Fixing the start point of the contractor's priority right to payment of the construction price (18 months at most) after rescission of the construction contract: the payment date expressly agreed in a rescission agreement or settlement agreement; the due date of the original payment clause as a settlement and winding-up clause; the date of rescission where a payment condition becomes unattainable upon rescission; the three deemed situations under Article 27 of Fa Shi [2020] No. 25; and the distinction from the start of the retention money return period
Rescission does not change the 18-month length of the period; it only changes which day counts as 'the date the employer ought to pay the works price': where a rescission agreement or settlement agreement expressly agrees a payment date, that date governs (Article 21(2) of Fa Shi [2026] No. 12); where the original payment clause is a 'settlement and winding-up clause' still applicable after rescission, the due date of its payment term governs (Article 567 of the Civil Code); where payment was conditioned on completion, acceptance or completed settlement review and the condition fails upon rescission, the date of rescission governs (some courts take the contractor's withdrawal from the site or handover of the works; count back conservatively from the earlier date); where none applies and the works are undelivered and unsettled, the date of filing suit (or applying for arbitration) is deemed (Article 27(3) of Fa Shi [2020] No. 25). The length is fixed at 18 months at most by Article 41 of Fa Shi [2020] No. 25, and the period is a peremptory exclusion period.
Applicable Codes
- 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》(法释〔2026〕12号)第十条、第十四条、第十七条、第二十一条、第二十三条
- 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》(法释〔2020〕25号)第二十七条、第三十八条、第三十九条、第四十条、第四十一条
- 《中华人民共和国民法典》第五百六十六条、第五百六十七条、第八百零六条、第八百零七条
- 《保障中小企业款项支付条例》(国务院令第802号,2025修订)第九条、第十条、第十三条、第十七条
- 江苏高院《建设工程施工合同纠纷案件若干问题的解答》(苏高法〔2018〕)第14条(六个月旧制,已被十八个月取代,仅作参考)
- https://www.moj.gov.cn/pub/sfbgw/gwxw/xwyw/202609/t20260908_539390.html
Topic positioning
After a construction contract is rescinded (including for the employer's breach, the contractor's breach, force majeure, or by mutual agreement), from which day does the 18-month exercise period of the contractor's priority right to payment of the construction price start to run? The core bases are Articles 566, 567, 806 and 807 of the Civil Code; Articles 27 and 38 to 41 of Fa Shi [2020] No. 25; and Articles 10, 14, 17, 21 and 23 of Fa Shi [2026] No. 12.
Core conclusions
1. The length of the period is unchanged; only the start date moves
Verbatim, Article 41 of Fa Shi [2020] No. 25: 'The contractor shall exercise its priority right to payment of the construction price within a reasonable period, which shall not exceed 18 months at most, counted from the date the employer ought to pay the construction price.' The 18 months is a peremptory exclusion period (an unextendable period), to which the suspension, interruption or extension of limitation periods does not apply. Rescission neither lengthens nor shortens the period; it only determines on which day falls 'the date the employer ought to pay the works price'.
2. Why rescission pulls the start date forward
Verbatim, Article 806(3) of the Civil Code: 'After the contract is rescinded, where the quality of the completed part of the works passes, the employer shall pay the corresponding works price as agreed; where the quality does not pass, Article 793 of this Code applies by reference.' Rescission thus brings the payment obligation for the executed works to maturity; the conditions premised on completion, acceptance or completed settlement review no longer occur, and 'the due date' accordingly falls towards the date of rescission.
Article 567 of the Civil Code: 'Termination of the relationship of rights and obligations under the contract does not affect the validity of the clauses on settlement and winding-up in the contract.' Article 566(1): 'After the contract is rescinded, performance not yet rendered terminates; for performance already rendered, the parties may, in light of the performance and the nature of the contract, request restoration to the original state or other remedial measures, and have the right to claim damages.' The original payment and settlement clauses therefore continue to apply as 'settlement and winding-up clauses'; the start point is then the due date of the payment term agreed in those clauses, not the day of rescission itself.
