Regulation on Quality Management of Construction Works — prohibited acts of employer and contractor: fragmented awarding, contract transfer, illegal subcontracting, arbitrary compression of reasonable duration (arts. 7/10/25/78)
Per the Regulation (2019 revision, Decree No. 714): the employer must not fragment a project for awarding (art. 7), must not force bidders below cost, arbitrarily compress the reasonable duration, or expressly/impliedly direct designers or contractors to violate mandatory standards and lower quality (art. 10); contractors must work within their qualification grade, may not exceed it or use another's name, may not lend their name, and must not transfer or illegally subcontract (art. 25). Art. 78 gives the statutory definitions of fragmented awarding, illegal subcontracting (four situations) and contract transfer — the benchmark for administrative determination and judicial decisions.
Applicable Codes
- 《建设工程质量管理条例》(国务院令第714号,2019年修订)第十六条
- 《房屋建筑和市政基础设施工程竣工验收规定》(建质〔2013〕171号)第四条
Topic Positioning
Prohibited acts of the employer and contractor regarding awarding, subcontracting and duration under the Regulation on Quality Management of Construction Works (Decree No. 714, 2019 revision): the prohibitions of arts. 7, 10 and 25, and the statutory definitions of fragmented awarding, illegal subcontracting and contract transfer in art. 78.
Core Conclusions
I. Acts the employer must not commit (arts. 7, 10):
- Art. 7: the employer shall award works to units with the corresponding qualification grade. It must not fragment a construction project for awarding.
- Art. 10: the awarding unit must not force contractors to bid below cost, and must not arbitrarily compress the reasonable duration. The employer must not expressly or impliedly direct the design or construction unit to violate mandatory construction standards and lower quality.
II. Acts the contractor must not commit (art. 25):
- It shall obtain the corresponding qualification certificate and undertake works within the scope permitted by its grade.
- It is forbidden to undertake works beyond its qualification scope or in the name of another contractor (borrowing qualifications).
- It is forbidden to allow other units or individuals to undertake works in its own name (lending qualifications/affiliation).
- It must not transfer or illegally subcontract works.
III. Statutory definitions (art. 78, the benchmark for administrative and judicial determination):
- Fragmented awarding: the act of the employer dividing a project that should be completed by one contractor into parts awarded to different contractors.
- Illegal subcontracting means: (1) the general contractor subcontracting to units lacking corresponding qualifications; (2) the contractor assigning part of the works to other units without contractual agreement and without employer recognition; (3) the construction general contractor subcontracting the construction of the main structure; (4) a subcontractor re-subcontracting its works.
- Contract transfer: the contractor, after taking the project, failing to perform its contractual duties and transferring the whole project to others, or splitting the whole project and transferring it to other units in the name of subcontracting.
Applicable Boundaries
- Based on the 2019 revision (Decree No. 714); mind the version history (previously 2017) and check clause numbers against the current text.
- This card covers only the prohibitions and the art. 78 definitions; penalties (from art. 54 on) are out of scope.
- Determination of "below cost" and quantification of "reasonable duration" need other bases (e.g. GB 50500-2013 cl. 9.11.1 acceleration ratios, duration norms); the Regulation sets only the red lines.
- Practical identification of transfer/illegal subcontracting/fragmented awarding also draws on the Construction Law, Bidding Law and rules such as MOHURD Order No. 124 on subcontracting management.
Further Reading
- Original text: Regulation on Quality Management of Construction Works (2019 revision, Decree No. 714), arts. 7, 10, 25 and 78; penalties from art. 54 (e.g. fines of 0.5%-1% of contract price for fragmented awarding/transfer/illegal subcontracting — verify clause numbers separately).
- Superior law: Construction Law of the PRC (2019 amendment); companion rule: MOC Order No. 124 Measures for Administration of Subcontracting of Housing and Municipal Works.
Keywords
- Regulation on Quality Management of Construction Projects (State Council Decree No. 279)
- taking-over (completion acceptance)
- 验收条件
- 建设单位
- 国务院令第714号
- 交付使用
- 质量合格文件
- 工程保修书