Bases for determining final account quantities: completed qualifying quantities + measurement certification and sign-off lock-in + measurement method by contract type
The final account quantity (in FIDIC contexts, the Final Statement plus discharge) = the qualifying quantities actually completed by the contractor in accordance with the contract and to be measured, calculated under the contract-agreed national and industry quantity take-off (measurement) standards and supplementary calculation rules; the measurement results certified and signed off by both parties (including documents for interim settlement by construction stage (China's 2020 node-based interim settlement system; no exact international equivalent)) serve as the basis for settlement (GB/T 50500-2024 Clauses 7.1.1, 7.1.8, 10.3.1). Lump-sum contracts adjust only the agreed adjustable contents; re-measurable (unit-rate) contracts measure actual completed quantities; cost-plus contracts calculate cost, fee, and taxes per the agreed method; as-built drawings, changes, site instructions/variation records, and concealed-acceptance records form the chain of evidence for 'actual completion'.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB/T 51095-2015 建设工程造价咨询规范
- GB/T 50326-2017 建设工程项目管理规范
- DB42/T 823—2021 建设工程造价咨询质量控制规范
- DB37/T 5130—2018 建设工程造价咨询服务规范
- 建设部令第107号 建筑工程施工发包与承包计价管理办法
Topic Positioning
On what basis final account quantities are determined: the object of the quantities, the calculation rules, the lock-in effect of measurement, and the chain of evidence.
Core Conclusions
- Object: the qualifying works completed by the contractor and to be measured per the contract; measurement of changes is based on the qualifying works and the employer's construction drawings and change instructions (GB/T 50500-2024 Clause 7.1.1).
- Rules and effect: quantities are calculated per the mutually agreed national and industry quantity take-off (measurement) standards and supplementary rules; certified and signed-off measurement results serve as the basis for settlement; interim settlement by construction stage is incorporated into the final account (Clauses 7.1.8, 10.3.1).
- Contract types: lump-sum contracts adjust only the agreed adjustable contents; re-measurable (unit-rate) contracts measure actual completed quantities; cost-plus contracts calculate cost, fee, and taxes per the agreed method (DB42/T 823—2021 Clause 8.2.4).
- Chain of evidence: as-built drawings and change documents are core, supported by site instructions/variation records, consultation records, claims, concealed-acceptance records, and employer's material price approval sheets (GB/T 51095-2015 Clause 8.2.4).
- Audit: check consistency between the settlement and as-built drawings and site instructions/variation records, quantity accuracy, and rule-compliant calculation (DB37/T 5130—2018 Clause 8.3.8).
Applicable Boundaries
Applies to determining 'quantities' in the final account; 'prices' are covered by the price-basis priority card; discrepancies between drawings and actual works and changes without site instructions/variation records are governed by separate rules.
Further Reading
GB/T 50500-2024 Clauses 7.1.1, 7.1.8, 10.3.1, 10.3.4; GB/T 51095-2015 Clause 8.2.4; GB/T 50326-2017 Clause 18.3.3; DB42/T 823—2021 Clause 8.2.4; DB37/T 5130—2018 Clause 8.3.8; Ministry of Construction Order No. 107 Article 16.
Keywords
- final account
- 工程量依据
- 合格工程量
- 合同工程计量
- 计量成果
- as-built drawings
- variation instruction and certified record
- 结算编制依据
- final account review
Related Cards
- →
Determining settlement quantities when drawings disagree with actual site dimensions: characterize first (variation / unauthorized work / measure-as-executed), then quantify
Where drawings and site dimensions disagree, one must not uniformly settle "per drawings" or "per actuals" — characterize first: employer changes baselines/levels/positions/dimensions -> variation, measured per the revised drawings (lump-sum contracts measure only the confirmed variation portion; unit-rate contracts re-measure per the final construction drawings); contractor builds not per drawings without authorization -> quantities beyond the drawings are not measured and no site instruction or variation record may be issued for them; design explicitly requires site verification -> a site instruction / variation record confirms per actuals. In disputes referred for construction cost expert assessment, determination follows the five-tier progression: valid confirmation signed by both parties -> one-party confirmation (no rebuttal) -> re-check or site inspection -> inspection measurement -> if still undeterminable, no measurement with explanation.
- →
Linking the five document types — contract, drawings, BOQ, site instructions / variation records, settlement — and managing the settlement chain of evidence
Using unified codes as the bond, lineage relations attached via linking fields, on-the-spot linkage in the workflow, and a basis for settlement ledger as the master index, build contract, drawings, BOQ, site instructions / variation records, and settlement into a traceable chain of evidence: every settlement amount must be able to state which contract clause it relies on, which BOQ item it corresponds to, which drawing it comes from, and which site instruction / variation record triggered it; only when the four elements are complete and certification and sign-off are complete is it included in settlement.
- →
Whether the employer's overdue non-reply to the final account documents is deemed acceptance of the submitted amount - the three-requirement test of Fa Shi [2020] No. 25, Article 21, and interface with GB/T 50500-2024
Where the contract stipulates 'overdue non-reply is deemed acceptance', under Fa Shi [2020] No. 25, Article 21, the people's court shall support the contractor's claim for settlement per the final account documents (submitted price); three requirements must be met simultaneously: an express contractual stipulation, delivery of complete settlement documents, and no reply within the agreed period. Absent such stipulation, claims based only on ministerial rules or model contract texts containing 'deemed acceptance' wording are not supported by the SPC and the overwhelming majority of courts. GB/T 50500-2024, Clause 10.3.8, points the same way but is a recommendatory national standard that becomes a contractual obligation only when incorporated by the contract; at the rule level, Article 16 of the former MOC Decree No. 107 has been carried over by Article 18 of MOHURD Decree No. 16, with 28 days as the default period absent agreement.
