Priority right of payment for construction project prices: entitled parties, exercise procedure, scope of coverage and the 18-month exercise period

Under Civil Code Article 807 and Fa Shi [2020] No. 25, Articles 35-41: the priority right is exercised by the contractor that concluded the construction contract with the employer (decoration contractors and contractors of uncompleted but quality-qualified works may also qualify when conditions are met), premised on the works being quality-qualified; the exercise path is demand, then overdue non-payment, then agreed discount of the works or petition to the court for auction according to law; the coverage is limited to the project price (labour cost, materials cost, plant and small tools cost, overheads (company and site), profit, statutory levies and fees, taxes and duties (VAT under the current standard), etc.), while interest for late payment, liquidated damages and damages rank as ordinary claims only; the right must be exercised within a reasonable period not exceeding 18 months from the date the price becomes payable - a peremptory period; it takes priority over mortgages and other claims, except the delivery claim of commodity-housing consumers who have paid all or most of the price.

Applicable Codes

  • 《中华人民共和国民法典》第八百零七条
  • 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第二十七条、第三十五至四十一条
  • 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第二十一条
  • 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第二十三条
  • 法释〔2023〕1号《最高人民法院关于商品房消费者权利保护问题的批复》

Topic Positioning

A complete map of the priority right of payment for construction project prices - entitled parties, exercise procedure, scope of coverage and time limit (Civil Code Article 807 plus SPC Interpretation (I) on Construction Contract Disputes, Articles 35-41) - for quickly locating provisions when a contractor asserts the priority or an employer defends against it.

Core Conclusions

  1. Basis of the claim and procedure (Civil Code, Article 807, original text): 'Where the employer fails to pay the price as agreed, the contractor may demand payment within a reasonable period. If the employer still fails to pay within that period, the contractor may, unless the nature of the works makes discount or auction inappropriate, agree with the employer to discount the works, or petition the people's court to auction the works according to law. The price of the construction works enjoys priority of payment out of the proceeds of the discount or auction.' Four requirements: (i) the employer failed to pay as agreed; (ii) the contractor has made a demand and allowed a reasonable period (demand is a procedural requirement); (iii) the works are not by nature unsuitable for discount or auction; (iv) satisfaction is achieved by agreed discount or petition for court-ordered auction.
  2. Entitled parties: the contractor that concluded the construction contract with the employer (Interpretation (I), Article 35); contractors of decoration works may enjoy priority over the price of the decoration works where they are capable of discount or auction (Article 37); contractors of uncompleted but quality-qualified works may exercise it for the part they built (Article 39); actual constructors do not in principle hold it directly and must proceed through the contractor or by subrogation.
  3. Precondition: the construction works are quality-qualified (Article 38); taking-over (completion acceptance) is not required, and the validity of the contract does not matter.
  4. Scope: determined per the pricing rules of the State Council's construction administration department (covering labour cost, materials cost, plant and small tools cost, overheads (company and site), profit, statutory levies and fees, taxes and duties (VAT under the current standard), etc.); interest on late payment of the project price, liquidated damages and damages do not enjoy priority and rank as ordinary claims (Article 40).
  5. Period: the right must be exercised within a reasonable period not exceeding 18 months from the date the project price becomes payable (Article 41); it is a peremptory period (fixed period), to which suspension, interruption or extension of the limitation period does not apply, and the right extinguishes on expiry; where the payable date is not agreed or unclear, refer to Article 27: for delivered works, the delivery date; for undelivered works, the date of submitting the final account documents; where neither delivered nor settled, the date of filing suit.
  6. Ranking: priority over mortgages and other claims (Article 36); exception 1: the delivery claim of commodity-housing consumers who have paid all or most of the price prevails over the priority right of payment (Fa Shi [2023] No. 1); exception 2: works unsuitable for discount or auction (public facilities, social housing, etc.) may not be discounted or auctioned for satisfaction (proviso to Article 807), but the price claim itself survives.

Applicable Boundaries

Applies to the civil handling of construction contract disputes. Contract invalidity usually does not defeat the priority right for works that passed acceptance (mainstream judicial view); whether contractor advance financing (deferred payment) and profit fall within the covered scope varies by locality. Once the peremptory period lapses the right extinguishes - demand payment from the employer in writing early and expressly claim the priority in the claims or enforcement proceedings; suing for the price without claiming priority may be found not to have exercised it. The consumer-priority rule applies only to purchaser-consumers who have paid all or most of the price.

Further Reading

Civil Code, Article 807 (demand, agreed discount or court auction, priority of payment) and Article 808 (matters not covered follow the provisions on work contracts); SPC Interpretation (I) on Construction Contract Disputes, Fa Shi [2020] No. 25, Articles 27 and 35-41; SPC Reply on the Protection of Commodity-Housing Consumers' Rights, Fa Shi [2023] No. 1; MOHURD, Measures for the Administration of Pricing in Contracting and Subcontracting of Building Works, on the composition of the project price.

Keywords

  • 建设工程价款优先受偿权
  • 十八个月
  • 除斥期间
  • 起算时点
  • 应付款之日
  • 工期顺延
  • 结算协议
  • 法释〔2026〕12号