The end-to-end time-limit chain of the final account: submission -> checking/review -> signature and seal confirmation -> payment -> final closure after the defects period - nodes, day counts, clause numbers and documentary proof requirements (GB/T 50500-2024 section 10.3 + GF-2017-0201 clause 14 + MOHURD Order No. 16)
The final account time-limit chain = submission (within 28 days after the works pass completion acceptance, GF-2017-0201 clause 14.1) -> supervising engineer checks within 14 days -> employer approves within 14 days (28 days in total from receipt of the final account application; failure to complete approval or raise objection within that time is deemed approval, and from day 29 after receipt the final payment certificate is deemed issued; GB/T 50500-2024 clause 10.3.8 is to the same effect) -> payment within 14 days after issue of the certificate (GF clause 14.2(2); 50500 clause 10.3.16) -> application within 7 days after termination of the defects liability period -> 14-day approval -> 7-day payment for the final closure of accounts after the defects period (GF clause 14.4; 50500 clauses 10.5.5/10.5.8/10.5.9). Where the contract sets none of these periods, all may be taken as 28 days under Article 18 of MOHURD Order No. 16; GB/T 50500-2024 itself states only 'agreed time/stipulated time' and procedural consequences, and gives no fixed day counts. Uncontested parts proceed first as a partial final account (clause 10.3.7 paragraph 2), contested parts are handled under Chapter 11; after signature and seal confirmation no repeat checking is allowed (clause 10.3.12).
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第10.3.6~10.3.12条、第10.5.5/10.5.8/10.5.9条、第10.1.9条、App. F Table F.5.1
- GF-2017-0201 建设工程施工合同(示范文本) 通用合同条款第14.1款、14.2款、14.4款
- 住房和城乡建设部令第16号 建筑工程施工发包与承包计价管理办法 第十八条、第十九条、第二十条
- 财建〔2004〕369号 建设工程价款结算暂行办法 第十六条
- DB42/T 823-2021 建设工程造价咨询质量控制规范 第8.1.8条
Topic positioning
This card maps the complete time-limit chain of the construction final account, from 'the contractor submits the final account documents' through 'payment of the final account' to 'final closure of accounts after the defects period', giving for each node the employer's/supervising engineer's review and approval periods, the corresponding clause numbers of the model contract text and of GB/T 50500-2024, the legal consequences of inaction beyond the time limits, and the documents and proof to be retained at each step, for direct use in settlement handling, reminders and dispute response.
Core conclusion
1. First separate 'who supplies the day counts' (avoid mixing instruments) Throughout section 10.3 of GB/T 50500-2024 'Standard for BOQ Pricing of Construction Works' the wording is 'agreed time/stipulated time': it lays down procedure and the consequences of delay, not fixed day counts. The day counts come from the contract - clause 14 of the general conditions of GF-2017-0201 'Model Construction Contract' gives default values (the particular conditions may agree otherwise); where the contract is silent on the periods, Article 18 of the 'Measures for Administration of Pricing of Construction Contract Award and Subcontracting' (MOHURD Order No. 16) applies: 'national provisions shall be followed; where the State has none, the agreed period may be taken as 28 days'.
2. The time-limit chain step by step (clause numbers + day counts)
- Contractor submission: GF-2017-0201 clause 14.1 [Final account application] - 'Unless otherwise agreed in the particular conditions, the contractor shall submit the final account application to the employer and the supervising engineer within 28 days after the works pass completion acceptance, together with complete final account documents.' The application shall state: (1) the final account contract price; (2) the amounts the employer has paid the contractor; (3) the retention money to be withheld (except where performance security has been posted or another form of work quality guarantee provided); (4) the contract price the employer should pay the contractor.
- Supervising engineer check: GF clause 14.2(1) - 'The supervising engineer shall complete the check within 14 days of receiving the final account application and forward it to the employer.'
- Employer approval: GF clause 14.2(1) - 'The employer shall complete approval within 14 days of receiving the checked final account application from the supervising engineer, and the supervising engineer shall issue to the contractor the final payment certificate signed by the employer'; where the supervising engineer or the employer has an objection, it may require the contractor to correct and supplement the documents, and the contractor shall resubmit the corrected application.
