The contractor's remedies in bankruptcy against an administrator's reduction or refusal of a works-payment claim: claim review opinion -> verification of the schedule of claims at the creditors' meeting -> a claim-confirmation action before the court accepting the bankruptcy petition (arbitration where an arbitration clause exists), covering the measure of the amount asserted (interest counted to the bankruptcy acceptance date) and joint confirmation of the construction payment priority right

The administrator's review conclusion is not final and the contractor has remedies: the administrator's treatment of the claims recorded in the schedule is procedural review only; final judgment on the substantive amount rests with the people's court (or, where the contract contains an arbitration clause, the arbitration institution). The route: request a written claim review opinion from the administrator (Enterprise Bankruptcy Law Art. 57: the administrator registers, reviews and compiles the schedule of claims, open to interested parties for inspection) -> object at the first creditors' meeting's verification of the schedule, leaving a record (Art. 58(1)) -> where the objection is unresolved, 'sue in the people's court accepting the bankruptcy petition' under Art. 58(3) (or apply to the arbitration institution under an arbitration agreement). After bankruptcy acceptance no separate performance action demanding payment from the debtor lies; only a claim-confirmation action (SPC Civil and Commercial Trial Conference Minutes, para. 110). Amount = contract-agreed price of completed works +/- variation records, price adjustment and claims + interest counted to the bankruptcy acceptance date - payments made - retention money / liquidated damages validly deductible; unmatured claims are deemed matured at acceptance and interest-bearing claims stop accruing interest from acceptance (Art. 46); the priority right may be confirmed in the same proceedings (Civil Code Art. 807; Fa Shi [2020] No. 25 Art. 36; Fa Shi [2026] No. 12 Art. 17(1)).

Applicable Codes

  • 《中华人民共和国企业破产法》(主席令第54号)第五十六条、第五十七条、第五十八条
  • 《中华人民共和国企业破产法》(主席令第54号)第四十六条、第四十七条、第五十三条
  • 《中华人民共和国企业破产法》(主席令第54号)第一百一十条、第一百一十三条
  • 《全国法院民商事审判工作会议纪要》(法〔2019〕254号)第110条
  • 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》(法释〔2020〕25号)第三十六条、第四十条、第四十一条
  • 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》(法释〔2026〕12号)第十七条、第二十一条、第二十三条(自2026年6月30日起施行)
  • 《中华人民共和国民法典》(主席令第45号)第七百九十三条、第八百零七条
  • 《保障中小企业款项支付条例》(国务院令第802号,2025修订)第九条、第十条、第十七条
  • 《中华人民共和国民事诉讼法》(2023修正)第一百五十六条
  • 《中华人民共和国仲裁法》(2025修订)第五条、第十条
  • https://splcgk.court.gov.cn/gzfwww/sfjs/details?id=ff8080816c22fc85016cd0c6673c0d9f
  • http://gongbao.court.gov.cn/Details/acb2a51944e8022044491376d19e6e.html
  • https://www.court.gov.cn/zixun/xiangqing/488441.html
  • https://pccz.court.gov.cn/pcajxxw/pcgg/ggxq?id=3191D0A247471875471ACB40EA7A9FD9

Positioning

After the debtor enters bankruptcy, the statutory chain of remedies for a contractor whose works-payment claim was reduced, refused admission, or left in suspense by the administrator ('the works cost needs expert assessment', 'litigation pending', 'settlement not yet reviewed'); how to bring the claim-confirmation action; the measure of the amount that may be asserted; and how the construction payment priority right is fixed in the same proceedings. For administrators, contractors and counsel in the claim-filing and confirmation stage.

Core conclusion

1. The administrator's review is not final

Enterprise Bankruptcy Law Art. 57: 'Having received the claim-filing materials, the administrator shall register them, review the filed claims and compile the schedule of claims. The schedule of claims and the claim-filing materials are kept by the administrator and open to the interested parties for inspection.'

Enterprise Bankruptcy Law Art. 58: 'The schedule of claims compiled under Art. 57 of this Law shall be submitted to the first creditors' meeting for verification. Where the debtor and the creditors raise no objection to the claims recorded in the schedule of claims, the people's court shall confirm them by ruling. Where the debtor or a creditor objects to a claim recorded in the schedule of claims, it may sue in the people's court accepting the bankruptcy petition.'