- →
Priority of price bases for construction payment settlement: contract agreement > price confirmed by both parties > published price information > market price enquiry (purchase contract / invoice prices require the employer's approval of material prices)
Bases for settlement by priority: ① contract-agreed price (fundamental basis); ② price confirmed by the employer and contractor (certified record of agreed material prices — report quantity and unit price to the employer for verification before purchase; deemed approval upon lapse of the response period); ③ published price information (base price for adjustment / dispute fallback); ④ market price enquiry (for provisional sums and materials without published prices). Purchase contract prices and invoice prices only prove actual cost and become a basis for settlement only after the employer's approval of material prices.
- →
Settlement of works variations without signed instructions (qianzheng): five-tier determination rules, substitute evidence chains, and variation pricing principles
Signed instructions are not the only settlement basis. Whether an un-instructed variation can be settled depends on "who proposed the variation and whether traces of employer/supervisor approval exist": if not proposed by the contractor and instructions/drawings exist, or proposed by the contractor with either the employer's or the supervisor's consent → a determinate opinion can be issued and the amount settled; proposed by the contractor with drawings only and no confirmation → only an elective opinion, with risk; no confirmation and no drawings → costs should not be adjusted. Substitute evidence — design variation sheets, meeting minutes, supervisor records, photos/videos, etc. — can be collected; the deemed-acceptance rule for late verification and variation pricing principles can also be invoked.
- →
Document verification in subcontract final account disputes: a five-tier order of evidentiary weight (contract sets the tone → certification and sign-off lock quantities → drawings verify quantities → price evidence verifies prices → supporting evidence validates)
Documents in subcontract final account disputes are checked in tiers of evidentiary weight: (1) contract-type documents set the tone (subcontract and supplementary agreements, tender documents, pricing bases — establish the pricing benchmark first); (2) mutually certified and signed documents lock quantities (certified measurement of the works results, interim settlement by construction stage documents, interim payment certificates, site instructions / variation records, dayworks confirmations, free-issue materials requisition/return records — certification and sign-off locks); (3) drawing/technical documents verify quantities (construction drawings, approved variation drawings — works beyond them are not measured); (4) price evidence verifies prices (material price approval records, purchase contracts and invoices, published price information (government guidance prices)); (5) supporting/procedural evidence validates (meeting minutes, photographs, acceptance records, supervisor logs). Order of weight: contract agreement > mutual certification and sign-off > unilateral declaration.
- →
The five-dimension method for systematically checking design changes at final account: four-way reconciliation across ledger, drawings, settlement, and site
Checking design changes at final account uses "ledger - drawings - settlement - site" four-way reconciliation, verified layer by layer across five dimensions: completeness -> truthfulness -> compliance -> accuracy -> correlation. Two-way reconciliation between the change ledger and the settlement prevents omissions and duplication (no pricing without supporting documents; no concealing of deductions); four-party certification and sign-off establishes authenticity; procedural compliance looks to designer issuance and the Engineer's release; pricing is verified on the same/similar/rate build-up ladder and the 15% boundary rule; as-built drawings, certifications, and claims are cross-proved.
- →
Overview of quantity take-off for construction works: basis, general rules and per-trade calculation methods
Quantity take-off rests on the four-tier basis "contract agreement -> design drawings -> approved project execution plan (construction methodology and site organization) -> appendix rules of the quota norms/measurement standards"; except where rules provide otherwise, all quantities are computed from the dimensions shown on the design drawings. General rules include: calculation per appendix rules (mandatory provisions of codes); the no-deduction threshold of single holes <=0.3 m2; significant figures of units of measurement (t/km three decimals; m/m2/m3/kg two; counts integer); and dual-track BOQ vs quota-norm quantities. Earthwork, concrete, reinforcement, formwork, masonry, waterproofing, finishes etc. each have standard algorithms.
- →
Preventing over-settlement and duplicate settlement of subcontracted quantities: dual-signature locking of measurement + interim settlement by construction stage merged into the final account + the list of items not measured
Preventing over-settlement/duplicate settlement relies on procedural control rather than account-checking error correction: measurement results, once signed and confirmed by both parties, are locked as the basis for settlement (GB/T 50500-2024 Clauses 7.1.7/7.1.8); signed interim settlement by construction stage documents are merged into the final account and are not re-measured or re-priced (Clause 10.2.3); after dual signing of the final account no repeated checking is allowed (Clause 10.3.12); quantities with unapproved commencement reports, failed acceptance, beyond the construction drawings, unlawful subcontracting or contract transfer (re-letting of the whole works), rework, etc. are not measured at all (TB 10402-2019 Clause 6.0.6 and others).
- →
Quantity take-off (measurement) follows design-drawn dimensions (measurement per drawings): general principle, rule exceptions, and final account linkage
Quantities are in principle calculated from design-drawn dimensions (measurement per drawings), not from actual site dimensions; only items where the method of measurement "provides otherwise" (e.g. earthwork by natural in-situ (undisturbed) volume, depth taken from surveyed elevation) and site instruction / variation record items not specified in the design (flowing sand and silt provisionally estimated, concealed works) are measured per actual conditions / site instruction / variation record. Parts constructed beyond design dimensions without variation or site instruction / variation record support are generally not measured in the final account.
