The contractor's construction works payment priority over insurance proceeds, damages and expropriation compensation after the works are damaged, destroyed or expropriated (subrogation of the security interest): conditions for applying Article 20 of Fa Shi [2026] No. 12, the boundaries of amount and time limit, and the temporal dividing point between the old and new rules
Yes. Article 20 of Fa Shi [2026] No. 12 provides: 'Where the construction works are damaged, destroyed or expropriated, and the contractor claims priority payment out of the insurance proceeds, damages or compensation so obtained, the people's court shall support the claim.' The doctrinal basis is subrogation of the payment priority onto substitute payments, by reference to Article 390 of the Civil Code. But the subrogated subject matter remains subject to two hard boundaries: in amount it is limited to the works price itself (interest on overdue payment, liquidated damages and damages take no priority under Article 40(2) of Interpretation No. 25, and losses from suspension and idle labour and plant caused by the employer take no priority under Article 17(2) of Interpretation No. 12), and in time it is bound by the maximum 18-month exclusion period (Article 41, with the starting point under Article 21); quality up to standard is a precondition. The rule takes effect on 30 June 2026 and, under Article 23, applies to first-instance cases newly accepted after that date; for cases accepted earlier only analogy to Article 390 of the Civil Code is available.
Applicable Codes
- 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》(法释〔2026〕12号)第十七条、第十八条、第十九条、第二十条、第二十一条、第二十三条
- 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》(法释〔2020〕25号)第三十八条、第三十九条、第四十条、第四十一条
- 《中华人民共和国民法典》第三百九十条、第八百零七条
- 《中华人民共和国民事诉讼法》(2023修正)第二百零七条、第二百零八条
- 《中华人民共和国仲裁法》(2025修订)第三条、第五条、第十条
- https://www.court.gov.cn/fabu/xiangqing/504221.html
Subject Positioning
Where construction works (under construction or completed) are damaged, destroyed or expropriated and thus converted into insurance proceeds, damages or expropriation compensation, can the contractor claim its construction works payment priority over such 'substitute payments' - that is, subrogation of the payment priority onto substitute subject matter. The core basis is Article 20 of the SPC Interpretation (II) on Application of Law in Cases Involving Construction Contract Disputes (Fa Shi [2026] No. 12), with Article 390 of the Civil Code as doctrinal support, while the claim remains subject to the limits inherent in the payment priority: scope of amount, quality precondition and time limit for exercise.
Core Conclusions
1. Conclusion: the claim can be made and the court shall support it. Article 20 of Fa Shi [2026] No. 12 reads: 'Where the construction works are damaged, destroyed or expropriated, and the contractor claims priority payment out of the insurance proceeds, damages or compensation so obtained, the people's court shall support the claim.'
2. Doctrinal basis (subrogation onto substitute payments). Article 390 of the Civil Code: 'During the security period, if the secured property is damaged, destroyed or expropriated, the holder of the security interest may claim priority payment out of the insurance proceeds, damages or compensation obtained. Where the period for performance of the secured claim has not yet expired, such insurance proceeds, damages or compensation may also be deposited with a depository.' Once the works, as the assets out of which the contractor is to be paid, are converted into insurance proceeds, damages or compensation, the priority passes to the substitute and is not defeated by the change in the form of the subject matter; where the performance period has not expired, deposit of the proceeds may be requested.
3. Boundary one - the subrogated subject matter remains limited to the 'works price' and does not expand by subrogation.
- Article 40 of Fa Shi [2020] No. 25: 'The scope of the contractor's construction works payment priority is determined under the provisions of the relevant administrative departments of the State Council on the scope of construction works payment. Where the contractor claims priority for interest on overdue construction works payment, liquidated damages, damages and the like, the people's court shall not support the claim.'
- Article 17(2) of Fa Shi [2026] No. 12: 'Where the contractor claims the construction works payment priority for losses such as suspension or idle labour and plant caused by the employer, the people's court shall not support the claim.'
