Start point of the exercise period (18 months at most) of the contractor's priority right to payment for construction works - determining 'the date the project price ought to be paid': where the payment date was varied by agreement due to objective causes, take the varied date; where a settlement agreement expressly fixes the date, take that date (Fa Shi [2026] No. 12, Article 21); where neither exists, the three presumptions of Article 27 of Fa Shi [2020] No. 25, and the effective-date threshold of Article 23

The exercise period of the priority right is 18 months at most, running from 'the date the project price ought to be paid', with the start point determined in sequence: (1) where the payment date agreed in the contract was varied by agreement for objective causes such as extension of time, take the varied date (Fa Shi [2026] No. 12, Article 21, paragraph 1); (2) where the contract is silent or unclear but the settlement agreement expressly fixes the payment date, take that date (Article 21, paragraph 2); (3) where neither exists, presume under Article 27 of Fa Shi [2020] No. 25: works delivered - the date of delivery; not delivered - the date of submitting the final account documents; neither delivered nor settled - the date of filing suit. Article 21 settles only the start point and does not alter the 18-month length of the period; the interpretation took effect on 30 June 2026 and applies to first-instance cases newly accepted after that date.

Applicable Codes

  • 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》(法释〔2026〕12号,2026年6月30日施行)第21条、第23条
  • 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》(法释〔2020〕25号)第26条、第27条、第41条
  • 《中华人民共和国民法典》第807条
  • https://www.court.gov.cn/fabu/xiangqing/504221.html

Topic Positioning

How to determine the start point of the exercise period of the priority right to payment for construction works (18 months at most) - which day counts as 'the date the project price ought to be paid' in each of three situations: a payment date varied by agreement, a date separately and expressly fixed in a settlement agreement, and a contract silent or unclear. The core bases are Article 21 of the Interpretation (II) of the Supreme People's Court on the Application of Law in Construction Contract Dispute Cases (Fa Shi [2026] No. 12), and Articles 27 and 41 of Interpretation (I) (Fa Shi [2020] No. 25).

Core Conclusions

1. Text of Article 21 of Fa Shi [2026] No. 12 (two situations, both supporting the contractor)

'Where the construction contract fixes the date on which the employer ought to pay the project price, and the parties, for objective causes such as extension of time, vary the payment date by agreement, and the contractor claims that the exercise period of the priority right to payment for construction works runs from the varied date on which the project price ought to be paid, the people's court shall support the claim. Where the construction contract does not fix, or unclearly fixes, the date on which the employer ought to pay the project price, but the parties have expressly fixed the date on which the project price ought to be paid in a settlement agreement, and the contractor claims that the exercise period of the priority right to payment for construction works runs from that date, the people's court shall support the claim.'

That is: (1) where the date originally agreed in the contract was varied by agreement 'for objective causes such as extension of time', the start point is the varied date on which the project price ought to be paid, not the originally agreed date; (2) where the contract is silent or unclear but the payment date is expressly fixed in a settlement agreement, the start point is the date fixed in that settlement agreement.

2. The length of the period remains 18 months at most Under Article 41 of Fa Shi [2020] No. 25, the priority right must be exercised within a reasonable period, not exceeding 18 months at most, running from the date the employer ought to pay for the construction works. Article 21 settles only 'on which day the start point falls' and does not change the 18-month period itself.

3. The three situations for 'the payment due date' where the contract is silent or unclear Text of Article 27 of Fa Shi [2020] No. 25:

'Interest is computed from the date the project price becomes payable. Where the parties have not agreed, or have unclearly agreed, on the time of payment, the following times are deemed the payment due date: (1) where the construction works have actually been delivered, the date of delivery; (2) where the construction works have not been delivered, the date of submitting the final account documents; (3) where the works have not been delivered and the price has not been settled, the date on which the party filed suit.'