Cited By
- ←
Judging the code non-compliance of 'cut only, never add' in final account review, the clause basis for the contractor's claim to symmetric upward review (the full-review method, objective and fair deliverables, two-way quantity-difference pricing, BOQ errors on the employer), and the entrances for upward adjustment and the written-objection remedy
'Cut only, never add' has no code basis: GB/T 51095-2015 clause 8.3.5 requires the full-review method for final account review, barring key, sampling or analogy methods, and clause 1.0.3 requires fair stand, conduct, procedure, method and deliverables; T/ZBD 100.5-2023 clause 4.2.3 requires the review report to state the disallowed and the added prices and rates with item-by-item reasons. The quantity-difference rules are themselves two-way: GB 50500-2013 clause 9.6.2 lowers the all-in rate on the added part beyond +15% and raises it on the remaining part beyond -15%; GB/T 50500-2024 clause 8.2.1 splits at 15% (inclusive / exclusive) with the mirrored pricing of clauses 8.9.1 and 8.9.2. The accuracy and completeness of unit-rate work-item lists rest on the employer (clause 3.1.8) - the normative entrance for upward review - but the contractor must file itemised written objections within the agreed time, silence being deemed acceptance (clauses 10.3.8, 10.3.10).
- ←
Differences in final account adjustment between lump-sum contracts (fixed total price) and unit-rate contracts (fixed unit rates): treatment rules for quantity changes, BOQ errors, design changes and cost fluctuation, mapped to GB/T 50500-2024 clause numbers
GB/T 50500-2024 uses 'lump-sum contract / unit-rate contract' rather than 'fixed total price / fixed unit rate'; the substantive difference lies in the allocation of quantity and price risk. A lump-sum contract wraps up both quantities and prices - the measured-works BOQ items need not be re-measured, and price changes arising from BOQ errors are deemed included in the contract total and are not adjusted during performance (clauses 4.1.6, 7.2.2, 8.2.3); only 'provisional quantity' unit-rate-priced items and variations may be adjusted. A unit-rate contract fixes the rates and re-measures the quantities - all BOQ items and quantities of the measured works must be re-measured, BOQ errors fall on the employer, and quantity changes are priced under clause 8.9.1 or clause 8.9.2 depending on the 15% (inclusive / exclusive) boundary (clauses 2.0.6, 4.1.4, 8.2.1). The adjustment rules for cost fluctuation (where no band is agreed, adjustment under Annex A is allowed once the movement exceeds 5%, the differential bearing VAT only, with no overheads or profit) and for changes in laws and regulations and policy are identical for both contract types.
- ←
Preserving evidence of completed quantities when the construction contract is terminated or the contractor is forcibly evicted: the window, the procedure, and the quantity-price determination routes (Fa Shi [2026] No. 12 Article 15, Civil Procedure Law Article 84, Interpretation on the Civil Procedure Law Article 98, Construction Interpretation (I) Article 20, GB/T 51262-2017 Article 5.10.1)
Preservation is possible, but the full window exists only before the contractor leaves the site: Fa Shi [2026] No. 12 Article 15(1) provides that after termination of the contract the employer's request for handover of the site and the construction documents is supported by the court (handover is not conditioned on settlement of payment, and withholding handover cannot be used to pressure settlement), and Article 15(2) states 'before the contractor leaves the site, where a party applies for preservation of evidence, the people's court shall handle it under Article 84 of the Civil Procedure Law'. The core of preservation is not site photos but a quantity evidence chain of 'location + dimensions + calculation sheets': measurement results signed and confirmed by both parties serve directly as the basis for settlement (GB/T 50500-2024 Article 7.1.8); disputed quantities are confirmed by written documents such as site instruction records formed during construction, and absent such records other evidence may confirm the quantities actually performed (Fa Shi [2020] No. 25 Article 20); after site exit only the expert-assessment fallback of GB/T 51262-2017 Article 5.10.1 remains - counting completed locations, measuring quantities, counting site labour, materials and plant, compiling registers with sign-off and pricing separately - with probative force falling off a cliff.
- ←
Determining the settlement quantity where the quantity in a materials procurement contract differs from the delivery note: contractual measurement terms prevail; signing raises only a presumption of quantity and apparent conformity (rebuttable); written quantity objection within the inspection period and the chain of proof
Neither the 'contract quantity' nor the 'delivery-note quantity' can be used directly as the settlement basis; the settlement quantity is the quantity actually delivered and confirmed by the buyer's inspection (acceptance / re-weighing) under the measurement and settlement standards agreed in the contract. The contract fixes only the 'due quantity' and the pricing basis; the quantity actually performed is fixed at the delivery and inspection stage. Where no inspection period is agreed, a signed delivery note merely 'presumes' under Article 623 of the Civil Code that the buyer has inspected the quantity and apparent defects, unless contrary evidence suffices to rebut it. The buyer must object to the quantity in writing within the agreed inspection period (or, absent agreement, within a reasonable period from discovery or when it should have discovered, at most two years from receipt); failure to notify deems the quantity conforming (Article 621).
