Responding to an employer that long delays final account review: the deemed approval upon lapse of the response period and the escalating remedy ladder
Where the employer fails to check or respond to the final account documents within the prescribed time, the documents are deemed accepted per Ministry of Construction Order No. 107, Article 16 and GB/T 50500-2024, Clause 10.3.8 (response period 28 days absent agreement; the review period runs from the employer's receipt of the complete final account materials); the contractor may then assert deemed acceptance of the payment application (Clause 10.3.16), interest on overdue payment (State Council Decree No. 728: no less than the 1-year LPR or 0.05% per day), a cost consultancy's separately issued review report, administrative mediation, and finally arbitration or litigation.
Applicable Codes
- 建设部令第107号 建筑工程施工发包与承包计价管理办法
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB/T 51095-2015 建设工程造价咨询规范
- 国务院令第728号 保障中小企业款项支付条例
- 财建〔2004〕369号 建设工程价款结算暂行办法
- DB42/T 823-2021 建设工程造价咨询质量控制规范
Topic Positioning
When the employer long fails to check, respond to, or pay the final account documents, the contractor can press its rights along the path of "deemed approval upon lapse of the response period + escalating remedies". This card compiles the statutory bases of deemed acceptance, the period-commencement rules, and the full response workflow — directly usable in final account practice and dispute handling.
Core Conclusions
- Periods and commencement: the final account review period runs from the employer's receipt of the "complete final account materials" (Cai Jian [2004] No. 369, Article 16) — ensure signed receipt with a materials checklist at submission; absent contractual agreement all periods are deemed 28 days (Ministry of Construction Order No. 107, Article 16).
- Deemed acceptance: where the employer fails to check or submit review comments within the agreed period, the final account documents are deemed accepted and the final account confirmed (GB/T 50500-2024, Clause 10.3.8; Order No. 107, Article 16 — failure to respond within the prescribed time deemed acceptance). An express "overdue non-response deemed acceptance" clause in the contract earns stronger judicial support.
- Payment-stage fallback: after the payment application for the final account price is submitted, the employer's failure to verify or issue the payment certificate within the prescribed time deems the application accepted and payable as listed (Clause 10.3.16); continued non-payment may be pursued by notice with interest and claims (Clause 10.3.17).
- Interest cost: where government agencies, public institutions, and large enterprises pay small and medium enterprises late, the agreed rate may not be below the 1-year LPR at contract conclusion, and absent agreement interest accrues at 0.05% per day (State Council Decree No. 728, Article 15).
- Escalating remedies: where the employer delays or refuses certification and sign-off without justification, the cost consultancy, failing coordination, may separately submit a final account review report (GB/T 51095-2015, Clause 8.3.8); objections to review opinions may be mediated by the county-level or higher construction authority within one month of receipt, failing which arbitration or litigation (Order No. 107, Article 16).
Applicable Boundaries
Applies to the final account stage after passing taking-over (completion acceptance). Deemed acceptance presupposes the contractor's timely submission of complete final account documents — incomplete materials restart the period and hand the employer a pretext for delay; where the contractor submits late, the employer may compile the final account from available materials (the reverse rule of Clause 10.3.5). Absent a deemed-acceptance clause, some courts turn to construction cost expert assessment (judicial appraisal), and full-amount claims may be less likely to succeed — contract wording and judicial practice govern.
Further Reading
Core bases: Ministry of Construction Order No. 107, Article 16 (28-day fallback, deemed acceptance, administrative mediation); GB/T 50500-2024, Clauses 10.3.5/10.3.8/10.3.16/10.3.17; GB/T 51095-2015, Clause 8.3.8 (consultancy's separate review report); State Council Decree No. 728, Article 15 (interest on overdue payment); Cai Jian [2004] No. 369, Article 16 (review period: overall project final account reviewed within 30 days of submission — see DB42/T 823-2021, Clause 8.1.8).