Filing construction payment claims in bankruptcy proceedings: addressee and filing period (30 days minimum, 3 months maximum from the announcement of acceptance), the scope of claims that may be filed (unmatured claims deemed mature, interest stops accruing, conditional and time-limited claims and claims pending litigation or arbitration), filing materials, late supplementary filing and forfeiture, verification and confirmation of the schedule of claims and objection actions, and the procedural effect that lawsuits stop and claims are filed instead after acceptance
Yes - the claim can and must be pulled into the bankruptcy proceedings: after the people's court accepts the bankruptcy petition, the contractor may no longer bring a payment action for performance; it must file in writing with the administrator within the court-fixed filing period (running from the date of the announcement of acceptance, minimum 30 days, maximum 3 months - Enterprise Bankruptcy Law Article 45); unmatured claims are deemed mature at acceptance and interest-bearing claims stop accruing from acceptance (Article 46); conditional, time-limited and litigation/arbitration-pending claims may all be filed (Article 47); the filing must state in writing the amount and whether there is property security, with evidence (Article 49); a late filer may file supplementary before the final distribution of the bankrupt estate, but distributions already made are not topped up, the costs of examination and confirmation are borne by the supplementary claimant, and one who fails to file as the law requires may not exercise rights through the bankruptcy procedure (Article 56); the administrator registers, examines and compiles the schedule of claims (Article 57), which is submitted to the first creditors' meeting for verification - unobjected claims are confirmed by court ruling, objected claims go to suit before the accepting court (Article 58).
Applicable Codes
- 《中华人民共和国企业破产法》(主席令第54号)第二十一条、第四十五条、第四十六条、第四十七条、第四十八条、第四十九条、第五十六条、第五十七条、第五十八条、第七十五条、第九十二条、第九十六条、第一百零九条、第一百一十条、第一百一十三条
- 《全国法院民商事审判工作会议纪要》(法〔2019〕254号)第110条
- 《中华人民共和国民法典》第八百零七条
- 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》(法释〔2020〕25号)第三十五条至第四十一条
- 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》(法释〔2026〕12号)第十七条、第二十一条、第二十三条
Topic Positioning
After the people's court accepts a bankruptcy petition against the debtor (the employer), the filing rules for the contractor's claim to unpaid construction payment: to whom the claim is filed, by when, what scope, what materials, what happens if late, and how the claim is confirmed after filing. Based on the Enterprise Bankruptcy Law (Presidential Order No. 54) Articles 21, 45, 46, 47, 48, 49, 56, 57 and 58, and Article 110 of the Minutes of the National Conference of Courts on Civil and Commercial Trial Work (Fa [2019] No. 254). The existence, scope and 18-month time limit of the construction payment priority right are covered by a dedicated card; this card covers only the filing stage.
Core Conclusions
I. First fix the time points: procedural milestones on acceptance (Article 21)
- Where a creditor petitions for bankruptcy, the people's court shall notify the debtor within 5 days of receiving the petition; if the debtor objects, it shall raise the objection within 7 days of receiving the notice; the court shall rule on acceptance within 10 days of the expiry of the objection period.
- Outside the foregoing, the court shall rule on acceptance within 15 days of receiving the bankruptcy petition; where special circumstances require extension, with approval of the court at the next higher level it may be extended by 15 days.
- Service of the acceptance ruling: where the court accepts a bankruptcy petition, it shall serve the ruling on the petitioner within 5 days of its making; where a creditor petitioned, it shall also serve it on the debtor within 5 days of the ruling; the debtor shall, within 15 days of service, submit a statement of its assets, schedules of debts and claims, relevant financial accounting reports, and particulars of wage payments and social insurance contributions for staff and workers.
- Key note: Enterprise Bankruptcy Law Article 21, original text - 'Where the people's court rules to accept a bankruptcy petition, it shall appoint an administrator at the same time. The people's court shall notify the known creditors within 25 days of the ruling accepting the bankruptcy petition, and shall make an announcement.' The notice and announcement shall state seven items, of which item (3) is 'the period, place and points of note for filing claims' and item (6) is 'the time and place of the first creditors' meeting'. The contractor fixes the starting point and the place of filing from the court's announcement or notice.
II. After acceptance: stop litigating and file instead (Article 21; Minutes Article 110)
Original text of the relevant parts of Enterprise Bankruptcy Law Article 21:
- 'After the people's court accepts a bankruptcy petition, any payment by the debtor to an individual creditor is void.'
- 'After the people's court accepts a bankruptcy petition, preservation measures over the debtor's property shall be lifted and enforcement procedures shall be suspended.'
- 'After the people's court accepts a bankruptcy petition, civil actions or arbitration proceedings concerning the debtor that have begun but not concluded shall be suspended; after the administrator takes over the debtor's property, such action or arbitration shall continue.'