- ←
The hierarchy of documentary force of monthly quantity reports and measurement results certified by the supervising engineer: when they may serve as a basis for the final account and when only as a basis for progress payment (GB/T 50500-2024 cl. 7.1.7, 7.1.8 and 9.4.14 plus the measurement procedure of GF-2017-0201)
Not directly equivalent. GB/T 50500-2024 cl. 7.1.8 makes only 'measurement results of the works signed and confirmed by both the employer and the contractor' a basis for adjustment of the contract price and for settlement of the works, and expressly excludes three cases: a different contractual agreement, an express stipulation of both parties that they serve only as the basis for progress payment, and measurement results that are rough estimates (cl. 9.4.14 correspondingly provides that roughly measured results are for progress payment only and are not a basis for settlement of the works). A monthly report certified by the supervising engineer alone is usually neither 'signed and confirmed by both parties' (cl. 7.1.7), nor more than that: its function is locked to progress payment and quantity evidence (Article 20 of Fa Shi [2020] No. 25), so it proves quantity but not price; under GF-2017-0201 cl. 12.3.3/12.3.4, quantities 'deemed actually completed' where the supervising engineer fails to review within 7 days likewise resolve only measurement and progress payment and are not automatically the final settlement price.
- ←
Handling inconsistencies between the content of site instructions and certified records and as-built drawings: written clarification -> adjustment to facts -> report record -> construction cost expert assessment (judicial appraisal) per facts / site survey
An inconsistency between a site instruction / variation record and the as-built drawing cannot be settled by a blanket 'drawing prevails' or 'site instruction / variation record prevails': at final account review the employer and contractor clarify the facts in writing and adjust accordingly (GB/T 51095-2015 8.3.6); if written clarification fails, the construction cost consultancy judges and records the issues in the final account review report; once in construction cost expert assessment (judicial appraisal), quantities are calculated on the basis of actually completed amounts (GB/T 51262-2017 5.9.1); where quantities cannot be confirmed, the expert assessor asks the client to organize a site survey and assesses per the survey results (5.10.2, 4.6). Validity is judged by evidence strength: a site instruction / variation record fully certified and signed off by both parties and the supervisor, with the drawing merely omitting the work — the site instruction / variation record prevails and the as-built drawing should be corrected; a drawing jointly confirmed with a site instruction / variation record suspected of inflated quantities — reduce per actual quantities; documents reflecting different points in time — the final actual state prevails.
- ←
Concealed works covered without acceptance: rules for determining quality, quantity and liability
Before concealment the contractor must give notice for acceptance, and the works may not be covered without acceptance (Regulations on Quality Management of Construction Works, Article 30; GB/T 50252-2018, Clause 3.0.9); where covered without authorization, the re-inspection and all adverse consequences rest with the contractor; where notice was given but the supervisor/employer failed to inspect in time, the cost and delay of a passing re-inspection are borne by the employer, which must also pay reasonable profit. Quantity determination follows the ladder 'valid joint sign-off - one-party sign-off - review and site survey - non-measurement' (T/ZBD 100.4-2023, Clause 4.3.6).
- ←
Whether quantities confirmed at the progress-payment stage can be re-measured and reduced at the final account: the line between provisional payment and lock-in (lock-in by signed measurement results, stage settlements absorbed into the final account, rough measurement as no basis for settlement)
No single answer; the determinant is the nature and level of the confirming document, not whether payment has been made: the three confirmations that are provisional in nature - issue of an interim payment certificate, provisional payment, and rough measurement (by physical progress or proportion) - may be re-measured and reduced at the final account (GB/T 50500-2024 Articles 9.1.14 and 9.4.14); once both parties sign the measurement results without limiting them 'for progress payment use only' (Article 7.1.8), or the interim settlement by construction stage documents have been signed (Article 10.2.3, 'the final account must not re-measure or re-price them'), the quantities are locked and may not be reduced, the sole exception being preliminaries and main contractor's attendance and coordination provisions, which must be recalculated under Articles 10.2.7 and 10.3.3; once the final account documents are signed and sealed by both parties, no repeated checking is allowed in any case (Article 10.3.12; Article 19 of MOHURD Decree No. 16).
- ←
Panorama of final account rules: starting point, basis of preparation, the 13 price components, review and confirmation, and finality (GB/T 50500-2024)
The final account is the activity of computing, adjusting, confirming, and paying the contract price after taking-over (completion acceptance) — the summary of interim settlements by construction stage (GB/T 50500-2024, Clause 2.0.35); it starts after the whole project passes taking-over (Clause 10.1.4), with 28 days as the period absent contractual agreement (Ministry of Construction Order No. 107, Article 16). The settlement price is itemized in 13 items in order (Clause 10.3.2), with preliminaries and the main contractor's attendance and coordination provisions recomputed (Clause 10.3.3); the employer's overdue non-checking is deemed acceptance (Clause 10.3.8), and after both parties sign and seal, no re-checking and no claims over pre-settlement events (Clauses 10.3.12, 8.11.22).
- ←
Effect of signed-off interim settlements by construction stage on the final account: the no-re-measurement and no-re-pricing principle, statutory exceptions that can overturn it, submission and deemed-approval rules for late response, and a clause comparison linking the two settlements (GB/T 50500-2024 + Cai Jian [2022] No. 183)
Except that preliminaries and main contractor's attendance and coordination provisions shall be recalculated under Clauses 10.2.7 and 10.3.3, interim settlement documents by construction stage signed and confirmed by both employer and contractor form part of the final account documents, and the final account shall not re-measure or re-price them. Where the contract provides that interim stage settlement amounts serve as the basis for the final account, after dual sign-off the employer may no longer engage another cost consultant to repeat the check. The only openings to break the lock-in are: fraud, gross mistake, obvious unfairness, duress (Civil Code Articles 147/148/150/151; preclusive periods of 1 year or 90 days, 5 years at most), lack of authority of the confirming party, invalidity of the basis of confirmation, contractual exclusion of the lock-in, statutory recomputation items (preliminaries and main contractor's attendance and coordination provisions), and other provisions of laws and regulations (government fiscal review or audit alone is not a ground for overturning).
