built drawings, changes, site instructions/variation records, and concealed-acceptance records form the chain of evidence for 'actual completion'.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 51095-2015 建设工程造价咨询规范
  • GB/T 50326-2017 建设工程项目管理规范
  • DB42/T 823—2021 建设工程造价咨询质量控制规范
  • DB37/T 5130—2018 建设工程造价咨询服务规范
  • 建设部令第107号 建筑工程施工发包与承包计价管理办法

Topic Positioning

On what basis final account quantities are determined: the object of the quantities, the calculation rules, the lock-in effect of measurement, and the chain of evidence.

Core Conclusions

  1. Object: the qualifying works completed by the contractor and to be measured per the contract; measurement of changes is based on the qualifying works and the employer's construction drawings and change instructions (GB/T 50500-2024 Clause 7.1.1).
  2. Rules and effect: quantities are calculated per the mutually agreed national and industry quantity take-off (measurement) standards and supplementary rules; certified and signed-off measurement results serve as the basis for settlement; interim settlement by construction stage is incorporated into the final account (Clauses 7.1.8, 10.3.1).
  3. Contract types: lump-sum contracts adjust only the agreed adjustable contents; re-measurable (unit-rate) contracts measure actual completed quantities; cost-plus contracts calculate cost, fee, and taxes per the agreed method (DB42/T 823—2021 Clause 8.2.4).
  4. Chain of evidence: as-built drawings and change documents are core, supported by site instructions/variation records, consultation records, claims, concealed-acceptance records, and employer's material price approval sheets (GB/T 51095-2015 Clause 8.2.4).
  5. Audit: check consistency between the settlement and as-built drawings and site instructions/variation records, quantity accuracy, and rule-compliant calculation (DB37/T 5130—2018 Clause 8.3.8).

Applicable Boundaries

Applies to determining 'quantities' in the final account; 'prices' are covered by the price-basis priority card; discrepancies between drawings and actual works and changes without site instructions/variation records are governed by separate rules.

Further Reading

GB/T 50500-2024 Clauses 7.1.1, 7.1.8, 10.3.1, 10.3.4; GB/T 51095-2015 Clause 8.2.4; GB/T 50326-2017 Clause 18.3.3; DB42/T 823—2021 Clause 8.2.4; DB37/T 5130—2018 Clause 8.3.8; Ministry of Construction Order No. 107 Article 16.