Whether the contractor on incomplete works (the completed parts being of acceptable quality) can claim the statutory priority right of payment for the construction price: conditions, the boundaries of the scope covered, the 18-month period, and a positive-versus-negative scenario comparison
Yes. Fa Shi [2020] No. 25, Article 39: 'Where the quality of construction works not completed is acceptable, and the contractor requests priority of payment of the price of the works it built out of the proceeds of the discount sale or auction of the part of the works it built, the people's court shall uphold the request.' The threshold is 'acceptable quality', not completion acceptance; but the right reaches only the part of the works built by the contractor; the claimant must be the contractor that concluded the construction contract with the employer (Article 35); the subject matter is limited to the construction price (excluding interest, liquidated damages, compensation for loss, and losses from stoppage and idle resources, Article 40(2) and Fa Shi [2026] No. 12, Article 17(2)); and it must be exercised within at most 18 months from the date the employer ought to pay the construction price (Article 41).
Applicable Codes
- 《中华人民共和国民法典》第八百零七条
- 《中华人民共和国民法典》第七百九十三条
- 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第十四条、第三十五条、第三十六条、第三十七条、第三十八条、第三十九条、第四十条、第四十一条
- 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第十七条、第十八条、第二十条、第二十一条、第二十三条
- GB 50300-2013 · Unified Standard for Constructional Quality Acceptance of Building Engineering 第5.0.3条
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第10.3.14条
Topic Positioning
Whether, and within what scope, the contractor on incomplete works (including works stopped after completing part and suspended or shelved works) enjoys the statutory priority right of payment for the construction price in respect of the completed parts; with a positive-versus-negative scenario comparison, the legal bases ranked by level of provision, and pointers on proving the acceptable-quality threshold and on the procedural time-limit risk.
Core Conclusions
Conclusion: yes. Per the SPC Interpretation (I) on Construction Contract Disputes (Fa Shi [2020] No. 25), Article 39, as enacted: 'Where the quality of construction works not completed is acceptable, and the contractor requests priority of payment of the price of the works it built out of the proceeds of the discount sale or auction of the part of the works it built, the people's court shall uphold the request.' Core reason: the provision sets 'acceptable quality', not 'completion acceptance', as the threshold for the priority, so incompleteness is not itself a ground of denial.
Basis of the right: Civil Code Article 807 - 'Where the employer fails to pay the price as agreed, the contractor may demand that the employer pay within a reasonable period. If the employer still fails to pay when the period expires, then, unless the nature of the construction works makes discount sale or auction inappropriate, the contractor may agree with the employer on converting the works into value at a discount, or may request the people's court to auction the works according to law. The price of the construction works has priority of payment out of the proceeds of the discount sale or auction of the works.' Ranking: Fa Shi [2020] No. 25, Article 36 - 'the priority right of payment for the construction price that the contractor enjoys under Civil Code Article 807 prevails over security interests in the works (mortgages) and other claims'. Standing: Article 35 confines it to 'the contractor that concluded the construction contract with the employer'.
Four hard boundaries (failing any one, the claim is dismissed): (1) it reaches only 'the part of the works built by the contractor', not unbuilt parts or parts built by others; (2) the claimant must be the contractor that concluded the construction contract with the employer (subcontractors, transferees of a re-let contract and actual constructors lack standing to claim directly against the employer); (3) the subject matter is limited to the construction price; (4) it must be exercised within at most 18 months.