- ←
Whether completed but unaccepted sub-divisional work items can be measured and claimed for progress payment: the quality-pass threshold to measurement and the negative rules barring valuation, exceptions for causes not attributable to the contractor and the measurement of rework quantities, the timing distinction between pre-concealment measurement and the final account, and the deduction rules when quality failures are found after measurement
Passing quality acceptance is a substantive threshold to measurement, not a formality: the object of measurement must be 'qualifying work the contractor has completed per the contract requirements and that is to be measured' (GB/T 50500-2024 cl. 7.1.1), and work not accepted under the quality acceptance standards, or failing acceptance, is withheld from measurement and valuation for payment by the project supervision office (TB 10402-2019 cl. 6.0.6 item 2) -- so it can be neither claimed for measurement nor enter progress payment; after rectification, rework and a passed re-inspection, measurement resumes for the same location. The only exception sits on the responsibility side: rework caused by a variation or by employer responsibility is measured per the rework items and quantities fixed in the rework confirmation sheet and the costs are compensated (cl. 7.6.1, 7.6.4); rework quantities caused by the contractor are not measured and the costs are borne by the contractor. Measurement results not checked in time may be deemed approved, but must not serve as evidence that the works have been delivered as accepted (cl. 7.1.5); where a quality failure is found after measurement, the employer may deduct repair and rework costs in the final account (cl. 10.3.13) and, within the defects liability period, deduct repair costs from the retention money (cl. 10.5.3).
- ←
What the four construction documents prove, who issues them and at which procedural stage - a comparison of the measurement sheet, the site instruction record, the variation order (variation instruction) and the progress payment certificate, with their documentary dependency chain and the time-limit requirements for certification
The four documents occupy four non-overlapping evidentiary layers. The variation order proves whether to vary and what to vary (the instruction fact; GF-2017-0201 Clauses 10.2 and 10.3). The site instruction record proves events outside the contract and the resulting cost facts (GB 50500-2013 Clauses 9.14.2 and 9.14.5; T/CAEC 006-2024 Clause 7.2.9). The measurement sheet proves the quantities of work actually completed (GF-2017-0201 Clause 12.3; GB/T 50500-2024 Clauses 7.1.5, 7.1.7 and 7.1.8) and states expressly that it 'shall not serve as the basis for the relevant works having been delivered as conforming'. The payment certificate proves the amount payable for the current period (GF-2017-0201 Clause 12.4.4; GB/T 50500-2024 Clause 9.1.11) and states that it 'does not indicate that the employer has agreed to, approved or accepted the part of the work completed by the contractor'. Issuing chain: the supervising engineer issues the variation instruction (which must be signed by the employer) -> the contractor submits the variation valuation application within 14 days -> monthly quantity reports are submitted (on the 25th of each month, with 7 days for supervisory review) -> the progress payment application (7 days of review by the supervising engineer, 7 days for the employer to approve and issue) -> payment within 14 days after issue.
- ←
Routes for claiming final account quantities of concealed works where no measurement records exist: the pre-concealment measurement confirmation procedure, who bears the exposure costs after covering without notice, the ranking of supplementary evidence, the requirements for retrospectively certified quantity sheets, and the interface with measurement from drawings
The absence of measurement records does not mean quantities cannot be claimed, but the claim route shifts from 'measurement certified on as-built facts at the time' to 'measurement re-proven from facts of completion plus a chain of evidence', with two adverse consequences: (1) where the works were covered without notice, the costs of drilling probes or uncovering for inspection and of reinstatement are always borne by the contractor and are not shifted by conforming quality (GF-2017-0201 clause 5.3.4); (2) the burden of proof is heavier - where there is no signed certification, the drawings cannot reflect the work and no site inspection is possible, the expert assessment refuses measurement as an 'item not susceptible to assessment' (T/ZBD 100.4-2023 clause 4.3.6 item 5). On the measurement confirmation procedure, failure to check within the time limit triggers deemed approval (GB/T 50500-2024 clauses 7.1.5 and 7.1.6), and measurement results signed and confirmed by both parties become the basis for the final account (clause 7.1.8), but such approval 'shall not serve as the basis for deeming the relevant works handed over as conforming'; quantities ultimately return to reconstruction from design-drawing dimensions plus variation instructions plus certified site records plus measurement rules (clause 7.2.1).
- ←
How quantities actually executed but not certified by the supervising engineer or the employer are measured at settlement: the GB 50500-2013 Chapter 8 measurement procedure, the 'deemed approval' rule where verification is overdue, hard cases of non-measurement, and the routes of evidence reinforcement and construction cost expert assessment
Quantities not certified under the standard procedure are in principle not measured at settlement, but 'not certified' does not mean 'cannot be measured'; three scenarios apply: (1) where the contractor has submitted, for the contractual measurement period, the report of the executed quantities and the employer neither verifies nor notifies within 7 days after receipt, this is deemed approval and the quantities listed in the report are measured directly (GB 50500-2013 Clause 8.2.3; the duty-bearer is the employer - the clause does not say 'certified by the supervising engineer'); (2) where no report was ever submitted, or the employer verified within the period and raised an objection and on-site measurement was not concluded with certification, direct measurement is not allowed - measurement is possible only after confirmation by evidence reinforcement or construction cost expert assessment; (3) where quality was not accepted or failed acceptance, or the contractor executed work beyond the contract scope or reworked for its own causes, no measurement in any case (Clause 8.1.3). Measurement after cure requires four conditions met simultaneously: the work is actually executed and quality acceptance has passed; it is within the contract scope or a variation consented by the employer; quantities are calculated under the calculation rules of the current national measurement standards (Clause 8.1.1, a mandatory provision); and a verifiable chain of evidence supports it. Where there are no certified materials, the drawings cannot show the work, site inspection cannot determine it and the applicant has no valid evidence, the item is treated in assessment as 'not capable of assessment' and is not measured.
