Whether an assignee of a construction payment claim can assert the construction payment priority right after assignment: the four-factor review of Fa Shi [2026] No. 12 Article 19, the accessory-transfer doctrine (Civil Code Article 547), exclusions from the scope of priority, the start of the 18-month exercise period, and jurisdiction and procedure

Yes, but not automatically - the assignee may, in its own name, claim priority payment out of the proceeds of the works sold by discount or auction, and the court must decide under Fa Shi [2026] No. 12 Article 19 by weighing factors such as 'whether the works passed completion acceptance, whether the price has been settled, whether the assignment contract is valid, and whether a reasonable assignment price has been paid'. The doctrinal basis is that the priority right, as an accessory right, transfers together with the construction payment claim (Civil Code Article 547); failure to notify the debtor does not prevent the assignee suing directly (Article 546; Fa Shi [2023] No. 13 Article 48 paragraph 2). However, interest, liquidated damages, damages, and suspension and idle-cost losses within the assigned subject matter enjoy no priority (Fa Shi [2020] No. 25 Article 40 paragraph 2; Fa Shi [2026] No. 12 Article 17 paragraph 2), and the maximum 18-month exercise period still applies (Fa Shi [2020] No. 25 Article 41, start point per Fa Shi [2026] No. 12 Article 21).

Applicable Codes

  • 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第十七条、第十九条、第二十条、第二十一条、第二十三条(2026年3月17日审委会第1969次会议通过,2026年6月29日公布,自2026年6月30日起施行)https://www.court.gov.cn/fabu/xiangqing/504221.html
  • 《中华人民共和国民法典》第三百九十条、第五百四十六条、第五百四十七条、第八百零七条(主席令第45号)
  • 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第二十七条、第三十五条、第三十六条、第四十条、第四十一条、第四十二条
  • 法释〔2023〕13号《最高人民法院关于适用〈中华人民共和国民法典〉合同编通则若干问题的解释》第四十七条至第五十条
  • 法释〔2015〕10号《最高人民法院关于人民法院办理执行异议和复议案件若干问题的规定(2020修正)》第二十九条
  • 《中华人民共和国民事诉讼法》(2023修正)第三十四条;法释〔2015〕5号《民诉法解释(2022修正)》第二十八条
  • 苏高法〔2018〕《江苏省高级人民法院建设工程施工合同纠纷案件若干问题的解答》第14~20条(地方参考,期限部分已被18个月规则取代)

Scope and Positioning

After a construction payment claim (the project payment receivable) is assigned by the contractor to a third party, can the assignee, in its own name, claim the construction payment priority right out of the proceeds of the works sold by discount or auction - the substantive requirements, the doctrinal basis of accessory transfer, the excluded scope of priority, the start of the exercise period, and jurisdiction and other procedural points. Basis: Fa Shi [2026] No. 12 (SPC Interpretation (II) on construction contract disputes) Articles 17 and 19-21; Civil Code Articles 390, 546, 547 and 807; Fa Shi [2020] No. 25 (Interpretation (I)) Articles 35-42.

Core Conclusion

1. Conclusion: it can be asserted, but only after judicial review; assignment does not automatically confer it.

The priority right attaches to the construction payment claim and passes with the principal claim; but because it concerns construction workers' interests and transaction security, an assignee's claim is subject to a dedicated review standard. Fa Shi [2026] No. 12 Article 19 reads: 'Where an assignee of a construction payment claim claims priority payment out of the proceeds of the construction works sold by discount or auction, the people's court shall decide comprehensively on factors including whether the construction works have passed completion acceptance, whether the project price has been settled, whether the assignment contract is valid, and whether the assignee has paid a reasonable assignment price.' Four review factors: (1) whether the works passed completion acceptance; (2) whether the price has been settled; (3) whether the assignment contract is valid; (4) whether the assignee paid a reasonable assignment price. The wording 'comprehensively ... and other factors' indicates a weighing discretion, not a closed list of requirements.

2. The doctrinal basis of accessory transfer.

Civil Code Article 547: 'Where a creditor assigns a claim, the assignee acquires the accessory rights related to the claim, except where an accessory right belongs exclusively to the creditor itself. The assignee's acquisition of an accessory right is not affected by failure to complete transfer registration or to hand over possession.' - Hence when a construction payment claim is assigned, the priority right passes with it, without separate registration or delivery; whether the assignee actually enjoys it still requires substantive review.

Civil Code Article 546: 'Where a creditor assigns a claim without notifying the debtor, the assignment has no effect against the debtor. A notice of assignment may not be revoked, unless the assignee consents.' Without notice, Fa Shi [2023] No. 13 Article 48 paragraph 2: 'Where the assignor did not notify the debtor and the assignee sues the debtor directly for performance, and the court confirms the assignment after hearing, the assignment shall be found to take effect against the debtor when copies of the statement of claim are served. Where the debtor claims deduction from the confirmed claim of the increased costs or losses caused by the lack of notice, the court shall support it under law.' - That is, absence of notice does not bar the assignee from suing to assert the right; the assignment takes effect against the employer when copies of the statement of claim are served.

