Interim settlement by construction stage (stage settlement) in GB/T 50500-2024 (Section 10.2): node agreements, procedure flow, price calculation, and differences from the one-off final account under GB 50500-2013
GB/T 50500-2024 first establishes "interim settlement by construction stage" as a formal system (Section 10.2): settlement nodes (monthly/quarterly/annual/physical progress) and procedures are agreed in the contract (10.1.3); stage-settlement documents signed and confirmed by both parties merge into the final account without re-measurement or re-pricing (10.2.3), except the preliminaries and the main contractor's attendance and coordination provisions (provisionally paid, accurately re-measured at the final account). The 2013 edition had only "interim progress payments + a one-off final account after completion", and the standard itself laid down fixed periods (28-day verification / 28-day review / 7-day signature / 7+14-day payment, 11.3.2-11.4.4); the 2024 edition leaves all periods to contractual "agreed times" while retaining and extending the "deemed approval upon lapse of the response period" mechanism. Substantive change: settlement shifts from "determined once after completion" to "locked in stages as construction advances, summarized at the final account".
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB 50500-2013 建设工程工程量清单计价规范
- 法释〔2004〕14号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释第二十条
Topic Positioning
A systematic account of the "interim settlement by construction stage" (stage settlement) first formalized in GB/T 50500-2024 (Section 10.2): how settlement nodes are agreed, how procedures flow, how prices are calculated and paid, compared with GB 50500-2013's "one-off final account after completion" model. For understanding the evolution of the settlement system across the two editions and the contract management of works that implement stage settlement.
Core Conclusions
- Institutional positioning in the 2024 edition
- Term 2.0.35: construction payment settlement "includes interim settlement by construction stage, settlement on contract termination, the final account, and settlement of warranty obligations"; interim settlement by construction stage, also called interim settlement, "includes settlement carried out at monthly, quarterly, annual and physical-progress nodes"; "the final account is the summary of interim settlements by construction stage", composed hierarchically of unit-works final account, single-project final account, and construction-project final account.
- Term 2.0.34: interim settlement by construction stage means the parties' "activities of calculating, adjusting, confirming and paying the contract price for completed works at an interim-settlement-by-construction-stage node".
- Nodes and procedures (Section 10.2)
- Nodes, procedures and methods are agreed in the contract (10.1.3): "the employer and contractor shall, in accordance with the interim-settlement-by-construction-stage nodes, procedures and methods agreed in the contract, carry out the measurement and payment of the relevant interim settlement by construction stage"; nodes are selected from monthly, quarterly, annual and physical-progress nodes (2.0.35).
- Trigger and submission (10.2.8): after the works at an interim-settlement-by-construction-stage node are completed, the contractor shall submit the stage-settlement documents to the employer within the prescribed time; if the contractor fails to submit them, or after the employer's demand still fails to submit or gives no clear reply, the employer may compile the stage-settlement documents from the available records and request the contractor's confirmation — "if the contractor confirms without objection or gives no clear reply within the agreed time, the stage-settlement documents compiled by the employer shall be deemed approved by the contractor and may serve as the basis for handling the stage settlement and paying the stage-settlement amount"; it is also made clear that "stage acceptance during construction cannot replace taking-over (completion acceptance)".
- Certification locks the settlement (10.2.3): except as provided in 10.2.7, stage-settlement documents signed and confirmed by both parties "shall form part of the final account documents, and the final account shall not re-measure or re-price them"; excepted are the preliminaries and the main contractor's attendance and coordination provisions — these are provisionally paid contract amounts in stage settlement (they may be calculated proportionally) and are accurately re-measured and determined at the final account in accordance with the contract (10.2.3 commentary; 10.3.3).
Price calculation and payment (10.2.10) The stage-settlement amount is calculated as "the difference between the cumulative contract price for works completed up to the settlement node and the cumulative contract price already paid". The payment application shall include: (1) the cumulative completed stage-settlement amount (cumulative costs of completed billed (BOQ) items, preliminaries, and other items costs including provisional sums for works and services that could not be fully foreseen or described in detail, contract price adjustments, and VAT payable); (2) the cumulative paid stage-settlement amount; (3) amounts to be deducted in the current period (prepayment to be recovered, progress payments already made, amounts the employer is entitled to deduct); (4) the stage-settlement amount payable in the current period. Provisional sums shall be listed separately for works, services and contract price adjustments that could not be fully foreseen or described in detail.