- ←
Constituent documents of the final account (cover / signature page / contents / compilation notes / tiered summary tables and their standard sources) and the list of compilation bases (GB/T 51095-2015, GB/T 50326-2017, DB37/T 5130-2018 etc.)
Per GB/T 51095-2015 Article 8.2.2, final account documents shall include the cover, signature page, contents, compilation notes, the final account summary and the project-wise and unit-works final account summaries, with BOQ-priced outputs per Appendix F; compilation bases per Article 8.2.4 (10 items), GB/T 50326-2017 Article 18.3.3 (5 items) and DB37/T 5130-2018 Article 8.2.4 (9 items); under BOQ pricing the cover, title page, notes and summary formats follow GB/T 50500-2024 Appendix B Table B.4.1, Appendix C Table C.4.1, Appendix D Table D.3.1 and Appendix E Table E.6.1.
- ←
Measurement of the works rules in Chapter 8 of GB 50500-2013: measurement basis and mandatory provisions, verification of completed-works quantity reports and deemed approval upon lapse of the period, notice procedure for on-site measurement and consequences of absence, and review of objections to measurement results
Chapter 8 of GB 50500-2013: quantities must be calculated under the rules of measurement of the current national measurement codes and determined by the quantities of the work the contractor has actually completed and that are to be measured (clauses 8.1.1 and 8.2.1 are mandatory provisions; tender BOQ quantities are only estimates). The contractor submits the completed-works quantity report each agreed period; the employer verifies within 7 days of receipt and notifies the contractor; where verification is not done within the agreed time, the quantities in the report are deemed the quantities actually completed by the contractor (8.2.3). On-site measurement verification requires notice to the contractor 24 hours before measurement; if the contractor is absent it is deemed to approve the employer's verification result, and if the employer fails to notify as agreed so that the contractor cannot attend, the verification result is invalid (8.2.4). A contractor disputing the verified result must raise written objections within 7 days of notice with calculation records attached, and the employer reviews within 7 days; continuing disputes follow the contract's dispute resolution (8.2.5). Under the current GB/T 50500-2024, clauses 7.1.7 and 7.1.8: measurement results signed and confirmed by both parties serve as the basis for contract price adjustment and settlement.
- ←
Handling the mismatch between construction-drawing quantities and tender BOQ quantities: measurement of actually completed quantities under GB 50500-2013 Chapter 8 and the 15% deviation price adjustment of Section 9.6 (including the divergence between the two lump-sum contract regimes of Clauses 8.3.1/8.3.2), against GB/T 50500-2024 Sections 7.2/8.2/8.9 routing the rules by contract type
GB 50500-2013 Clause 8.2.1 (a mandatory provision) requires that 'quantities shall be determined by the quantities of the contract works that the contractor has completed and that are to be measured'; the quantities stated in the tender BOQ are only estimated quantities and the common basis for tender pricing, and the final account quantities are determined by the quantities actually completed and to be measured, calculated by the contractor under the calculation rules of the current national measurement standards, not by the BOQ quantities. Clause 8.3.1 provides that for lump-sum contracts formed by tendering on a bill of quantities basis the quantities are still calculated under Section 8.2 (i.e. quantity differences remain adjustable), which diverges from Clause 8.3.2: for lump-sum contracts formed by letting the works on the basis of construction drawings and budgets examined and approved, except for variations, the BOQ quantities are the final settlement quantities. GB/T 50500-2024 instead routes the rules by contract type: for unit-rate contracts the employer bears the BOQ defects, the works are re-measured under Clause 7.2.1 and the price adjusted via Clause 8.2.1 (15% as the boundary) and then Clauses 8.9.1/8.9.2; for lump-sum contracts Clause 7.2.2 allows no re-measurement, and Clause 8.2.3 provides that 'the contract price and the time for completion shall not be adjusted for defects in the contract bill of quantities' (except items priced at provisional quantities). Directional rule for quantity deviations beyond 15%: where the increase exceeds 15%, the all-in unit rate of the increased portion is adjusted downwards; where the decrease exceeds 15%, the all-in unit rate of the remaining portion after the decrease is adjusted upwards.
- ←
Reviewing the final account of lump-sum contracts: adjust only the agreed-adjustable content on the contract total, plus the universal checkpoints, plus the compiling method by contract type
Lump-sum review adjusts, on the contract total, only the content agreed adjustable and the risk factors beyond the agreed scope (T/ZBD 100.5-2023 clause 3.1.5): judge the non-adjustable part from the measurement, pricing and risk-scope clauses and review adjustments only within the adjustable range; against the non-adjustable part, check the settlement drawings, scope and acceptance reports against the contract-price content - unexecuted or inconsistent parts are generally written down; BOQ gaps and quantity issues in a lump-sum contract are deemed fully verified by the contractor and generally attract no further adjustment (unless the employer issued the BOQ and the contract says adjustable); materials above contract brand or quality without employer request add nothing, below contract re-price down; statutory HSE and similar adjust per policy with the contract - agreed non-adjustable preliminaries stay; overlapping interfaces between specialist packages and the main contractor are written down; provisional materials adjust per the approved-price slips (usually materials and tax only); employer-supplied materials and metered water and electricity deduct against contract quantities, over-drawals without back-orders not counted. Clause 3.1.4 lists the universal checkpoints whatever the form: scope changes, work interfaces, whether quantities need re-determination, gaps, provisional specialist works, provisional material and plant prices, employer-supplied materials. DB37/T 5130-2018 clause 8.2.5 sets the compiling method by type: lump-sum adjusts the adjustable on the total; unit-rate holds all-in rates fixed within the risk band and measures as executed; cost-plus computes cost, fee and taxes per the agreed method.