3. Scenarios where support may be given (key points)

  1. All four factors present: the claim is genuine, the works passed completion acceptance, the price has been settled, the assignment contract is valid, and the assignee paid a reasonable assignment price (Fa Shi [2026] No. 12 Article 19).
  2. The employer has confirmed the claim is genuine: Fa Shi [2023] No. 13 Article 49 paragraph 2 - 'Where the assignee took the assignment in reliance on the debtor's confirmation of the claim's existence and the debtor then refuses to perform towards the assignee on the ground the claim does not exist, the court will not support it, unless the assignee knew or should have known the claim did not exist.'
  3. The ranking is not downgraded by assignment: Fa Shi [2020] No. 25 Article 36, 'the construction payment priority right enjoyed by the contractor under Civil Code Article 807 prevails over mortgages and other claims' - the assignee steps into the contractor's position, ahead of mortgagees and other creditors.
  4. The construction contract is void but the works quality passed acceptance: the priority right is unaffected (Fa Shi [2020] No. 25 Article 35 is limited to 'the contractor that concluded the construction contract with the employer' and does not presuppose a valid contract).
  5. An employer-contractor agreement to waive or limit the priority right that harms construction workers' interests: Fa Shi [2020] No. 25 Article 42 - 'Where the employer and the contractor agree to waive or limit the construction payment priority right to the detriment of construction workers, and the employer invokes the agreement to assert that the contractor does not enjoy the priority right, the court will not support it.'
  6. The works are damaged, destroyed or expropriated: Fa Shi [2026] No. 12 Article 20 - 'Where the construction works are damaged, destroyed or expropriated, the contractor's claim to priority over the insurance proceeds, damages or compensation obtained shall be supported.' (Structurally identical to the subrogation of security interests in Civil Code Article 390.)
  7. The judgment must specify the amount and the corresponding works: Fa Shi [2026] No. 12 Article 17 paragraph 1 - 'Where the contractor requests confirmation that it enjoys the construction payment priority right, the people's court shall ascertain the amount of the price enjoying priority and the corresponding works, and state them in the operative part of the judgment.'

4. Scenarios of non-support or limitation (key points)

  1. The assigned subject includes overdue payment interest, liquidated damages or damages: Fa Shi [2020] No. 25 Article 40 paragraph 2 - 'The contractor's claim to priority over interest on overdue construction payments, liquidated damages, damages and the like will not be supported.' The assignee likewise enjoys no priority ranking; they remain ordinary claims.
  2. The assigned subject includes suspension, idle and similar losses: Fa Shi [2026] No. 12 Article 17 paragraph 2 - 'The contractor's claim to enjoy the construction payment priority right for suspension, idle and similar losses caused by the employer will not be supported.'
  3. What is assigned is a claim against the contractor (not the employer): claims of subcontractors, sub-letting transferees or actual constructors against the contractor carry no priority right in themselves, so an assignee of such claims cannot acquire one (Fa Shi [2020] No. 25 Article 35 is limited to the contractor that concluded the contract with the employer).
  4. The assignment contract is void (sham assignment, malicious collusion, evasion of enforcement, or assignment in name but profit-making holding in substance) or the assignee paid no reasonable price (gratuitous, or at a grossly unreasonable low price): the Article 19 review factors fail and support may be refused.
  5. The works have not passed completion acceptance, or quality is non-conforming and still fails after repair: the first Article 19 factor fails (also engaging Civil Code Articles 807 and 793 paragraph 2).
  6. The price has not been settled and the amount cannot be determined: the second factor fails; the claim is usually deferred until settlement.
  7. The 18-month exercise period is exceeded: Fa Shi [2020] No. 25 Article 41 - 'The contractor shall exercise the construction payment priority right within a reasonable period, not exceeding eighteen months at most, reckoned from the date the employer ought to pay the construction price.' Its nature is a peremptory period: assignment neither interrupts nor restarts it.
  8. The nature of the works makes discount sale or auction inappropriate: only an ordinary claim can be made (Civil Code Article 807, 'except where discount or auction is inappropriate given the nature of the construction works').
  9. Conflict with the rights of commercial-housing consumers who have paid most of the price: Fa Shi [2015] No. 10 Article 29 (a lawful and effective written sales contract signed before seizure, the housing bought for living purposes with no other dwelling in the buyer's name, and over fifty percent of the contractual total price paid) - consumer rights can exclude enforcement, and the assignee's priority cannot prevail over them.
  10. The contractor validly waived the priority right without harming construction workers' interests: the accessory right is extinguished and the assignee cannot acquire it (the proviso of Civil Code Article 547; the converse of Fa Shi [2020] No. 25 Article 42).

