Interest, liquidated damages and damages for late payment of the project price do not enjoy the contractor's priority right of payment out of the works - the scope locked by the composition of the project price, separating principal and interest in blended settlements, and 'agreement cannot expand the statutory priority scope'
Not included. The scope of the priority right is confined to the project price itself: Article 40(1) of Fa Shi [2020] No. 25 provides that the scope 'is determined under the provisions of the relevant administrative department of the State Council on the scope of construction project prices', and paragraph 2 states expressly that 'where the contractor claims priority for interest, liquidated damages or damages arising from late payment of the construction project price, the people's court will not support the claim'. The interest claim itself stands and may be sued for (the rate follows Article 26 of the same interpretation, the start date Article 27), but only as an ordinary claim, without priority over mortgages or other claims; Article 17 of the 2026 Interpretation (II) (Fa Shi [2026] No. 12) further requires the court to ascertain and 'state in the operative part of the judgment' the amount of project price enjoying the priority right and the corresponding works, and paragraph 2 restates that suspension and idle-resource losses are not supported.
Applicable Codes
- 《中华人民共和国民法典》第八百零七条
- 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第二十六条、第二十七条、第三十五条、第三十六条、第三十八条、第四十条、第四十一条
- 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第十七条、第二十条、第二十三条
- 《保障中小企业款项支付条例》(2025修订,国务院令第802号)第九条、第十条、第十七条
- 建标〔2013〕44号《建筑安装工程费用项目组成》
- 苏高法〔2018〕《江苏省高级人民法院关于审理建设工程施工合同纠纷案件若干问题的解答》第四部分第14~20条
Topic Positioning
This card answers one of the scope questions on the contractor's priority right of payment out of the construction project price: whether interest generated by the employer's late payment of the project price (and liquidated damages, damages and similar sums) enters the priority scope. It involves Article 807 of the Civil Code, Article 40 of Fa Shi [2020] No. 25 (the core provision), Articles 17, 20 and 23 of Fa Shi [2026] No. 12, and the supporting rules on the interest rate and the start date (Articles 26 and 27 of the same interpretation).
Core Conclusions
1. Conclusion and the statutory text
Not included. The subject of the priority is locked to the project price; interest is outside it.
- Article 807 of the Civil Code: 'Where the employer fails to pay the price as agreed, the contractor may urge the employer to pay the price within a reasonable period. If the employer still fails to pay within that period, the contractor may, unless the project is by its nature unsuitable for discounting or auction, agree with the employer to discount the project, or may request the people's court to auction the project in accordance with law. The price of the project enjoys priority of payment out of the proceeds of the discounting or auction of the project.' - what is protected is 'the price of the construction project', not 'every monetary claim'.
- Article 40(1) of Fa Shi [2020] No. 25: 'The scope of the contractor's priority right of payment of the construction project price is determined under the provisions of the relevant administrative department of the State Council on the scope of construction project prices.' Paragraph 2: 'Where the contractor claims priority for interest, liquidated damages or damages arising from late payment of the construction project price, the people's court will not support the claim.'
2. The three-step reasoning (why interest is excluded)
- Character under the governing law: the object of the priority is 'the price of the construction project' payable out of the proceeds of discounting or auctioning the project; it is a statutory priority whose scope is fixed by law and judicial interpretation, not creatable at will by the parties.
- The locked definition: the scope depends on the provisions of the relevant administrative department of the State Council on the composition of the construction project price (the cost items of construction and installation works) - that is, the pricing elements invested in forming the physical works: labour cost, material cost, plant and small tools cost, overheads, profit, statutory levies and fees, taxes and duties and the like. Interest is the price of the employer's occupation of funds through late payment, not a cost element of forming the physical works, and so falls outside that definition.
- Express exclusion by interpretation: paragraph 2 lists interest, liquidated damages and damages, and the word 'etc.' extends it to similar breach losses such as funds-occupation charges, late-payment penalties and late-payment losses (suspension and idle-resource losses are restated as unsupported by Article 17(2) of Fa Shi [2026] No. 12).