- ←
Determining the drawing basis for the final account: as-built drawings govern (as-built drawings + variation/site instruction records jointly verify the work actually completed), with construction drawings serving as the benchmark for contract-scope definition and variation-difference comparison
The final account is based on the as-built drawings — more fully stated: the qualified work actually completed is verified by 'as-built drawings + design changes, variations, site instructions / variation records and other variation documents'. GB/T 50326-2017 Clause 18.3.3 lists 'as-built drawings and variation documents' as bases for the final account without separately listing construction drawings; JGJ/T 185-2009 Clause 4.2.4 provides that absent changes, construction drawings stamped as as-built become the as-built drawings (the two being equivalent), and where changes exist, the changed content must be redrawn into the as-built drawings; the construction (contract) drawings recede in the final account to the benchmark defining the contract scope and comparing variation differences (GB/T 50500-2024 Clause 7.4.1).
- ←
Final account deliverables composition, archiving scope, dual-track electronic file requirements, and cost consultants' quality liability (GB/T 50500-2024 Chapter 12 + GB/T 51095-2015 Chapter 8)
Final account deliverables composition per GB/T 51095-2015 8.2.2 (cover, signature page, contents, explanatory notes of the estimate, final account summary table, single-project/unit-work final account summary tables); review deliverables per 8.3.1 (final account review cover, signature page, final account review report, final account approval certification and sign-off form, summary comparison tables). Archiving per GB/T 50500-2024 Section 12.3: deliverables must be archived dual-track as paper originals + electronic files, with electronic files meeting standard data-interface requirements; archiving may be phased or after the final account is completed; handover requires a transfer list signed and sealed by both parties. Consultant quality liability per 1.0.5's three-tier system: the consultant is responsible to the client, and after client confirmation the deliverable counts as the client's toward the other party; deliverables must be prepared by cost professionals and reviewed/signed with the practice seal by Grade-1 registered cost engineers (1.0.4); final account review conclusions are jointly certified and signed off by the employer, contractor, and consultant (GB/T 51095-2015 8.3.8).
- ←
The role of as-built drawings in construction payment settlement: statutory basis status and graphical benchmark for audit quantity checks
As-built drawings are a statutory basis for the final account and the graphical benchmark for audit quantity checks: GB/T 50326-2017 Clause 18.3.3 lists them among the foremost bases for the final account; GB/T 51095-2015 8.2.4/8.3.4 require checking against them in both preparation and audit; DB37/T 5130-2018 8.3.8 requires checking 'whether the final account contents agree with the as-built drawings and site instruction / variation record contents'. Quantities not reflected in the drawings (especially concealed works) may be reduced in the final account; each variation and site instruction / variation record must be drawn into the as-built drawings and confirmed by the four parties; the drawings must bear a compliant as-built drawing certification stamp (50 x 80 mm) to be a valid basis.
- ←
Settlement review vs fiscal appraisal vs audit: subject, nature, object, and effect
The final account is a civil-contract act of employer and contractor (checking and confirming the final account documents); fiscal appraisal is the finance department's administrative supervision of fiscally invested funds; audit is the audit institution's statutory audit supervision of government-invested projects under the Audit Law. Fiscal appraisal and audit conclusions in principle do not affect the validity of the employer-contractor contract, unless the contract expressly makes them the settlement basis.
- ←
Full process of construction payment: advance payment, safety-measures fee, progress payment, interim settlement by construction stage, final account, retention money and final settlement (GB/T 50500-2024 Chapters 9-10)
Payment along the timeline in six segments: advance payment (for works with contractor-procured materials, neither below 10% nor above 30% of the contract price after deducting provisional sums etc., prepaid before commencement, recovered as agreed) → statutory safety provisions (at least 50% prepaid within 28 days after commencement; not deducted from progress payments, recovered once at the final account) → progress payments (amount due = cumulative completed − cumulative paid − deductions; not less than 80% of the cumulative completed value where the contract is silent) → interim settlement by construction stage (new in 2024: signed stage settlements enter the final account without re-pricing; stage payments not below 80%) → final account (thirteen heads; failure to check or to certify in time is deemed acceptance) → retention money (3% cap) and final closure (defects liability period generally 1 year, 2 at most). The chain runs on contract-agreed time limits with a 28-day backstop; judicial enforcement of "accepted at the submitted price" requires an express contractual provision.
- ←
Claim costs in the final account: settlement line item + 28-day procedure chain + review and determination rules
Claim costs enter the final account only where both procedural compliance and a complete chain of evidence are satisfied: (1) line item — item 11 of the final account price under GB/T 50500-2024, Clause 10.3.2 is the "engineering claim amount", a separately billed item in the final account documents; (2) procedure — absent contract agreement, the 28-day chain applies (Notice of Claim -> claim report -> continuing notices -> final report); failure to give notice in time is deemed waiver, and the other party's failure to respond in time is deemed acceptance (8.11.3/8.11.4); (3) determination — amounts are stated per the claim documents and confirmed site instructions signed by both parties, and where disputed instructions enter appraisal they are computed under the GB/T 51262-2017 5.9.1 rules.