Although the article is worded as a rule on computing interest, it establishes the presumption order for 'the payment due date', and judicial practice likewise uses it as the fallback path for fixing 'the date the project price ought to be paid' and hence the start point of the priority right: delivered -> date of delivery; not delivered -> date of submitting the final account documents; neither delivered nor settled -> date of filing suit.

4. Interface with payment-period clauses held invalid (e.g. pay-when-paid clauses) Once a pay-when-paid (back-to-back) clause is held invalid, the original payment period is deemed not agreed; the parties must first supplement it by agreement and then have it reasonably determined by reference to industry standards and trade usage (Fa Shi [2024] No. 11, Article 2). If the parties then fix the payment date by supplementary or settlement agreement, that date becomes the 'date expressly fixed in a settlement agreement' under Article 21, paragraph 2, and at the same time starts the 18-month priority right period; absent such agreement, the matter falls back to the three presumptions of Article 27.

5. The practical sequence

  1. First check whether the contract fixes a payment date -> if it does, check whether that date was varied by agreement for objective causes such as extension of time (written traces are needed: a variation agreement, minutes or correspondence); if the variation stands, take the varied date;
  2. Contract silent or unclear -> check whether the settlement agreement expressly fixes a payment date; if so, take that date;
  3. Neither -> apply Article 27 in order: date of delivery / date of submitting the final account documents / date of filing suit;
  4. From the determined start point the right must be exercised within 18 months (by demand, by agreeing with the employer to discount the works, or by filing suit or applying for arbitration); delay risks the claim being refused.

Boundaries of Application

  • The scope is the contractor's priority right to payment for construction works in construction contract disputes; disputes over the start point do not affect separate claims to the price principal and to interest (interest: see also Articles 26 and 27 of Fa Shi [2020] No. 25).
  • Article 21, paragraph 1 confines the cause of variation to 'extension of time and other objective causes' and requires variation by agreement; a unilateral notice, or the employer's unjustified unilateral dragging out of payment, is not 'variation by agreement' and cannot push the start point later.
  • Article 21, paragraph 2 confines the vehicle to a date 'expressly fixed in a settlement agreement'; a payment arrangement loosely mentioned in minutes or a reconciliation letter, without a clear date, may not satisfy 'expressly fixed'.
  • The 18 months is a maximum; where the law or a judicial interpretation provides otherwise, or the parties agree a shorter period, those govern; once the start point is fixed, it is too late to argue the period has not started on the ground that 'the works have not been finally settled' or 'the audit is not complete' (an audit clause settles the basis of the account, not the time of payment).
  • Temporal effect: Fa Shi [2026] No. 12 was adopted at the 1969th meeting of the Adjudication Committee of the Supreme People's Court on 17 March 2026, published on 29 June 2026 and takes effect on 30 June 2026. Under its Article 23, it applies to first-instance construction contract dispute cases newly accepted by the people's courts after it takes effect, and where earlier judicial interpretations of the Supreme People's Court are inconsistent with it, it prevails. First-instance cases accepted before 30 June 2026 are still handled under the earlier interpretations.

Further Reading

  • Interpretation (II) of the Supreme People's Court on the Application of Law in Construction Contract Dispute Cases (Fa Shi [2026] No. 12), full text (including Articles 21 and 23): https://www.court.gov.cn/fabu/xiangqing/504221.html
  • Interpretation (I) (Fa Shi [2020] No. 25), Articles 26, 27 and 41.
  • Civil Code Article 807 (the substantive basis of the contractor's priority right: after demand and continued non-payment, the contractor may agree with the employer to discount the works or apply to the court for auction).
  • For systemic impact see the overall-impact topic on Interpretation (II): https://www.court.gov.cn/zixun/xiangqing/504201.html

Keywords

  • 建设工程价款优先受偿权
  • 优先受偿权行使期限
  • 十八个月
  • 应当给付工程价款之日
  • 法释〔2026〕12号
  • 应付款时间推定