Panorama of final account rules: starting point, basis of preparation, the 13 price components, review and confirmation, and finality (GB/T 50500-2024)

The final account is the activity of computing, adjusting, confirming, and paying the contract price after taking-over (completion acceptance) — the summary of interim settlements by construction stage (GB/T 50500-2024, Clause 2.0.35); it starts after the whole project passes taking-over (Clause 10.1.4), with 28 days as the period absent contractual agreement (Ministry of Construction Order No. 107, Article 16). The settlement price is itemized in 13 items in order (Clause 10.3.2), with preliminaries and the main contractor's attendance and coordination provisions recomputed (Clause 10.3.3); the employer's overdue non-checking is deemed acceptance (Clause 10.3.8), and after both parties sign and seal, no re-checking and no claims over pre-settlement events (Clauses 10.3.12, 8.11.22).

Topic Positioning

A panorama framework card of final account rules: starting point, basis of preparation, the 13 price components, review and confirmation, and finality — the navigation entry to the special settlement rules of the 15% price adjustment, claim time limits, provisional sums for specified materials/nominated works, free-issue materials (by the employer), etc.

Core Conclusions

The final account is the activity of computing, adjusting, confirming, and paying the contract price after the works pass taking-over (completion acceptance) — the summary of interim settlements by construction stage (GB/T 50500-2024, Clause 2.0.35); it starts after the whole project passes taking-over (Clause 10.1.4), with 28 days as the period absent contractual agreement (Ministry of Construction Order No. 107, Article 16). Basis of preparation includes contract documents, as-built drawings, variation, negotiation, site instruction and claim documents, employer's material price approvals, mutually confirmed price adjustments, and pricing bases (GB/T 50326-2017, 18.3.3). The settlement price is itemized in 13 items: contract BOQ total; BOQ errors/omissions; provisional sums; provisional sums for specified materials/nominated works; main contractor's attendance and coordination provisions; dayworks; changes in costs; changes in laws and policies; valuation of variations; additional works; claims; penalties; others (Clause 10.3.2). Preliminaries and the main contractor's attendance and coordination provisions are recomputed — interim settlement by construction stage listings do not serve as the basis (10.3.3). The employer's overdue non-checking is deemed acceptance (10.3.8); after signature and seal, no re-checking and no claims over pre-settlement events (10.3.12, 8.11.22).

Applicable Boundaries

Applies to the final account of works priced on a bill of quantities basis. This card is a framework overview — the 15% adjustment, 28-day claims, provisional sum replacement, free-issue material clawback, price adjustment, and objection remedies each have dedicated cards; contractual agreement takes precedence over the standard's defaults.

Further Reading

GB/T 50500-2024, Chapter 10 (10.1.4, 10.3.1-10.3.17), Chapter 8, Clause 2.0.35; Ministry of Construction Order No. 107, Article 16; Cai Jian [2004] No. 369, Article 16; GB/T 51095-2015, Sections 8.2, 8.3; GB/T 50326-2017, Clause 18.3.3.