Positive versus negative scenario comparison
| Scenario | Outcome | Basis |
|---|---|---|
| Works incomplete; the completed parts of acceptable quality | Yes; priority out of the discount-sale or auction proceeds of 'the part built' | Fa Shi [2020] No. 25, Article 39 |
| Works completed and of acceptable quality | Yes; priority out of the discount-sale or auction proceeds of the works | Fa Shi [2020] No. 25, Article 38 |
| Works incomplete and not accepted; the employer uses them prematurely | Yes (the parts used are deemed of acceptable quality, only as to the parts actually used; liability for the foundation and principal structure is not released) | Fa Shi [2020] No. 25, Articles 14 and 39 |
| The construction contract is void but the completed parts are of acceptable quality | Yes (validity of the contract is not a requirement of the priority; where the contract is void but acceptance passes, converted-value compensation is made by reference to the contract) | Civil Code Articles 793(1) and 807; Fa Shi [2020] No. 25, Article 35 |
| Fitting-out works meet the conditions for discount sale or auction | Yes; priority only over that fitting-out work | Fa Shi [2020] No. 25, Article 37 |
| The works are damaged, destroyed or expropriated | Yes; priority out of the insurance proceeds, damages and compensation (subrogation in value) | Fa Shi [2026] No. 12, Article 20 |
| Concurrence with mortgagees and other creditors | The priority right prevails over mortgages and other claims | Fa Shi [2020] No. 25, Article 36 |
| The completed parts are of unacceptable quality and remain so after repair | No (no right to converted-value compensation by reference to the contract, still less a priority) | Civil Code Article 793(2), item 2; the converse of Article 39 |
| The claim extends to unbuilt parts or parts built by others | No (beyond 'the part of the works built by the contractor') | Fa Shi [2020] No. 25, Article 39 |
| A subcontractor, re-let transferee or actual constructor claiming directly against the employer | No (lack of standing) | Fa Shi [2020] No. 25, Article 35 |
| The nature of the construction works makes discount sale or auction inappropriate | No | Civil Code Article 807, proviso |
| Not exercised within 18 months | No (peremptory period) | Fa Shi [2020] No. 25, Article 41 |
| Interest on late payment, liquidated damages, compensation for loss | No priority (may be claimed separately as ordinary claims) | Fa Shi [2020] No. 25, Article 40(2) |
| Losses from stoppage and idle resources caused by the employer | No priority | Fa Shi [2026] No. 12, Article 17(2) |
| The action does not expressly claim confirmation of the priority, or the operative part of the judgment does not state the amount and the corresponding works | Cannot be confirmed (procedural failure) | Fa Shi [2026] No. 12, Article 17(1) |
| Relying only on a discount-sale agreement that fails the four requirements | Not upheld | Fa Shi [2026] No. 12, Article 18 |
Scope of payment and procedure: Fa Shi [2020] No. 25, Article 40(1): 'the scope of the contractor's priority right of payment for the construction price is determined under the provisions of the relevant administrative department of the State Council on the scope of construction prices'; Article 40(2): 'where the contractor claims priority of payment for interest on late payment of the construction price, liquidated damages or compensation for loss, the people's court will not uphold it'. Fa Shi [2026] No. 12, Article 17(1), requires the court to 'ascertain the amount of the construction price covered by the priority right and the corresponding works, and state them clearly in the operative part of the judgment' - so the claim must specify the 'amount + the corresponding works'. Article 17(2): 'where the contractor claims the priority right of payment for losses from stoppage and idle resources caused by the employer, the people's court will not uphold it'.
The period: Fa Shi [2020] No. 25, Article 41: 'the contractor shall exercise the priority right of payment for the construction price within a reasonable period, not exceeding 18 months at the longest, from the date the employer ought to pay the construction price.' Refinements of the starting point (Fa Shi [2026] No. 12, Article 21): where the payment date agreed in the contract is varied by agreement for objective reasons such as an extension of time, the period runs from the varied date; where the contract does not stipulate, or unclearly stipulates, the payment date and a settlement agreement fixes it, the period runs from that date.
The four requirements of the discount-agreement path (Fa Shi [2026] No. 12, Article 18): (1) the quality of the works built by the contractor is acceptable; (2) the construction works are susceptible of discount sale; (3) the employer is late in paying the construction price and, after demand by the contractor, still fails to pay within a reasonable period; (4) the discounted amount is substantially equivalent to the actual value of the construction works at the time of the discount.
