Four statutory conditions for a contractor to exercise the construction payment priority right (the statutory priority right of the contractor to payment for the works under Article 807 of the Civil Code) through a discount agreement with the employer - acceptable work quality, works capable of discounted transfer, payment still overdue after demand, and a discount amount broadly equivalent to actual value - plus the subrogation rule under which the contractor claims priority payment out of insurance proceeds, damages or expropriation compensation when the works are damaged, destroyed or expropriated

Where a contractor claims to have exercised the construction payment priority right through a discount agreement with the employer, all four conditions of Article 18 of Fa Shi [2026] No. 12 must be met simultaneously: the quality of the works constructed is acceptable, the works are capable of discounted transfer, the employer still fails to pay within a reasonable period after the contractor's demand, and the discount amount is broadly equivalent to the actual value of the works at the time of the discount; where the works are damaged, destroyed or expropriated, the contractor may claim priority payment out of the insurance proceeds, damages or compensation obtained (Article 20).

Applicable Codes

  • 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第十八条、第十九条、第二十条
  • 《中华人民共和国民法典》第八百零七条
  • 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第三十八条、第四十条

Positioning

The two non-litigation forms of realising the construction payment priority right: first, the four conditions that must be satisfied for a contractor to exercise the priority right through a discount agreement with the employer (one of the routes under Article 807 of the Civil Code); second, subrogation of the subject matter of the priority right - whether the contractor may claim priority payment out of insurance proceeds, damages or compensation when the works are damaged, destroyed or expropriated.

Core conclusions

1. The four conditions for exercising the priority right by discount agreement (Article 18 of Fa Shi [2026] No. 12, original text): 'Where a contractor claims, on the basis of a discount agreement concluded with the employer, to have exercised the construction payment priority right under Article 807 of the Civil Code, and the following conditions are met, the people's court shall support the claim: (1) the quality of the works constructed by the contractor is acceptable; (2) the construction works are capable of discounted transfer; (3) the employer is overdue in paying the project price and still fails to pay within a reasonable period after the contractor's demand; (4) the discount amount is broadly equivalent to the actual value of the works at the time of the discount.' The four conditions must hold simultaneously; failure of any one means the claim is unsupported: conditions (1) and (2) set the object and quality thresholds, condition (3) corresponds to the prior demand procedure under Article 807 of the Civil Code, and condition (4) is the fairness review of the discount agreement itself - where the discount amount is manifestly below the actual value (a disguised low-price set-off of debt prejudicing other creditors), the priority right cannot be held to have been exercised on that basis.

2. Priority payment out of substitutes (Article 20 of Fa Shi [2026] No. 12, original text): 'Where the construction works are damaged, destroyed or expropriated, and the contractor claims priority payment out of the insurance proceeds, damages or compensation obtained, the people's court shall support the claim.' The priority right is thus not extinguished by the physical loss of the works; its effect extends to the transformed forms of its value (insurance proceeds, damages, expropriation compensation), on the same reasoning as priority payment out of the discounted or auction proceeds of the works.

3. An assignee claiming the priority right after transfer of the payment claim (Article 19, original text): 'Where an assignee of a claim to the project price claims priority payment out of the proceeds of discounting or auctioning the construction works, the people's court shall rule by comprehensively considering factors such as whether the construction works have passed completion acceptance, whether the project price has been settled, whether the claim-transfer contract is valid, and whether the assignee has paid a reasonable transfer price.' The assignee's claim does not stand automatically; it undergoes a four-factor review (for the review approach on an assignee's standing, see the separate card on claim transfer).

4. Relation to existing rules: Article 18 does not alter the constitutive requirements or the scope of the priority right - the scope of the project price remains determined under Article 40 of Fa Shi [2020] No. 25 (excluding interest, liquidated damages and damages), and the quality requirement is consistent with Article 38; a discount agreement is merely one means of exercise, parallel to petitioning the court for auction, and both presuppose 'payment overdue after demand'.

Boundaries of application

  • Article 18 governs the determination that the priority right 'has been exercised': signing a discount agreement does not mean the right has been realised; the four conditions must be proven item by item. Where the agreed amount is seriously out of line with the actual value, the court will not support the claim, and other creditors (such as mortgagees) may allege prejudice to their interests.
  • 'Capable of discounted transfer' excludes the cases expressly stated in Article 807 of the Civil Code where the works 'are by their nature unsuitable for discounting or auction'.
  • A discount agreement remains subject to the time limit on exercising the priority right - 18 months at most, running from the date on which the project price became payable by the employer; a discount agreement signed after expiry produces no priority effect.
  • Article 20 addresses insurance proceeds, damages and compensation obtained after the works are damaged, destroyed or expropriated, and presupposes that the priority right itself is established (proper holder, acceptable quality, exercise within the time limit, amount within the scope of the project price); interest, liquidated damages, damages, and costs of suspension or idle resources cannot obtain a priority ranking through substitutes.
  • Fa Shi [2026] No. 12 takes effect on 30 June 2026; under its Article 23, first-instance cases newly accepted after that date apply this Interpretation, while cases accepted earlier are handled under the previous interpretation framework.

Further reading

  • Civil Code of the PRC, Article 807 (three routes: demand, discount agreement, petition for auction).
  • Fa Shi [2026] No. 12, SPC Interpretation (II) on Construction Contract Disputes: Article 18 (four conditions for a discount agreement), Article 19 (four factors for an assignee claiming the priority right), Article 20 (priority payment out of insurance proceeds, damages and compensation), Article 23 (temporal application).
  • Fa Shi [2020] No. 25: Article 38 (acceptable quality), Article 40 (scope of priority payment), Article 41 (18 months).
  • Public court commentary (Chinese source): http://hebdw.hljcourt.gov.cn/public/detail.php?id=3961

Keywords

  • 折价协议
  • 协议折价行使优先受偿权
  • 物上代位
  • 保险金赔偿金补偿金
  • 法释〔2026〕12号第十八条
  • 建设工程价款优先受偿权行使方式