- 'After the people's court accepts a bankruptcy petition, civil actions concerning the debtor may only be brought before the people's court that accepted the bankruptcy petition.'
- On executory contracts: 'After the people's court accepts a bankruptcy petition, the administrator has the right to decide to rescind or continue performing a contract formed before acceptance of the petition that neither the debtor nor the counterparty has fully performed, and to notify the counterparty. If the administrator fails to notify the counterparty within two months of acceptance of the bankruptcy petition, or fails to reply within 30 days of receiving the counterparty's demand, the contract is deemed rescinded.' Where the administrator decides to continue performance, the counterparty shall perform but may demand security from the administrator; if none is provided, the contract is deemed rescinded.
Minutes Article 110, further operating rules:
- 'After the people's court accepts a bankruptcy petition, new payment actions brought by creditors against the debtor are not accepted, and the creditors are told instead to file their claims with the administrator. After filing, a creditor disputing the schedule of claims compiled by the administrator may bring a claim-confirmation action under Article 58 of the Enterprise Bankruptcy Law.'
- Payment actions brought before acceptance continue after the administrator takes over the debtor's property and litigation affairs: 'where a creditor has already brought a payment action against the debtor, after acceptance of the bankruptcy petition the people's court shall continue to try it, but in determining the substantive rights and obligations of the parties concerned it shall co-ordinate with the provisions of the Enterprise Bankruptcy Law and its judicial interpretations'.
- 'Before such judgment is rendered and takes effect, the creditor may at the same time file its claim with the administrator, but as a creditor whose claim is not yet determined it may in principle not exercise voting rights, unless the people's court provisionally fixes its claim amount. After the judgment takes effect, the creditor shall be paid in the bankruptcy proceedings according to the amount found in the judgment, and interest on its claim against the debtor shall stop accruing under Article 46(2) of the Enterprise Bankruptcy Law.'
III. To whom and for how long (Article 45)
Article 45, original text: 'After the people's court accepts a bankruptcy petition, it shall fix the period for creditors to file claims. The claim-filing period runs from the date of the people's court's announcement of acceptance of the bankruptcy petition, and shall be no shorter than 30 days and no longer than 3 months.'
Claims are filed with the administrator, not the people's court; the period runs from the date of the announcement of acceptance (not the date of the ruling, nor the date of receiving the notice).
IV. What may be filed: scope of claims (Articles 46, 47, 48, 49)
- Article 46, original text: 'An unmatured claim is deemed mature upon acceptance of the bankruptcy petition. Interest-bearing claims stop accruing interest from acceptance of the bankruptcy petition.' -> Even if the payment date of the construction payment has not fallen due, it must still be filed; interest and losses for late payment are computed only up to the acceptance date.
- Article 47, original text: 'Conditional claims, time-limited claims and claims in pending litigation or arbitration may be filed by the creditor.' -> Construction payment claims whose settlement is undetermined, or which are in litigation or arbitration, are not barred from filing for being 'not yet determined'.
- Article 48(1), original text: 'Creditors shall file their claims with the administrator within the period fixed by the people's court.' Paragraph 2 exempts employee claims from filing: wages owed by the debtor to staff and workers, medical and injury subsidies and death benefits, basic pension and basic medical insurance contributions that ought to be credited to individual employee accounts, and compensation required by laws or administrative regulations to be paid to employees need not be filed; the administrator investigates, lists and publicises them; an employee objecting to the list may demand correction, and if the administrator refuses to correct, the employee may sue in the people's court.
- Article 49, original text: 'When filing a claim, the creditor shall state in writing the amount of the claim and whether it is secured by property, and submit the relevant evidence. Where the claim filed is a joint and several claim, this shall be stated.' -> A party asserting the construction payment priority right must at this stage expressly state 'secured by property / priority' and submit evidence of scope and entitlement, otherwise the ranking can hardly be asserted later.
V. If late (Article 56)
Original text: 'A creditor who has not filed a claim within the period fixed by the people's court may make a supplementary filing before the final distribution of the bankrupt estate; however, distributions already made are not supplemented for it. The costs of examining and confirming the supplementary claim are borne by the supplementary claimant. A creditor who fails to file as provided in this Law may not exercise rights under the procedures of this Law.' -> The supplementary filing right survives until the final distribution of the bankrupt estate, but at the price of: no top-up for what was already distributed, and self-borne examination costs; total failure to file forfeits rights within the bankruptcy procedure. Article 92 adds: a creditor who has not filed as the law requires may not exercise rights during implementation of the reorganisation plan, and after the plan is implemented may exercise rights on the repayment terms for claims of the same class provided in the plan.
VI. After filing: examination - schedule - verification - confirmation (Articles 57, 58)
- Article 57, original text: 'After receiving the claim-filing materials, the administrator shall register them, examine the claims filed, and compile a schedule of claims. The schedule of claims and the claim-filing materials are kept by the administrator for inspection by interested parties.'