- Article 17(1) of the same interpretation: 'Where the contractor requests confirmation that it enjoys the construction works payment priority, the people's court shall ascertain the amount of works payment covered by the priority and the corresponding works, and specify them in the operative part of the judgment.' When claiming priority over insurance or compensation proceeds, the 'amount plus corresponding works' must likewise be specified.
4. Boundary two - the time limit for exercise is unchanged, at a maximum of 18 months. Article 41 of Fa Shi [2020] No. 25: 'The contractor shall exercise the construction works payment priority within a reasonable period, which in no case exceeds 18 months, running from the date on which the employer should pay the construction works price.' The starting point follows Article 21 of Fa Shi [2026] No. 12: where a payment date was agreed and is then varied by negotiation for objective reasons such as an extension of the construction period, the period runs from the varied date; where no date was agreed or the agreement is unclear but a settlement agreement clearly specifies a payment date, the period runs from that date.
5. Precondition - quality up to standard. Article 38 of Fa Shi [2020] No. 25: 'Where the quality of the construction works is up to standard and the contractor requests that the price of the works it constructed be paid in priority out of the proceeds of discounting or auction of the works, the people's court shall support the request.' Article 39: 'Where the quality of an uncompleted construction work is up to standard and the contractor requests that the price of the part it constructed be paid in priority out of the proceeds of discounting or auction of that part, the people's court shall support the request.' Where quality fails there is no priority, and receipt of insurance proceeds does not change that conclusion.
6. Affirmative and negative scenarios compared.
| Scenario | Conclusion | Basis |
|---|---|---|
| Works damaged, destroyed or expropriated; insurance proceeds, damages or compensation obtained or definitively obtainable | Priority supported | Article 20 of Interpretation No. 12 |
| Works uncompleted but the part constructed by the contractor is up to standard; claim over the compensation for that part | Supported, limited to 'the part of the works it constructed' | Article 39 of Interpretation No. 25 plus Article 20 of Interpretation No. 12 |
| Claimed amount falls within the works price | Supported; the operative part of the judgment must specify the amount and the corresponding works | Article 20 and Article 17(1) of Interpretation No. 12 |
| Claiming interest on overdue payment, liquidated damages or damages out of insurance or compensation proceeds | Priority not supported; ordinary claim only | Article 40(2) of Interpretation No. 25 |
| Claiming losses such as suspension or idle labour and plant out of insurance or compensation proceeds | Priority not supported | Article 17(2) of Interpretation No. 12 |
| Works quality fails (not rectified to standard) | No payment priority | A contrario reading of Article 38 of Interpretation No. 25 |
| Insurance or compensation proceeds not yet paid; amount still under loss adjustment or compensation still under negotiation | The right may be asserted and the receivable preserved; deposit may be requested where the performance period has not expired | Second sentence of Article 390 of the Civil Code |
| 18-month exercise period exceeded | Not supported; reduced to an ordinary claim | Article 41 of Interpretation No. 25; starting point under Article 21 of Interpretation No. 12 |
7. The temporal dividing point (critical). Article 23 of Fa Shi [2026] No. 12: 'This Interpretation takes effect on 30 June 2026. For first-instance construction contract dispute cases newly accepted by the people's courts after this Interpretation takes effect, this Interpretation applies. Where judicial interpretations previously issued by the Supreme People's Court are inconsistent with this Interpretation, this Interpretation prevails.' That is: first-instance cases newly accepted on or after 30 June 2026 may apply Article 20 directly; cases accepted before that date may not invoke Article 20 directly - Fa Shi [2020] No. 25 contains no express provision on subrogation onto insurance or compensation proceeds, so only analogy to Article 390 of the Civil Code is available, and judicial practice differs across regions. The Interpretation was adopted at the 1969th meeting of the SPC Adjudication Committee on 17 March 2026 and published on 29 June 2026.
8. Assignees must additionally pass the Article 19 review. Article 19 of Fa Shi [2026] No. 12: 'Where the assignee of a construction works payment claim claims priority payment out of the proceeds of discounting or auction of the works, the people's court shall rule taking into account whether the works passed taking-over (completion acceptance), whether the works price has been settled, whether the claim assignment contract is valid, and whether the assignee has paid a reasonable assignment price.' Where the works have been destroyed or expropriated and only substitute payments remain, the assignee must likewise pass this four-factor review.
