Start point and time chain of final account handling: starts once taking-over is passed; deadlines for each link and the 28-day fallback

Final account handling starts once the whole contract works pass taking-over (completion acceptance) (GB/T 50500-2024 Clause 10.1.4): the contractor submits the final account documents within the agreed period; the employer checks and replies within the agreed period, and failure to reply in time is deemed acceptance; objections must be raised within the reply period and negotiated; if negotiation fails, a construction cost consultancy is engaged to carry out the review. Where the contract is silent on these periods, each is deemed to be 28 days (Ministry of Construction Order No. 107, Article 16); the review period runs from the employer's receipt of complete final account documents; the project completion summary final account is compiled within 15 days after the last single-project final account is reviewed and confirmed, and is reviewed within 30 days after submission to the employer.

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.35、10.1.4、10.1.5、10.3.1、10.3.4~10.3.10、10.3.16、10.3.17、10.5.8条及Ch. 11
  • 住建部令第16号《建筑工程施工发包与承包计价管理办法》第十八条(承继原建设部令第107号第十六条,原107号令已废止)
  • 财建〔2004〕369号《建设工程价款结算暂行办法》第十六条
  • DB42/T 823-2021 · Specification for Quality Control of Construction Cost Consulting (Hubei) 第8.1.8条
  • 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第二十一条
  • https://www.mohurd.gov.cn/gongkai/fdzdgknr/zqyj/art/2014/art_406_219911.html

Topic Positioning

Answers "when must the final account start being handled": the statutory start point, the complete time chain from submission to confirmation, the deadline for each link, and the 28-day fallback where the contract is silent.

Core Conclusions

  • Start point: after the whole contract works pass taking-over (completion acceptance), the employer and contractor shall handle the final account within the settlement period agreed in the contract (GB/T 50500-2024 Clause 10.1.4); the final account is compiled and checked on the basis of the contract and all interim settlement by construction stage documents signed and confirmed by both parties, and the interim settlement amounts serve as the basis for the final account (Clause 10.3.1).
  • Time chain (Ministry of Construction Order No. 107, Article 16): (1) the contractor submits the final account documents within the agreed period after taking-over — for a single project, the settlement report and complete settlement documents shall be submitted at the same time as the taking-over report; (2) the employer checks and replies within the agreed period, and failure to reply in time is deemed acceptance; (3) objections shall be raised within the reply period and negotiated; (4) if negotiation fails, a construction cost consultancy is engaged within the agreed period to carry out the review.
  • Fallback: where the contract does not provide for the above periods, each agreed period may be taken as 28 days; if there is still objection to the review opinion, mediation by the competent authority may be applied for within one month of receipt of the opinion, and failing mediation, arbitration or litigation may be pursued; once confirmed by both parties, the final account documents serve as the basis for the project final accounts.
  • Commencement of periods: the review period runs from the employer's receipt of complete final account documents (incomplete documents do not start it); the project completion summary final account is aggregated within 15 days after the last single-project final account is reviewed and confirmed, and is reviewed within 30 days after submission to the employer (Cai Jian [2004] No. 369, Article 16).

Applicable Boundaries

  • Applies to contractor-employer final account procedures; does not apply to interim settlement by construction stage or settlement on termination of contract — the start points differ.
  • Where the contract expressly agrees periods, the contract prevails; 28 days is only the presumption where there is no agreement; where local pricing measures contain more detailed provisions, those provisions apply.

Further Reading

  • GB/T 50500-2024, the China national pricing standard for BOQ, Clause 2.0.35 (definition and classification of construction payment settlement), Clause 10.1.4 (start point), Clause 10.3.1 (bases for compilation and checking)
  • Ministry of Construction Order No. 107 "Measures for the Administration of Pricing of Construction Works under Contracting", Article 16 (submission-reply-negotiation-review chain and the 28-day fallback)
  • GB/T 50326-2017 "Code for Construction Project Management", Clause 18.3.3 (contents of the basis for the final account)
  • Cai Jian [2004] No. 369 "Interim Measures for Settlement of Construction Project Payments", Article 16 (deemed approval and review periods)