3. Comparison table of start situations
| # | Situation | Start point (= date the employer ought to pay the works price) | Period | Basis |
|---|---|---|---|---|
| 1 | At rescission the parties expressly agree a payment date in the rescission agreement or settlement agreement | The payment date agreed in that agreement | 18 months at most | Fa Shi [2026] No. 12 Art. 21(2); Civil Code Art. 567 |
| 2 | The original payment clause is a 'settlement and winding-up clause' still applicable after rescission (e.g. monthly progress settlement, payment a set number of days after settlement review) | The due date of the payment term in that clause | 18 months at most | Civil Code Arts. 567 and 566; Fa Shi [2020] No. 25 Art. 41 |
| 3 | The original contract conditions payment on completion / acceptance / completed settlement review; the works are unfinished and the condition fails upon rescission | The date of rescission (some courts take the contractor's withdrawal from the site or handover of the works; where the dates differ, count back conservatively from the earlier date) | 18 months at most | Civil Code Art. 806(3), Arts. 566 and 567; Fa Shi [2020] No. 25 Art. 41 |
| 4 | The agreed payment date is varied by negotiation for objective reasons such as extension of time | The due payment date after the variation (not the original agreed date) | 18 months at most | Fa Shi [2026] No. 12 Art. 21(1) |
| 5 | No agreement / unclear agreement; the works actually delivered | The date of delivery | 18 months at most | Fa Shi [2020] No. 25 Art. 27(1) |
| 6 | No agreement / unclear agreement; not delivered but the final account documents have been submitted | The date of submitting the final account documents | 18 months at most | Fa Shi [2020] No. 25 Art. 27(2) |
| 7 | No agreement / unclear agreement; neither delivered nor settled (the most common situation after rescission) | The date the party files suit (where arbitration is agreed, the date of applying for arbitration) | 18 months at most | Fa Shi [2020] No. 25 Art. 27(3) |
| 8 | The contractor is a small or medium-sized enterprise; the employer is a state organ / public institution / large enterprise | The due date of the statutory or agreed payment term: for organs and public institutions, within 30 days of delivery (up to 60 days if the contract provides otherwise); for large enterprises, within 60 days of delivery; where staged or periodic settlement is agreed, from the date both parties confirm the settled amount; where payment is conditioned on passing acceptance, from the date of passing (from the expiry of the agreed acceptance period where acceptance is delayed) | 18 months at most | Regulation on Ensuring Payment to Small and Medium-sized Enterprises (State Council Decree No. 802, 2025 revision), Arts. 9 and 10 |
Verbatim, Article 27 of Fa Shi [2020] No. 25: 'Interest runs from the date the works price ought to be paid. Where the parties have not agreed, or have unclearly agreed, the time of payment, the following times are deemed the time payable: (1) where the works have been actually delivered, the date of delivery; (2) where the works have not been delivered, the date of submitting the final account documents; (3) where the works have not been delivered and the works price has not been settled, the date the party files suit.' Although the article is worded as an interest rule, it establishes precisely the order of presumptions for 'the time payable', and judicial practice likewise uses it to determine 'the date the employer ought to pay the works price'.
4. A divergence that must be stated candidly
Fa Shi [2026] No. 12 contains no separate start provision for 'rescission'; its Article 21 resolves only two situations - verbatim: 'Where the construction contract has agreed the date on which the employer ought to pay the works price, and the parties vary the payment date by negotiation for objective reasons such as an extension of the time for completion, and the contractor claims that the exercise period of the priority right to payment of the construction price runs from the varied due payment date, the people's court shall support the claim. Where the construction contract has not agreed, or has unclearly agreed, the date on which the employer ought to pay the works price, but the parties have expressly agreed that date in a settlement agreement, and the contractor claims that the period runs from that date, the people's court shall support the claim.' The start after rescission therefore remains governed by the general determination of 'the due date'; courts differ between taking 'the date of rescission' and taking 'the date of the contractor's withdrawal from the site or handover of the works'. Count back from the earliest defensible date, and do not stretch the period by arguing that 'withdrawal came later than rescission' or that 'settlement is incomplete'.