9. Route of realisation. Article 807 of the Civil Code: 'Where the employer fails to pay the price as agreed, the contractor may demand payment within a reasonable period. If the employer still fails to pay upon expiry of that period, the contractor may, unless the nature of the works makes discounting or auction inappropriate, agree with the employer to discount the works, or request the people's court to auction the works in accordance with law. The construction works price is paid in priority out of the proceeds of the discount or auction of the works.' Where the works have been destroyed or expropriated and cannot be discounted or auctioned, the remedy shifts to the corresponding payments: the contractor may sue for confirmation of the priority and for priority payment out of those payments; it may also use the special procedure for realisation of security interests under Articles 207 and 208 of the Civil Procedure Law (applying to the basic-level court of the place of the secured property or of the registration of the security interest; after review the court rules on auction or sale, enforcement is applied for under the ruling, and if the conditions are not met the application is rejected by ruling and a separate action may be brought). Such property-interest disputes may be arbitrated under Article 3 of the Arbitration Law; where an arbitration agreement exists the court will not accept the case (Article 5), and the award is final on one decision (Article 10).
Scope of Application
- This card resolves only whether the priority carries over to substitute payments, not the existence or amount of the substitute payments themselves; whether insurance is payable, and the standard and scope of expropriation compensation, are determined separately under the insurance contract, the expropriation compensation agreement and the related provisions.
- The subrogated subject matter does not extend to value beyond the scope of the works constructed by the contractor: compensation for land use rights, parts separately contracted out by the employer, indoor equipment and other payments not corresponding to work performed by the contractor are not the price of 'the part of the works it constructed' and carry no priority (a conclusion of systematic interpretation, not express wording).
- 'Claimable' is not 'priority in full': portions beyond the works price (interest, liquidated damages, damages, suspension and idle-resource losses) remain valid claims but rank as ordinary claims, paid alongside mortgages and other claims in order of priority.
- Temporal effect is a hard boundary: first-instance cases accepted before 30 June 2026 do not automatically apply Article 20; the claim must be framed as analogy to Article 390 of the Civil Code, with divergence in judicial practice anticipated.
- Article 20 speaks of insurance proceeds, damages or compensation 'obtained': where payment has not actually been received, the right exists in principle but must be secured by preserving the receivable or requesting deposit; priority over a definitively ascertained amount cannot be claimed directly.
- Where this intersects with exercise by discount agreement (the contract separately provides discount arrangements for damage, destruction or expropriation), the conditions for exercise by discount under Article 18 of Fa Shi [2026] No. 12 must also be met.
Further Reading
- Fa Shi [2026] No. 12, Articles 17, 18, 19, 20, 21 and 23; original text at the Supreme People's Court website: https://www.court.gov.cn/fabu/xiangqing/504221.html
- Fa Shi [2020] No. 25, Article 38 (quality), Article 39 (uncompleted part), Article 40 (scope, excluding interest, liquidated damages and damages), Article 41 (18 months)
- Civil Code of the PRC, Article 390 (subrogation and deposit where the secured property is damaged, destroyed or expropriated), Article 807 (manner of exercising the payment priority)
- Civil Procedure Law (2023 amendment), Articles 207 and 208 (special procedure for realisation of security interests)
- Arbitration Law (2025 revision), Article 3 (arbitrable scope), Article 5 (court will not accept where an arbitration agreement exists), Article 10 (award final on one decision)
- Supporting point: the scope of works payment is determined by the provisions of the relevant administrative departments of the State Council on the scope of construction works payment (the cost-composition basis), which is the yardstick for what can take priority in the subrogated subject matter.
Keywords
- 建设工程价款优先受偿权
- 物上代位
- 保险金赔偿金补偿金
- 毁损灭失被征收
- 法释〔2026〕12号第二十条
- 18个月行使期限
- 工程价款范围
- 建工解释二