3. 'No priority as to scope' does not mean 'no claim' (two layers kept apart)
- Claim layer: interest can be claimed and adjudged, and sued for together with the project price; it simply does not enter the priority distribution of the discount or auction proceeds and participates as an ordinary claim (the ranking rule is Article 36 of Fa Shi [2020] No. 25: the priority right prevails over mortgages and other claims - conversely, interest does not enjoy that rank).
- Computation layer: where the interest rate is agreed, the agreement governs; absent agreement, interest runs at the rate for loans of the same type and period, or at the loan prime rate for the corresponding period (Article 26); interest runs from the date the project price falls due; where the payment time is not agreed or is unclear, in order: the date of actual delivery of the works; failing delivery, the date of submitting the final account documents; where neither delivered nor settled, the date of the party's suit (Article 27).
- Operative-part layer: Article 17(1) of Fa Shi [2026] No. 12: 'Where the contractor requests confirmation of the priority right of payment of the construction project price, the people's court shall ascertain the amount of the project price enjoying the priority right and the corresponding works, and state them in the operative part of the judgment.' Principal and interest must therefore be itemised in the suit; a blanket claim that 'all arrears (including interest) enjoy priority' will not be supported beyond the principal.
4. Situation table (situation x conclusion x basis)
| Situation | Priority or not | Textual basis |
|---|---|---|
| Principal of the unpaid project price (the part confirmed as project price under the composition of the project price) | Priority | Fa Shi [2020] No. 25 Article 40(1) |
| Interest on late payment of the project price (agreed or statutory) | No priority; ordinary claim | Fa Shi [2020] No. 25 Article 40(2) |
| Liquidated damages for late payment | No priority | Same (paragraph 2 listing) |
| Damages (late-payment loss, funds-occupation charges, etc.) | No priority | Same (the word 'etc.') |
| Suspension and idle-resource losses caused by the employer (idle labour, plant standing idle, material losses, etc.) | No priority | Fa Shi [2026] No. 12 Article 17(2) |
| A settlement agreement or reconciliation confirming 'principal plus interest' as one 'unpaid project price' without separation | Only the principal part that is project price enjoys priority; the court must ascertain the amount and state it in the operative part | Fa Shi [2026] No. 12 Article 17(1) + Fa Shi [2020] No. 25 Article 40(2) |
| Contract terms that 'interest is counted into the project price' or 'arrears are treated as project price' | Agreement cannot expand the statutory priority scope; still no priority | Fa Shi [2020] No. 25 Article 40(1) and (2) (statutory priority, statutory scope) |
| Interest on advance financing and occupation charges on advanced funds | No priority (same category as interest) | Fa Shi [2020] No. 25 Article 40(2) |
| Insurance proceeds, damages or compensation after the project is damaged, destroyed or expropriated | Priority (subrogation over the proceeds) | Fa Shi [2026] No. 12 Article 20: 'Where a construction project is damaged, destroyed or expropriated, the contractor's claim to priority over the insurance proceeds, damages or compensation obtained is supported by the people's court.' |
Local judicial practice points the same way (Jiangsu Higher People's Court, Su Gao Fa [2018] Answers): Article 17, 'a contractor's claim to include project price interest in the scope of the priority right is not supported'; Article 15, a void contract does not defeat the priority right; Article 16, an actual constructor may claim within the employer's unpaid project price where the main contractor or the transferor fails to claim or is dilatory; Article 18, suit or arbitration is a valid mode of exercise, and 'a contractor asserting the priority right by letter is not recognised as effective exercise'; Article 19, voluntary waiver is in principle effective, but is not effective against third parties such as actual constructors whose interests it harms; Article 20, on assignment of the project price claim the priority right passes with it, and whether the assignee actually holds it remains subject to substantive review.
5. Practical points
- Drafting the claims: state separately 'project price principal X yuan (claim to priority out of the discount or auction proceeds of the works)' and 'interest / liquidated damages / loss Y yuan (claim for payment only, no priority claimed)', and apply under Article 17(1) for the court to ascertain the priority amount and the corresponding works.
- Evidence: prove the principal and its price make-up with settlement documents, site instruction records and measurement and payment records; for interest, fix the due date (Article 27) and the rate (Article 26, contractual agreement).