Final account review and "deemed approval" (Section 10.3)
- Review (10.3.7): where there is no objection, the final account documents shall be signed and sealed within the agreed time; where there is objection, a partial final account shall first be processed for the undisputed part, and the disputed part shall be settled through negotiation, failing which it shall be handled under the dispute resolution methods in Chapter 11 of this standard.
- Deemed approval (10.3.8): if the employer fails to verify the final account or raise verification comments within the agreed time, the final account documents submitted by the contractor are deemed approved; 10.3.9: if the contractor neither confirms nor objects within the agreed time, the employer's verification comments are deemed approved; 10.3.16: if the employer neither verifies nor issues a payment certificate within the prescribed time after receiving the final account payment application, the application is deemed approved and the amount stated in the application shall be paid.
- Differences from GB 50500-2013
- The 2013 edition had no stage-settlement system, only "interim progress payments (advances in nature) + a one-off final account after completion", and the standard itself laid down fixed periods: the employer shall verify within 28 days of receiving the final account documents, and where supplementary information is required the contractor shall supplement, revise and resubmit within 28 days of receiving the verification comments (11.3.2); the employer shall re-verify within 28 days of the resubmission, and where there is no objection both parties shall sign the final account documents within 7 days (11.3.3); failure to verify or raise verification comments within 28 days deems the contractor's submitted final account documents approved (11.3.4, the commentary citing Article 20 of the Supreme People's Court Interpretation on Legal Issues in the Trial of Construction Contract Disputes, Fa Shi [2004] No. 14); failure to verify or issue a payment certificate within 7 days of receiving the payment application deems the application approved, and payment shall be made within 14 days after those 7 days in the amount stated in the application (11.4.4).
- The 2024 edition changed from a mandatory standard to a recommended standard (GB/T); all periods are left to the "agreed time" in the contract, with no fixed periods such as 28 days, but the "deemed approval upon lapse of the response period" mechanism is retained and extended (corresponding clauses exist at each stage: submission of stage settlement, verification of the final account, and verification of the payment application).
- Substantive difference: settlement moves from "determined once after completion" to "locked in stages as construction advances and summarized at the final account" — the measurement and pricing confirmed in stage settlement are not recalculated in the final account; only the preliminaries and the main contractor's attendance and coordination provisions are accurately re-measured at the final account.
Applicable Boundaries
- Applies to works for which interim settlement by construction stage is agreed; the nodes, procedures and periods follow the contract, and the standard's provisions serve as a reference where the contract cites them or is silent.
- The 2024 edition is a recommended standard (GB/T) and the 2013 edition a mandatory standard (GB); their levels of force differ, and both follow "the contract agreement prevails".
- Interim settlement by construction stage differs from progress payment: once certified, the stage settlement locks the basis for measurement and pricing and forms part of the final account, whereas progress payments are advances in nature.
- Stage acceptance during construction cannot replace taking-over (completion acceptance); the preliminaries and the main contractor's attendance and coordination provisions are provisional in stage settlement and must be accurately re-measured at the final account.
- This card summarizes standard provisions only and contains no specific project data or amounts.
Further Reading
- GB/T 50500-2024 China national pricing standard for BOQ (GB/T 50500): Chapter 2 terms 2.0.34 and 2.0.35; Chapter 10 "Construction payment settlement and payment" clauses 10.1.3, 10.2.3, 10.2.8, 10.2.10, 10.3.3, 10.3.7, 10.3.8, 10.3.9, 10.3.16.
- GB 50500-2013 Code for bill of quantities and valuation of construction works: Chapter 11 "Final account and payment" clauses 11.3.2, 11.3.3, 11.3.4, 11.4.4.
- Supreme People's Court Interpretation on Legal Issues in the Trial of Construction Contract Disputes (Fa Shi [2004] No. 14) Article 20 — the judicial basis for "failure to reply within the time limit is deemed approval" cited in the 2013 commentary; that interpretation has been replaced by Fa Shi [2020] No. 25, whose current counterpart is Article 21 (see the card referenced by this card).
Keywords
- interim settlement by construction stage
- final account
- GB/T 50500-2024
- GB 50500-2013
- 结算节点
- 期中结算
- settlement procedure
- deemed acceptance / deemed approval