- Article 58, original text: 'The schedule of claims compiled under Article 57 of this Law shall be submitted to the first creditors' meeting for verification. Where the debtor and the creditors raise no objection to the claims recorded in the schedule, the people's court shall rule to confirm them; where the debtor or a creditor objects to the claims recorded, it may sue in the people's court that accepted the bankruptcy petition.'
VII. Payment after confirmation: the priority part and the ordinary part are computed separately (Articles 110, 113)
- Article 110, key points of the original text: 'A right holder with security over specific property of the bankrupt enjoys a right of priority payment out of that specific property. Where a creditor with the right under Article 109 of this Law fails to be paid in full upon exercising its right of priority payment, the unpaid part of its claim ranks as an ordinary claim; where it waives its right of priority payment, its claim ranks as an ordinary claim.'
- Article 113, order of payment, original text: (1) wages owed by the bankrupt to its staff and workers, medical and injury subsidies and death benefits, basic pension and basic medical insurance contributions that ought to be credited to individual employee accounts, and compensation required by laws or administrative regulations to be paid to employees; (2) social insurance contributions other than those in the preceding item owed by the bankrupt and taxes owed by the bankrupt; (3) ordinary bankruptcy claims; where the bankrupt estate is insufficient to meet payment demands of the same order, distribution is pro rata.
- Hence the filing should be split on a dual basis: the priority amount (the part falling within 'the price of the construction works', limited to the proceeds of the discounted sale or auction of the works, excluding interest, liquidated damages, damages, and suspension and idle-time losses for first-instance cases newly accepted after 30 June 2026) plus the ordinary amount (total minus the priority amount), to avoid the whole claim being paid at the ordinary ratio.
VIII. The pace of enforcing security differs by procedure: during reorganisation, security over specific property of the debtor is suspended; where the secured property is at risk of damage or evident diminution in value sufficient to harm the secured creditor's rights, the secured creditor may request the people's court to allow enforcement (Article 75); from the date of the ruling of settlement, right holders with security over specific property may exercise their rights (Article 96); in liquidation, priority payment out of specific property is governed by Articles 109 and 110.
Scope and Limits
- The filing period is not the limitation period: it runs from the announcement of acceptance, 30 days to 3 months, fixed by the court upon acceptance and communicated by notice and announcement; once missed, only supplementary filing under Article 56 is available, with no top-up for prior distributions.
- The Article 45 filing period and the 18-month exclusion period of the priority right are two independent periods: expressly asserting priority with the administrator within the former does not amount to exercising the priority right within the latter (which requires demand, an agreement on discounted sale, litigation or arbitration); both must be tracked separately.
- Risk of filing with the wrong party: lodging the filing with the court or the trial court has no filing effect; file with the administrator; it is the objection to the schedule of claims that goes to the accepting court.
- The exemption of employee claims from filing (Article 48(2)) covers only wage-type items among claims, investigated and publicised by the administrator; it does not apply to the contractor's claim for construction payment against the employer.
- 'Deemed mature' for unmatured claims only makes them filable; it does not alter the substantive rights and obligations under the contract; the time point at which interest-bearing claims stop accruing is acceptance of the bankruptcy petition (not the declaration of bankruptcy, nor the date of announcement).
- This card covers only the filing stage; remedies after the administrator disallows a claim, and the scope and starting point of the priority right, are covered by dedicated cards.
Further Reading
- Enterprise Bankruptcy Law of the PRC (Presidential Order No. 54), Article 21 (acceptance procedure, announcement, effects of acceptance and executory contracts), Article 45 (filing period), Article 46 (deemed maturity and stop of interest), Article 47 (conditional, time-limited and pending claims), Article 48 (duty to file and the employee-claim exemption), Article 49 (filing materials), Article 56 (supplementary filing and forfeiture), Article 57 (examination and schedule), Article 58 (verification, confirmation and objection actions), Article 75 (suspension of security during reorganisation), Article 92 (effect of the reorganisation plan on non-filing creditors), Article 96 (exercise of security after the settlement ruling), Articles 109 to 110 (separation rights and the unpaid balance as ordinary claims), Article 113 (order of payment).
- Minutes of the National Conference of Courts on Civil and Commercial Trial Work (Fa [2019] No. 254), Article 110 [treatment of debtor-related litigation after acceptance].
- Civil Code Article 807; Interpretation of the Supreme People's Court on the Application of Law in Cases of Construction Contract Disputes (I) (Fa Shi [2020] No. 25) Articles 35 to 41; Interpretation (II) (Fa Shi [2026] No. 12) Articles 17, 21 and 23 - for the boundary of the 'priority amount' of the filed claim and the 18-month limit.
- Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Order No. 802), Articles 8 to 17 - for payment terms, late-payment interest and settlement disputes before bankruptcy acceptance; the 'when payment is due' track, complementary to the 'how to realise it' track of bankruptcy filing.