That is: the administrator's review is a procedural, interim conclusion; final judgment on the substantive amount rests with the people's court, or with the arbitration institution where the contract contains an arbitration clause. The core reason is that bankruptcy changes only the manner in which claims are exercised (no individual payment; unified filing and distribution), not the substance of the claims.

2. Four forms of non-recognition, one remedy route, different prayers

(1) Reduction (part admitted, the rest disallowed) -> seek confirmation of the claim in the balance amount; (2) Total refusal (not entered in the schedule) -> seek confirmation that the claim exists and of its amount; (3) Suspended confirmation (parked as 'the works cost needs expert assessment', 'litigation pending', 'settlement not yet reviewed') -> seek confirmation of the claim (a construction cost expert assessment may be requested); suspended confirmation itself causes no forfeiture; (4) Amount admitted but registered as an ordinary claim, with the priority ranking denied -> seek confirmation of priority, up to the stated amount, over the proceeds of discounting or auctioning the specific works. All four are 'objections to claims recorded in the schedule of claims' and fall uniformly under Art. 58(3).

3. Operational steps and their bases

  1. Obtain the written conclusion: request in writing that the administrator issue a claim review opinion / schedule of claims stating the admitted amount, the reductions and the reasons -- the administrator has the statutory duty to register, review and compile (Art. 57).
  2. Written objection + request for explanation and adjustment: rebut each ground of reduction item by item with evidence (settlement documents, variation records, supervisor records, acceptance reports, payment ledgers, pricing bases), retaining proof of service.
  3. Object at the creditors' meeting verification: verifying the schedule of claims is a statutory step; require the objection and its reasons to be minuted, fixing the point of 'close of verification' (the time base for the later action); creditors whose claims are undetermined may not in principle vote unless the people's court provisionally fixes their amounts (Conference Minutes, Fa [2019] No. 254, para. 110).
  4. Bring the claim-confirmation action or apply for arbitration: no arbitration clause -> sue in the court accepting the bankruptcy petition (Art. 58(3)); arbitration clause / arbitration agreement -> apply to the chosen arbitration institution, since Arbitration Law (2025 revision) Art. 5 provides that 'where the parties have reached an arbitration agreement and one party sues in a people's court, the people's court shall not accept the case, unless the arbitration agreement is void or the law provides otherwise'.
  5. Fix the price in the proceedings: apply for judicial construction cost expert assessment; for the parts as to which the facts are already clear, a partial judgment may be requested (Civil Procedure Law (2023 amendment) Art. 156: 'where part of the facts of a case is already clear, the people's court may give judgment on that part first').
  6. Confirm the priority right in the same action: request that the amount of works payment enjoying the priority right and the corresponding works be ascertained and stated in the operative part of the judgment (Fa Shi [2026] No. 12 Art. 17(1)); the priority prevails over security interests and other claims (Fa Shi [2020] No. 25 Art. 36); it must be exercised within eighteen months at most, running from the date the employer should pay the works price (the same Interpretation, Art. 41).
  7. Into the distribution stage: after the declaration of bankruptcy, a holder of security over specific property of the bankrupt enjoys priority of payment out of that specific property; under Art. 109, where the priority right is exercised without full satisfaction, the unsatisfied claim ranks as an ordinary claim; a holder that waives the priority right has its claim rank as an ordinary claim (Art. 110).

4. Two directional errors to avoid

  • After acceptance of the bankruptcy petition, a newly filed performance action 'demanding that the debtor pay' will not be accepted; the court at the same time tells the creditor to file its claim with the administrator (Conference Minutes para. 110).
  • Where the administrator refuses admission, one cannot separately sue for payment; only the claim-confirmation action under Art. 58 lies (or arbitration under the arbitration agreement).

5. Interface with actions / arbitrations brought before acceptance (Conference Minutes para. 110)

After the people's court accepts the bankruptcy petition, civil actions concerning the debtor that have been commenced but not concluded continue after the administrator takes over the debtor's property and litigation affairs; performance actions already brought by the creditor continue to be tried, but the determination of substantive rights and obligations must be coordinated with the Enterprise Bankruptcy Law and its judicial interpretations. Before such a judgment is rendered and takes effect, the creditor may at the same time file its claim with the administrator; as a creditor whose claim is undetermined it may not in principle vote unless the people's court provisionally fixes its amount; after the judgment takes effect, the creditor is paid uniformly in the bankruptcy process according to the amount determined in the judgment, and interest on its claim against the debtor stops accruing under Enterprise Bankruptcy Law Art. 46(2).

