Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Legal consequence chain when the employer fails to check the final account or pay on time: GB/T 50500-2024 cl. 10.3.8/10.3.16/10.3.17/10.5.8/10.5.9 “deemed acceptance + liability for breach of contract” and the 28-day fallback

The consequences of the employer failing to check the final account on time progress in four layers: (1) no checking or no comments within the agreed time -> the contractor's final account documents are deemed accepted and the final account is confirmed (GB/T 50500-2024 cl. 10.3.8); (2) failure to verify the payment application or to issue the final account payment certificate -> the payment application is deemed accepted and the final account money must be paid per the amount stated in the application (cl. 10.3.16); (3) still no payment -> the contractor may give notice requiring payment and may claim per cl. 8.11.9 (cl. 10.3.17); (4) at the final closure of accounts after the defects liability period terminates, overdue checking without comments on modification -> deemed consent to the final closure application and deemed issuance of the final closure payment certificate, with liability for late payment per the contract or per laws and regulations (cl. 10.5.8, 10.5.9). Where no period is agreed, the 28-day fallback applies (former MOC Order No. 107 art. 16, carried on by current MOHURD Order No. 16 art. 18); judicial enforcement presupposes a contractual “deemed acceptance” clause (Fa Shi [2020] No. 25 art. 21).

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第10.3.8、10.3.16、10.3.17、10.5.8、10.5.9条
  • 原建设部令第107号《建筑工程施工发包与承包计价管理办法》第十六条(已被住建部令第16号废止,内容由第十八条承继)
  • 住建部令第16号《建筑工程施工发包与承包计价管理办法》第十八条(现行)
  • 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第21条

Topic Positioning

What are the legal consequences when the employer, having received the final account documents, fails to check them, respond, issue the payment certificate or pay on time? This card sets out the “four-layer consequence chain” under Chapter 10 of GB/T 50500-2024: final account documents deemed accepted -> payment application deemed accepted with payment due per the amount stated -> notice to pay + claim -> final closure of accounts deemed consented + liability for late payment, together with the 28-day departmental-rule fallback and the preconditions for judicial application.

Core Conclusions

Consequences escalate through the two stages of the final account and the final closure of accounts:

I. Final account documents “deemed accepted” (cl. 10.3.8) Original text: “Where the employer, within the agreed time after receiving the contractor's final account documents, neither checks the final account as agreed nor raises comments on the checking, the contractor's final account documents shall be deemed accepted by the employer and the final account confirmed.” — the final account amount is fixed by the contractor's submitted documents and the confirmation procedure is complete.

II. Payment application “deemed accepted”, payment due per the amount stated (cl. 10.3.16) Original text: “The employer shall, within the prescribed time after receiving the contractor's final account payment application, verify it and issue the final account payment certificate to the contractor. Where the employer neither verifies it nor issues the final account payment certificate to the contractor within the prescribed time, the contractor's final account payment application shall be deemed accepted by the employer, and the employer shall, within the prescribed time after receiving the contractor's final account payment application, pay the contractor the final account money per the amount stated in the contractor's final account payment application.” — note that the consequence is not only “acceptance” but directly creates an obligation to pay the amount stated in the application.

III. Still no payment: notice to pay + right to claim (cl. 10.3.17) Original text: “Where the employer fails to pay the final account money as agreed, the contractor may give notice requiring the employer to pay and may claim against the employer per cl. 8.11.9 of this standard.” — i.e. entering the construction claims procedure (section 8.11: the Notice of Claim / claim report nodes; the symmetrical deemed-acceptance mechanism for late responses is covered by the claims card), which may stack with liability for interest on overdue payment.

IV. The same applies at the final closure of accounts (cl. 10.5.8, 10.5.9) Cl. 10.5.8: “The employer shall, within the agreed time after receiving the contractor's final closure application, complete the checking and issue the final closure payment certificate to the contractor. Where the employer neither completes the checking in time nor raises comments on modification, it may be deemed to agree to the contractor's final closure application and to have issued the final closure payment certificate.” Cl. 10.5.9: “The employer shall complete payment within the agreed time after issuing the final closure payment certificate. Where the employer pays late, it shall bear liability for breach of contract per the contract or per laws and regulations.” — the final closure of all project payments after the defects liability period terminates, with consequences symmetrical to the final account stage (deemed consent + deemed issuance of the payment certificate + liability for late payment).