- Procedural time-limit risk: the priority right must be exercised within a reasonable period, not exceeding 18 months at most, running from the date the project price falls due (Article 41 of Fa Shi [2020] No. 25), a peremptory period; suing for the price without claiming priority, or asserting it only by letter, risks being held not to have exercised it effectively (local practice above).
- A parallel track: for overdue interest on payments to SMEs by state organs, public institutions and large enterprises, see Article 17 of the Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Decree No. 802): an agreed rate may not be below the 1-year loan prime rate at the time of conclusion, and absent agreement 0.05% per day - that rate belongs to the payment-compliance track of 'how much interest, when', and does not change the ranking conclusion that interest is not priority.
Scope and Limits
- Cut-off in time: Article 23 of Fa Shi [2026] No. 12: 'This Interpretation takes effect on 30 June 2026 and applies to first-instance construction contract dispute cases newly accepted by the people's courts after that date. Where earlier SPC interpretations conflict with this Interpretation, this Interpretation prevails.' First-instance cases newly accepted after 30 June 2026 are governed by Article 17 (ascertainment in the operative part; exclusion of suspension losses); earlier accepted cases are handled under Civil Code Article 807 + Article 40 of Fa Shi [2020] No. 25, and the conclusion that interest is not priority is the same under every version.
- Parties and preconditions: the claimant must be the contractor who concluded the construction contract with the employer (Article 35 of Fa Shi [2020] No. 25), and the quality of the works must be acceptable (Article 38; passing completion acceptance is not a condition); actual constructors, transferees and unlawful subcontractors, and qualification borrowers follow their own rules and cannot directly apply this card's conclusion to claim the priority right.
- Currency of local practice: the 'six-month' exercise period in Article 14 of the Jiangsu Higher People's Court's Su Gao Fa [2018] Answers reflects the interpretation of its time; Article 41 of Fa Shi [2020] No. 25 has unified it at 'not exceeding 18 months at most', and the old local position must no longer be cited.
- Regional divergence: whether the principal of advance financing enjoys priority as project price differs across courts; interest and funds-occupation charges on advances are clearly not priority, by analogy with interest.
- This card resolves only the ranking question 'priority or not', not the substantive questions whether interest may be claimed and at what rate (see Articles 26 and 27 and related cards).
Further Reading
- Civil Code of the PRC, Article 807 (demand -> discount by agreement or auction on request -> priority out of the proceeds).
- SPC Interpretation (I) on Construction Contract Disputes (Fa Shi [2020] No. 25): Article 26 (interest rate), Article 27 (start of interest and the three deemed-due situations), Article 35 (claimant), Article 36 (ranking ahead of mortgages and other claims), Article 38 (acceptable quality precondition), Article 40 (scope and exclusion of interest / liquidated damages / damages), Article 41 (18-month peremptory period).
- SPC Interpretation (II) on Construction Contract Disputes (Fa Shi [2026] No. 12): Article 17 (ascertainment in the operative part; suspension losses not priority), Article 20 (subrogation over insurance proceeds / damages / compensation), Article 23 (effective date and transition).
- Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Decree No. 802): Articles 9 and 10 (payment terms and start), Article 12 (no compelling audit conclusions as the settlement basis), Article 17 (overdue interest).
- Composition of Construction and Installation Project Costs (Jian Biao [2013] No. 44) by MOHURD and the Ministry of Finance: the pricing-definition source of the 'scope of project price' under Article 40(1) of Fa Shi [2020] No. 25; check the principal against it.
- Jiangsu Higher People's Court, Answers on Construction Contract Disputes (Su Gao Fa [2018]), Part 4, Articles 14-20 (start date, void contract, actual constructor, exclusion of interest, mode of exercise, waiver, assignment); note that the 'six months' in Article 14 is superseded by 18 months.
- Related reading: overview of the priority right (parties / procedure / scope / period), the object scope and the amount scope of the priority right, whether suspension losses enjoy priority, the start date and rate basis of project price interest, SME payment terms and overdue interest.
Keywords
- 建设工程价款优先受偿权
- 受偿范围
- 工程款利息
- 逾期付款违约金
- 损害赔偿金
- 法释〔2020〕25号第四十条
- 法释〔2026〕12号第十七条
- 普通债权