- Consequence of failure to approve in time: same clause - 'Where the employer neither completes approval within 28 days of receiving the final account application submitted by the contractor nor raises an objection, the final account application submitted by the contractor is deemed accepted, and from day 29 after the employer receives the application the final payment certificate is deemed issued.'
- Payment: GF clause 14.2(2) - 'The employer shall complete final payment to the contractor within 14 days after issue of the final payment certificate'; late payment bears liquidated damages at the PBOC benchmark lending rate for loans of the same type for the same period, doubled where payment is more than 56 days late.
- Final closure: GF clause 14.4.1 - within 7 days after the certificate of termination of the defects liability period is issued, the final closure application is submitted stating the retention money, the retention to be deducted and the increases and decreases during the defects liability period; clause 14.4.2 - the employer completes approval and issues the final closure certificate within 14 days of receipt; failure to complete approval without raising amendments is deemed consent, and the certificate is deemed issued from day 15 after receipt; payment is completed within 7 days after issue, with late-payment damages as above.
3. GB/T 50500-2024 section 10.3 clause comparison (procedure and consequences of delay)
- Clause 10.3.6: on receipt of the final account documents the employer shall check them within the agreed time; where it considers that the contractor should further supplement and revise the documents, it shall raise checking comments within the agreed time, and the contractor shall supplement and revise as reasonably required within the agreed time after receiving the comments and resubmit for review and confirmation.
- Clause 10.3.7: on receipt of the resubmitted final account documents the employer shall review them within the agreed time and notify the contractor of the result - paragraph 1, where neither party has an objection, both shall sign and seal the final account documents within the agreed time and the final account is confirmed; paragraph 2, where the employer or the contractor objects to the review result, the uncontested part is handled as a partial final account under paragraph 1, and the contested part is settled by negotiation between the parties, failing which the Chapter 11 dispute resolution applies.
- Clause 10.3.8: where the employer, within the agreed time after receiving the final account documents, neither checks them as agreed in the contract nor raises checking comments, the final account documents submitted by the contractor are deemed accepted by the employer and the final account is confirmed.
- Clause 10.3.9: where the contractor, within the agreed time after receiving the checking (or review) comments raised by the employer, neither confirms nor raises an objection as agreed in the contract, the checking comments raised by the employer are deemed accepted by the contractor and the final account is confirmed.
- Clause 10.3.10: where the employer entrusts a cost consultant to check the final account, the check confirmed by the client is treated as the employer's check; the consultant shall complete the check within the agreed time; where its check result differs from the contractor's final account documents, it shall submit the result to the contractor for review and copy it to the employer; the contractor shall submit its agreement or disagreement with an explanation within the agreed time; on receiving an objection the consultant shall review again within the agreed time, closing under clause 10.3.7 paragraph 1 if no objection remains and under clause 10.3.7 paragraph 2 otherwise; where the contractor fails to raise a written objection within the agreed time after receiving the check result, the final account documents checked by the consultant are deemed accepted by the contractor.
- Clause 10.3.11: final account documents checked without objection by the authorised personnel of the employer, or of the cost consultant entrusted and confirmed by the employer, and the authorised personnel of the contractor shall be signed and sealed by both parties; a party refusing to sign shall bear liability for breach and the losses caused.
- Clause 10.3.12: once the final account check is complete and both parties have signed and sealed, the employer shall not require the contractor to repeat the check with another cost consultant; save as laws and regulations provide otherwise, the final account documents signed and sealed by both parties take effect as agreed in the contract.
- Clause 10.1.9: where the parties dispute the stage settlements during construction or the final account, and agreement cannot be reached after checking and negotiation, the Chapter 11 dispute resolution applies; dispute review or mediation is recommended.
- Clauses 10.5.5/10.5.8/10.5.9: after the defects liability period terminates, the contractor shall submit the final closure application within the agreed time; the employer shall complete the check and issue the final closure payment certificate within the agreed time; failure to check while raising no amendments may be deemed consent to the application and the certificate deemed issued (10.5.8); payment shall be made within the agreed time after issue, with liability for breach under the contract or laws and regulations for delay (10.5.9).