V. Period fallback: 28 days Former MOC Order No. 107, Measures for Administration of Pricing of Construction Project Contracting, art. 16: “Where the contract does not clearly agree the periods for the above matters, the agreed periods may be deemed to be 28 days for both parties.” Note: Order 107 was repealed by MOHURD Order No. 16 (effective 2014-02-01), and the rule is carried on by art. 18 of Order No. 16 (final account documents deemed accepted where no response is given in time; 28 days where no period is agreed; the confirmed final account documents serve as the basis for the project final accounts).

VI. Precondition for judicial enforcement: contract agreement GB/T 50500-2024 is a recommended national standard (GB/T); whether “deemed acceptance” can be enforced in litigation depends on the contract: Article 21 of the SPC Interpretation (I) on Legal Issues Concerning the Trial of Construction Contract Disputes (Fa Shi [2020] No. 25) provides that where the parties agree that the employer's failure to respond within the agreed period after receiving the final account documents is deemed acceptance of the final account documents, the agreement governs, and where the contractor requests settlement of the project price per the final account documents, the people's court shall support it; where the contract contains no such agreement, most courts will not support a claim based merely on the recommended standard or on the departmental rule (the three-element test is set out in the cited card).

Applicable Boundaries

  • All consequences presuppose the contractor submitting complete final account documents/payment applications within the agreed periods; incomplete documents restart the period and instead give the other party grounds for delay (where the contractor is late, the employer may itself compile final account documents from the available data per cl. 10.3.5 — the reverse rule).
  • Cl. 10.5.8 and 10.5.9 apply only to the final closure stage after the defects liability period terminates, a procedure distinct from the cl. 10.3 final account stage — they must not be mixed.
  • Whether a “deemed acceptance” assertion fully succeeds in litigation depends on the contract terms and the evidence (service and acknowledgment of receipt, completeness of the documents); some courts may instead turn to construction cost expert assessment (judicial appraisal).
  • For state-funded projects the employer must by rule engage a cost consultancy to review; “deemed acceptance” cannot exclude the statutory review procedure.
  • This card lists only the consequence chain; the contractor's concrete countermeasures (letter of demand, a separate review opinion, administrative mediation, arbitration/litigation) are in cited card ac7f8b5c.

Further Reading

  • GB/T 50500-2024 Chapter 10: 10.3.5 (reverse rule where the contractor fails to submit in time), 10.3.7 (partial final account of the undisputed parts first), 10.3.8, 10.3.10 (contractor's objection period against the checking result), 10.3.16, 10.3.17, 10.5.5 (return of the remaining retention money after the defects liability period terminates), 10.5.8, 10.5.9; claims procedure in section 8.11 (8.11.3 contractor's claims, 8.11.4 employer's counterclaims, 8.11.5 employer's handling of claims).
  • Departmental rules: former MOC Order No. 107 art. 16 (repealed); current MOHURD Order No. 16, Measures for Administration of Pricing of Construction Project Contracting, art. 18 (carried on, 28-day fallback retained).
  • Judicial: Fa Shi [2020] No. 25 art. 21 (following Fa Shi [2004] No. 14 art. 20); Cai Jian [2004] No. 369, Interim Measures for Settlement of Construction Project Payments, art. 16 (the review period runs from receipt of the complete final account documentation; no response is deemed acceptance).
  • Related cards: the three judicial elements and the contractual incorporation mechanism — card_302b266d; contractor response paths (notice to pay, interest, mediation and arbitration) — card_ac7f8b5c; the contractor's objection ladder against review results — card_631ed5aa; Order 107 vs Order 16 evolution — card_dd8f1895.

Keywords

Cited By