Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Works put into use before completion acceptance: payment, quality liability and warranty rules (the employer's unauthorized use deemed acceptance of quality)

The employer's unauthorized use of un-accepted works equals deemed acceptance of quality (presumed qualification): the project price remains payable, with the date of transfer of possession serving as the completion date and the payment due date (interest at the 1-year LPR absent an agreed rate); quality risk passes to the employer except for foundations and the main structure (for which the contractor remains liable within the reasonable service life), and only for the parts actually used; warranty duties are not discharged - minimum warranty periods per Article 40 of the Regulations on Quality Management of Construction Works (waterproofing 5 years; heating and cooling 2 heating/cooling seasons; electrical wiring, water supply and drainage piping, equipment installation and finishing 2 years; foundations and main structure, the reasonable design life); the employer additionally bears an administrative fine of 2%-4% of the contract price (Article 58).

Applicable Codes

  • 法释〔2020〕25号 第9条、第14条、第27条
  • 《建筑法》(2019修正)第61条
  • 《建设工程质量管理条例》(2019修订)第40条、第58条
  • 《建设工程质量保证金管理办法》(建质〔2017〕138号)第8条

Topic Positioning

Resolves the legal consequences of 'works put into use by the employer before completion acceptance': whether the project price is payable, how quality liability is allocated, warranty periods and administrative liability. General adjudication rules for construction contract disputes (Fa Shi [2020] No. 25 plus the Construction Law plus the Regulations on Quality Management of Construction Works).

Core Conclusions

  1. Underlying prohibition: Construction Law (2019 amendment), Article 61(2): 'A construction project may be delivered for use only after passing completion acceptance; a project that has not been accepted, or has failed acceptance, may not be delivered for use.' The employer's unauthorized delivery into use is itself unlawful.
  2. The project price is payable: Fa Shi [2020] No. 25, Article 9(3): where the works have not passed completion acceptance but the employer uses them without authorization, the date of transfer of possession of the works is the completion date - once fixed, the contractual payment conditions are satisfied and the employer may not refuse payment on the ground of 'no acceptance'. Article 27 of the same interpretation: where the payment time is not agreed or unclear and the works have been actually delivered, the delivery date is the payment due date, with overdue interest running from that date (absent an agreed rate, at the 1-year LPR for the corresponding period).
  3. Quality liability shifts: Article 14 - where the employer uses the works without authorization and then claims rights on the ground that the quality of the parts used does not conform to the agreement, the people's court will not support the claim; but the contractor remains civilly liable within the reasonable service life of the works for the quality of the foundation works and the main structure - a mandatory baseline. 'Deemed acceptance' extends only to the parts actually used; the right to object to the quality of unused parts is unaffected. Procedurally, after unauthorized use the employer's application for quality expert determination of the works is generally not granted; warranty claims require the employer to prove that it notified the contractor for repair within the warranty period and the contractor refused.
  4. Warranty duties not discharged: Regulations on Quality Management of Construction Works (2019 revision), Article 40, minimum warranty periods under normal use: foundation works and main structures of infrastructure projects and buildings - the reasonable service life specified in the design documents; roof waterproofing works and waterproofing of bathrooms, rooms and exterior walls requiring waterproofing - 5 years; heating and cooling systems - 2 heating periods and 2 cooling periods; electrical wiring, water supply and drainage piping, equipment installation and finishing works - 2 years; other items as agreed between employer and contractor. The warranty period runs from passing completion acceptance; with unauthorized use, the transfer-of-possession date is presumed to be the completion date, and judicial practice usually runs the warranty period from the transfer of possession. The employer may claim deduction of the quality retention from unpaid project payments.
  5. Administrative liability (employer): Article 58 of the Regulations - where the employer fails to organize completion acceptance and delivers the works for use without authorization (or delivers despite failed acceptance, or accepts failed works as qualified), it is ordered to correct and fined 2% to 4% of the project contract price; where losses are caused, it bears compensation liability according to law.
  6. Defects-liability period: where completion acceptance cannot proceed on schedule for reasons attributable to the employer, the defects-liability period starts automatically 90 days after the contractor submits the completion acceptance report, and the retention return period runs accordingly (Measures for the Administration of Construction Quality Retention Money, Jian Zhi [2017] No. 138, Article 8).

Applicable Boundaries

Applies where the employer knowingly uses un-accepted works without authorization (including handover to unit owners for fit-out and occupancy, or transfer to third parties to continue the works). 'Deemed acceptance' presupposes unauthorized use by the employer: where both parties agree to early use, or the contractor's refusal to cooperate in acceptance or to hand over documents prevents acceptance, the deeming rule does not apply and liability is allocated by fault. Deemed acceptance covers only the parts actually used; liability for foundations and the main structure remains with the contractor within the reasonable service life, subject to proof by the employer. Individual outcomes also depend on the contract terms and the determination of the scope of unauthorized use.

Further Reading

Fa Shi [2020] No. 25, SPC Interpretation (I) on Construction Contract Disputes: Article 9 (completion date/transfer of possession), Article 14 (limits on quality objections after unauthorized use), Article 27 (payment time and overdue interest); Construction Law (2019 amendment), Article 61; Regulations on Quality Management of Construction Works (2019 revision), Article 40 (minimum warranty periods) and Article 58 (administrative fine of 2%-4%); Measures for the Administration of Construction Quality Retention Money (Jian Zhi [2017] No. 138), Article 8 (90-day defects-liability period). Settlement interface: GB/T 50500-2024, Clause 10.3.14 (quality disputes over works already in use go to warranty; settlement proceeds as usual).

Keywords

Cited By