4. Documents and proof required at each step
- Submission: the completion acceptance report/filing form; the final account documents and their schedule (titles, number of copies); the receipt acknowledged and dated by the employer or the supervising engineer (where service is refused, fix the fact of service with an EMS dispatch note + contents list + photos or notarised service). The review period runs from the employer's receipt of the complete final account documents (per Article 16 of the 'Interim Measures for Settlement of Construction Project Prices', Cai Jian [2004] No. 369).
- Checking/review: the checking letter must state the contested items, the amounts involved, the basis, the further documents required and the reply deadline, with proof of service retained; the consultant's review output is signed and sealed by the compiler and a first-class registered cost engineer, and signed or sealed by the contractor's representative, the supervising engineer and the employer's representative; the final account payment application (approval) form is made in four copies, filed by the contractor and held by the employer, the supervising engineer, the cost consultant and the contractor (GB/T 50500-2024 Annex F, Table F.5.1, notes 2 and 3).
- Confirmation: both parties sign and seal the final account documents, or confirm the absence of objections by exchanged letters; where a party refuses to sign, preserve the evidence of 'no objection after checking' (check records, meeting minutes) to claim liability for breach.
- Basis: Article 20 of MOHURD Order No. 16 requires cost engineers preparing settlement review documents to sign and affix their practice seal; Article 19 provides that final account documents confirmed by both parties' signatures serve as the basis of the project financial settlement, that neither party may entrust a cost consultant to re-review the effective final account documents without the other party's consent, that the employer shall pay the final account promptly, and that the documents shall be filed with the housing and urban-rural development authority of the place of the works at or above county level.
5. Interim payment of the contested parts Objections do not block the uncontested parts: where the review of the final account raises objections, the uncontested part is signed and sealed first and handled as a partial final account under clause 10.3.7 paragraph 1 (model text clause 14.2(3) correspondingly provides 'for the uncontested part the employer shall issue an interim final payment certificate and complete payment as in item (2) of this clause'); the contested part is settled by negotiation, failing which the Chapter 11 dispute resolution applies (dispute review, mediation, arbitration or litigation), and both parties continue to perform their contractual obligations during the dispute.
Applicability boundaries
- The 28/14/14/7-day figures above are model-text defaults and regulatory fallbacks; where the particular conditions agree otherwise, the agreement prevails; GB/T 50500-2024 is a recommended national standard whose clauses carry no fixed day counts - never present the model-text day counts as mandatory national-standard figures.
- This card covers the procedural time limits for 'confirming the settlement amount' and 'issuing payment certificates'; the conditions for 'deemed approval of the submitted price on failure to reply' in litigation (express contract agreement, served and complete final account documents, no reply within the period - three requirements) are in the companion card; the two must not be mixed.
- The former Ministry of Construction Order No. 107 'Measures for Administration of Pricing of Construction Contract Award and Subcontracting' was expressly repealed by Article 27 of MOHURD Order No. 16 (in force from 1 February 2014); when citing the regulatory basis, cite Article 18 and Article 19 of Order No. 16.
- Deductions and settlement handling where the works quality fails or is disputed, and the computation of the final account payment and the final closure payment, are covered in the companion cards on final account payment and final closure after the defects period.
Further reading
GB/T 50500-2024 'Standard for BOQ Pricing of Construction Works': clause 10.1.9, clauses 10.3.6-10.3.12, clauses 10.5.5/10.5.8/10.5.9, Chapter 11 (dispute resolution), Annex F Table F.5.1; GF-2017-0201 'Model Construction Contract' general conditions clause 14.1 [final account application], clause 14.2 [final account review], clause 14.3 [agreement on completion with outstanding items], clause 14.4 [final closure]; MOHURD Order No. 16 'Measures for Administration of Pricing of Construction Contract Award and Subcontracting' Article 18 (agreed periods and the 28-day fallback), Article 19 (effect and filing after confirmation), Article 20 (cost engineer signature and seal); Cai Jian [2004] No. 369 'Interim Measures for Settlement of Construction Project Prices' Article 16 (review period and its starting point). Local cost consultancy quality control rules also refine the start of the settlement period, for example DB42/T 823-2021 clause 8.1.8: the settlement period runs from the cost consultant's receipt of the complete final account documents.
Keywords
- final account
- 时限链
- 竣工付款证书
- 28 days
- 核对复核确认
- deemed acceptance / deemed approval
- 竣工结算申请单
- 结算签收凭证