Old-versus-new boundary of application: Fa Shi [2026] No. 12, Article 23: 'This Interpretation takes effect on 30 June 2026. For construction contract dispute cases newly accepted by the people's courts after this Interpretation takes effect, this Interpretation applies. After this Interpretation takes effect, where judicial interpretations previously issued by the Supreme People's Court are inconsistent with it, this Interpretation prevails.' That is, first-instance cases newly accepted after 30 June 2026 apply this Interpretation; cases accepted earlier still follow the approach of Fa Shi [2020] No. 25.
Practical pointers: (1) Points of proof - proof of acceptable quality centres on the lot-by-lot acceptance records; under GB 50300-2013, Unified Standard for Constructional Quality Acceptance of Building Engineering, Clause 5.0.3, acceptance of a division of the works as passed requires that 'the sub-divisions it contains all pass acceptance; the quality-control documentation is complete; the sampling test results concerning safety, energy saving, environmental protection and the main functional uses comply with the corresponding provisions; and the visual quality meets the requirements'; the completed parts of suspended or shelved works should likewise undergo interim acceptance on this basis and keep the records. (2) Quality disputes - under GB/T 50500-2024, China national pricing standard for BOQ, Clause 10.3.14, for quality disputes over completed-but-unaccepted works not yet put into use, and over stopped and shelved works, the parties may jointly appoint, for the disputed part, a qualified testing and appraisal institution to test, proceed according to the test results or the decision of the quality-supervision authority, and then complete the final account; the parts as to which there is no objection are settled as agreed in the contract. (3) Risk points - the peremptory period is not interrupted by demands or negotiation, and the right is extinguished when the 18 months expire; therefore plead, at filing, an express claim for confirmation (amount + corresponding works), and claim stoppage and idle-resource losses and interest separately as ordinary claims, instead of mixing them into the priority claim and so affecting the whole claim.
Boundaries of Application
- 'Acceptable quality' is judged on the acceptance or test conclusions for the contractor's own completed parts, and cannot be denied on the ground that the whole works have not passed completion acceptance; conversely, where the completed parts are unacceptable and remain unacceptable after repair, there is no right to payment, still less a priority.
- Priority of payment covers only the proceeds of the discount sale or auction of 'the part of the works built by the contractor'; unbuilt parts and parts built by others do not enter the computation base; the amount of the price covered by the priority and its corresponding works must be specified when claiming.
- The holder of the right is confined to the contractor that concluded the construction contract with the employer; subcontractors, re-let transferees and actual constructors cannot claim this priority against the employer directly in their own names.
- Where the nature of the construction works makes discount sale or auction inappropriate (works touching the public interest, works whose transfer the law prohibits, and the like), the priority path fails.
- These rules resolve 'standing and scope'; they do not resolve disputes over the concrete amount of the price or over the settlement basis; the amount is still determined by the contract, the settlement documents or the conclusions of expert assessment.
- This card takes Fa Shi [2020] No. 25, applied to cases accepted before 30 June 2026, as its main line; first-instance cases newly accepted after 30 June 2026 apply Fa Shi [2026] No. 12, which prevails where inconsistent.
Further Reading
- PRC Civil Code, Article 807 (basis of the priority right), Article 793 (converted-value compensation on the void contract and treatment of unacceptable quality).
- Fa Shi [2020] No. 25, Article 35 (standing), Article 36 (ranking), Article 37 (fitting-out works), Article 38 (works completed, acceptable quality), Article 39 (works incomplete, acceptable quality), Article 40 (scope of payment), Article 41 (the 18-month period).
- Fa Shi [2026] No. 12, Article 17 (stating the amount and corresponding works in the operative part of the judgment; no priority for stoppage and idle-resource losses), Article 18 (the four requirements of the discount agreement), Article 20 (subrogation into insurance proceeds, damages and compensation), Article 21 (commencement of the period), Article 23 (effective date and the application threshold for newly accepted cases).
- GB 50300-2013, Unified Standard for Constructional Quality Acceptance of Building Engineering, Clause 5.0.3 (conditions for acceptance of a division of the works; for proving the quality of the completed parts).
- GB/T 50500-2024, China national pricing standard for BOQ, Clause 10.3.14 (testing, appraisal and settlement of quality disputes over stopped and shelved works).