- ←
The relation between measurement and payment: quantities fixed before payment (the causal chain of GB/T 50500-2024 Chapters 7 and 9)
Measurement is the precondition and quantitative basis of payment, and payment is the monetary realization of the measurement result: progress payment = confirmed measured quantities x all-in unit rates; measurement results, once checked and confirmed by both parties, serve as the basis for computing the price but not as a basis for acceptance of conforming delivery; the measurement period should coincide with the payment period; for disputed BOQ items, payment certificates are issued and payment made first on the undisputed portion.
- ←
Bases the employer must provide for disallowance / downward adjustment on review of the settlement: the review-basis checklist, type-by-type reconciliation, and burden of proof
The employer's claimed disallowance / downward adjustment on review must be "evidence-based and itemized": the bases include contract documents, tender documents, construction/as-built drawings, changes/negotiations/site instructions and variation records/claims/minutes, employer's approval of material prices, site survey and re-verification records, and pricing bases; different types of disallowance / downward adjustment (quantities, unit prices, changes/site instructions, provisional sums for specified materials / nominated works, free-issue materials (by the employer), preliminaries, unexecuted items) require different evidence; disallowance / downward adjustment opinions should be written with "amount + reason + basis document", and review conclusions must be jointly certified and signed off by employer, contractor, and consultancy; in construction cost expert assessment (judicial appraisal) the employer bears the burden of proof for the disallowance / downward adjustment — failure of proof means rejection.
- ←
Site instructions and certified records overview: applicable matters and prohibited items, the five-node handling procedure, graded signing authority, the 2024 standard basis and settlement application
Certification runs a five-node closed loop: assess reasonableness beforehand and survey the original conditions → at occurrence, measure on site, keep photos, have all parties sign the original vouchers → submit the certification file within the contract-agreed time → the supervising engineer reviews, the chief supervising engineer signs, the employer approves → participate in acceptance, confirm the completed content and compute the final cost. Signature authority: written documents signed by both parties' site management within their scope of duty are valid pricing vouchers (GB/T 50500-2024 cl. 12.2.1); the supervisor certifies facts strongly but prices weakly — priced certifications need the joint sign-off of employer, contractor and supervisor (T/CAEC 006-2024 cl. 7.2.9); a one-party signature binds only the signing party. With the 2024 code dropping the site-certification clause, off-contract work flows through three channels — variation, additional works and dayworks — and dayworks certification reports not verified in time are deemed accepted (cl. 7.5.5).
- ←
Appendix D “Pricing Statements” of GB/T 50500-2024: required contents of the four statement tables and dispute risks of omissions (tender price ceiling / tender (priced offer) / final account statement + method of measurement statement for the bill of quantities (BOQ))
GB/T 50500-2024 Appendix D has four statement tables: D.1.1 tender price ceiling preparation (review) statement must include project overview, scope, basis of preparation (review), special requirements (if any), and other issues to be explained; D.2.1 tender (priced offer) statement must include scope, item description (work item specification), planned duration, site conditions, project execution plan (construction methodology and site organization) features, and other issues to be explained; D.3.1 final account (interim) preparation (review) statement must include project overview, scope, basis of preparation (review), and other issues; D.4.1 statement of method of measurement for the BOQ must specify the names and numbers of the national/industry measurement standards adopted and list supplementary rules of measurement (with 4.1.3). Omitting basis details, scope delimitation, supplementary rules of measurement, and explanations of price and percentage rate determination (GB/T 51095-2015 8.2.3) are high-frequency final account dispute triggers.
- ←
Design change overview: authority to propose, classification and grading, approval and implementation, three-tier pricing, settlement and disputes across six links (with variation concept cross-links and FIDIC mapping)
The design-change full chain: any of four parties may propose; only the original designer issues the document (Survey and Design Administration Regulations, art. 28); the chief supervising engineer must sign it off before construction; approve first, then construct; price on the three-tier ladder; settle on the documents. Procedural red lines: verbal instructions are no pricing voucher (unless construction per them is proven); the supervisor's emergency verbal instruction must be confirmed in writing within 24 hours (local supervision codes); emergency-rescue works proceed first with formalities completed within 10 working days. Pricing runs the ladder "identical — contract rate; analogous — converted; different — negotiated" (GB/T 50500-2024 cl. 8.9.1), with quantities beyond ±15% re-rated (down for increases, up for decreases) and the preliminaries scheme to be submitted before execution or the adjustment forfeited. Claims run the double 28-day limit, forfeited on default; the variation price takes the ninth head of the final account, disputes assessed across five tiers by instructions, drawings and confirmations.
- ←
Provisional sums at final account: settlement line item, replacement paths, VAT basis and review essentials (GB/T 50500-2024)
At final account, provisional sums are dealt with as "the actually determined price replaces the provisional price, with the contract price adjusted by the difference": PC sums for materials (pre-tax) are replaced by the pre-tax winning bid price or by the pre-tax price from an inquiry/self-quotation confirmed by the employer, adjusting only the PC sum item for materials within the all-in unit rate, with all other cost elements unchanged; provisional sums for nominated specialist subcontract works (tax-inclusive) are replaced in their entirety by the winning tax-inclusive subcontract price. These enter settlement line item 4, "adjustment of provisional prices after procurement"; provisional sums for nominated specialist subcontract works do not enter the VAT calculation base; the core vouchers are the price-confirmation sheet (employer's approval of material prices) / letter of acceptance confirmed by both parties.