5. Start of the exercise period (full text of both paragraphs of Article 21).

'Where the construction contract stipulates the date the employer ought to pay the price, and the parties amend that date by agreement for objective reasons such as extension of time, the contractor's claim that the exercise period of the construction payment priority right runs from the amended payment date shall be supported by the people's court.'

'Where the construction contract does not stipulate, or unclearly stipulates, the date the employer ought to pay the price, but the parties clearly agree that date in a settlement agreement, the contractor's claim that the period runs from that date shall be supported by the people's court.'

That is: the start point is the amended or settlement-agreed payment date; where neither exists, the date is presumed under Fa Shi [2020] No. 25 Article 27 (the delivery date if delivered; the date of submitting final account documents if not delivered; the date of suing if neither delivered nor settled).

6. Procedural points.

Construction contract disputes are jurisdictionally treated as real-estate disputes: Civil Procedure Law Article 34 item (1) places suits over real-estate disputes with the court at the location of the property; Fa Shi [2015] No. 5 Article 28 confirms that 'rural land contracting, housing lease, construction contract and policy-based housing sales disputes are subject to real-estate jurisdiction' - so an assignee suing for priority after assignment remains bound by exclusive real-estate jurisdiction (exclusive and not variable by agreement).

Applicable Boundaries

  • Temporal effect: Fa Shi [2026] No. 12 was adopted on 17 March 2026 at the 1969th meeting of the SPC Judicial Committee, published on 29 June 2026 and effective from 30 June 2026; under its Article 23, it applies to first-instance construction contract cases newly accepted after it takes effect, cases accepted earlier following the then-current rules. Articles 19-21 are new rules and do not apply to previously accepted cases.
  • Article 19 addresses 'whether the assignee may assert'; it does not alter the foundation of the priority right (Civil Code Article 807) or its scope (Fa Shi [2020] No. 25 Article 40); scope and period issues still follow Interpretation (I).
  • The four factors are weighing factors ('and other factors' in the text), not a closed list that must all be met; in individual cases a single defect such as non-settlement or unpaid consideration may lead to denial or deferral.
  • The subject basis remains 'the contractor that concluded the construction contract with the employer'; the assignee obtains a continuation of that contractor's right and cannot break the subject limitation to acquire a priority that did not originally exist.
  • Local adjudication guidance (e.g. the Jiangsu High Court 2018 Answers) cannot serve as a national uniform basis: its 'six-month' period for the priority right conflicts with the current 18-month rule and has been superseded by higher norms; its approach that on assignment of the payment claim the priority right passes with it and whether the assignee actually enjoys it is substantively reviewed aligns with new Article 19 and has reference value only.
  • The consumer-priority rule is a special rule in conflicts between enforcement objections and the priority right; its application depends case by case on facts such as seizure timing and payment proportion.

Further Reading

  • Fa Shi [2026] No. 12 official release page (SPC): https://www.court.gov.cn/fabu/xiangqing/504221.html - key articles: Article 17 (judgment must specify amount and works; suspension and idle losses not prioritised), Article 19 (four-factor review of assignees), Article 20 (subrogation), Article 21 (start of the period), Article 23 (effective date and transition).
  • Comparison: Civil Code Article 390 (subrogation where the secured property is damaged, destroyed or expropriated), Article 546 (notice of assignment), Article 547 (accessory rights follow the principal claim), Article 807 (the priority right itself).
  • Fa Shi [2020] No. 25 Interpretation (I): Article 35 (subject), Article 36 (ranking over mortgages), Article 40 (scope and exclusions), Article 41 (18 months), Article 42 (effect of waiver/limitation agreements), Article 27 (presumed payment date).
  • Fa Shi [2023] No. 13 Interpretation on the General Provisions of the Contract Part: Articles 47-50 (debtor defences in assignment, effect of notice, confirmation of claim authenticity).
  • Fa Shi [2015] No. 10 Article 29 (commercial-housing consumer enforcement objections); Civil Procedure Law Article 34 and Fa Shi [2015] No. 5 Article 28 (exclusive real-estate jurisdiction).
  • Local guidance for reference: Jiangsu High Court, Answers on Issues Concerning Construction Contract Dispute Cases (Su Gao Fa [2018]) Articles 14-20; note the period portion is superseded by the 18-month rule.

Keywords

  • 建设工程价款优先受偿权
  • 工程款债权转让
  • 受让人
  • 法释〔2026〕12号
  • 第十九条
  • 从权利随主债权移转
  • 18个月除斥期间
  • 受偿范围