6. The measure of the amount that may be asserted

Confirmed amount = (contract-agreed price of the completed works +/- variation records, price adjustment, claims) + interest counted to the bankruptcy acceptance date - payments made - retention money / liquidated damages validly deductible.

  • The works price itself: settled under the pricing method agreed in the contract; where the contract is void but the works have passed acceptance, the contractor may be compensated by reference to the agreed works price (Civil Code Art. 793).
  • Maturity and interest: 'A claim not yet due is deemed due at the acceptance of the bankruptcy petition. Interest-bearing claims stop accruing interest from the acceptance of the bankruptcy petition.' (Art. 46)
  • Filable scope: 'Claims that are conditional, subject to a time limit, or in pending litigation or arbitration may be filed.' (Art. 47) Where the administrator or the debtor rescinds the contract under law, the counterparty files its claim for damages arising from the rescission (Art. 53).
  • Late payment interest (where the employer is a state organ, a public institution or a large enterprise and the contractor is an SME): the agreed rate may not be lower than the one-year loan prime rate at the time of contracting; absent an agreement, late interest is paid at 0.05% per day (Regulations on Ensuring Payment to Small and Medium Enterprises (State Council Decree No. 802, 2025 revision) Art. 17). Payment periods run 30 days from delivery (organs and public institutions; up to 60 days where the contract provides otherwise) / 60 days (large enterprises); where passing inspection or acceptance is agreed as the payment condition, from the date of passing inspection or acceptance (Arts. 9, 10).
  • Parts enjoying no priority: interest on late payment of the works price, liquidated damages and damages cannot be paid with priority (Fa Shi [2020] No. 25 Art. 40(2)); claims to priority for suspension, idle time and like losses caused by the employer are not supported (Fa Shi [2026] No. 12 Art. 17(2)).
  • Distribution order: after bankruptcy expenses and common-benefit debts are paid in priority, the estate is distributed in order: workers' wages, and medical and disability subsidies, comfort and compensation expenses, and basic old-age and basic medical insurance premiums payable into workers' personal accounts, and statutory compensation; then other social insurance premiums in arrears and taxes owed; then ordinary bankruptcy claims; where the same order cannot be satisfied in full, distribution is pro rata (Art. 113).

7. Consequences of failing to file in time

'Where a creditor fails to file its claim within the claim-filing period determined by the people's court, it may file a supplementary claim before the final distribution of the bankruptcy estate; provided that distributions already carried out are not supplemented to it. The costs of reviewing and confirming the supplementary claim are borne by the party filing it. A creditor that fails to file its claim as provided in this Law may not exercise its rights under the procedures of this Law.' (Art. 56) -- the filing obligation therefore cannot be bypassed; what is remedied is 'not admitted after filing', not 'not filing'.

Scope and limits

  • Applies to the claim-filing and confirmation stage after the people's court accepts the bankruptcy petition; voting and grouping rules in reorganisation and composition proceedings are outside this card.
  • Art. 58 remedies only 'objections to claims recorded in the schedule of claims' and does not replace the filing obligation; a creditor that fails to file as required may not exercise its rights through the bankruptcy procedure (Art. 56(2)), and supplementary filing is further limited by distributions already made.
  • After bankruptcy acceptance no separate performance action for payment may be brought; only a claim-confirmation action / arbitration; suing in the wrong court (not the court accepting the bankruptcy petition) ends in dismissal.
  • The time limit for a claim-confirmation action (a given number of days after close of verification) follows the Enterprise Bankruptcy Law judicial interpretations and the accepting court's requirements; in practice, sue immediately after verification closes to avoid forfeiture by lapse.
  • The priority right presupposes works quality passing acceptance and must be exercised within eighteen months at most, failing which it extinguishes (peremptory in nature).
  • Fa Shi [2026] No. 12 Arts. 17, 21, 10, 11 and 14 apply only to first-instance construction contract dispute cases newly accepted after 30 June 2026; cases accepted before that continue under the corresponding provisions of Fa Shi [2020] No. 25 (Art. 23).
  • Where the debtor has not entered bankruptcy, the contractor claims works payment by the ordinary route of a performance action plus the priority right; the file-verify-confirm chain of this card does not apply.