Old-regime reference: Article 14 of the Answers of the Jiangsu Higher People's Court on Construction Contract Dispute Cases (Su Gao Fa [2018]) once set a 6-month period with three starts (works completed and the settlement amount due: from the completion date or the agreed completion date; contract rescinded or performance ceased: from the actual date of rescission or cessation; acceptance passed but the payment term for amounts other than retention money not yet due: from the due date). That '6 months' has been superseded by the 18 months of Article 41 of Fa Shi [2020] No. 25 and no longer applies; its approach of 'running from the actual date of rescission' still has reference value. Article 18 of the same Answers also confirmed that claiming the priority right by filing suit or applying for arbitration is an effective mode of exercise, while mere letters asserting it are not accepted.
5. Distinguished from the start of the retention return period
Verbatim, Article 14(1) of Fa Shi [2026] No. 12: 'Where the construction contract is rescinded and the contractor claims to retain works retention money calculated on the works price it ought to receive, the people's court shall support the claim. The return period of the retention money runs from the date the contractor withdraws from the site; where the contract is rescinded after the contractor's withdrawal, it runs from the date of rescission.' Paragraph 2: 'Where the construction contract is void and the works are unfinished, and the contractor claims to retain works retention money calculated on the discounted compensation it ought to receive, the people's court shall support the claim. The return period of the retention money runs from the date the contractor withdraws from the site.' This is the start of the retention return period, not of the priority right period; the two must not be interchanged: the former anchors the withdrawal date (the rescission date where rescission comes after withdrawal), the latter anchors the date the works price ought to be paid.
6. Related substantive thresholds and judgment practice
- Precondition: the quality of the works passes (Article 38 of Fa Shi [2020] No. 25); for unfinished works, provided the quality passes, the contractor has priority over the proceeds of discounting or auctioning the part it constructed (verbatim, Article 39: 'Where the quality of an unfinished construction project passes, and the contractor claims priority payment of the price of the works it constructed out of the proceeds of discounting or auctioning the part it constructed, the people's court shall support the claim.').
- Scope: determined under the rules of the competent department of the State Council on the scope of construction prices; claims to priority for interest on overdue payment, liquidated damages or damages are not supported (Article 40).
- Suspension and idle-resource losses enjoy no priority: verbatim, Article 17(2) of Fa Shi [2026] No. 12: 'Where the contractor claims the priority right to payment of the construction price for losses from suspension, standby and the like caused by the employer, the people's court shall not support the claim.' Under paragraph 1 of the same article, the court must ascertain the amount of the works price enjoying the priority and the corresponding works and state them in the operative part of the judgment - so at filing, request confirmation of both the amount and the corresponding scope of works.
- The amount of the executed works after rescission: where a lump-sum (fixed total price) construction contract is rescinded and the parties have no agreement, and cannot agree, on the price of the executed part whose quality passes, the people's court may, by reference to the pricing standards and pricing methods published by the construction administrative authority at the place of the works at the time of contract conclusion, or the relevant norms of the construction sector, determine the proportion of the price of the executed part to the price of the whole works, and multiply the fixed total price agreed in the contract by that proportion to determine the price of the executed part (Article 10 of Fa Shi [2026] No. 12). Determining the amount and determining the start date are two independent issues.
- Mode of exercise and substantive basis: Article 807 of the Civil Code - after notice and default in payment, the contractor may, except where the nature of the works makes discount or auction inappropriate, agree a discount with the employer or request the people's court to auction under law, and take priority payment out of the proceeds.
Applicability limits
- Applies only to the contractor's priority right to payment of the construction price in construction contract disputes; disputes over the start point do not affect separate claims to the principal of the works price and overdue interest.
- The 18 months is the maximum and a peremptory exclusion period; the right extinguishes on expiry. Once the start point is fixed, the period cannot be reopened by arguing 'settlement is incomplete' or 'audit incomplete'.
- The variation in Article 21(1) is confined to 'objective reasons such as extension of the time for completion' and requires negotiation; unilateral notice, or the employer's unjustified unilateral dragging, is not a negotiated variation and cannot postpone the start point. Paragraph 2 confines the vehicle to a 'settlement agreement' with an 'express agreement' of the date; a vague mention of payment arrangements in meeting minutes or reconciliation letters, without a clear date, may not qualify.
- Where the contract is void and the works are unfinished, no 'rescission' occurs; the amount and the payment time follow the discounted-compensation rules for void contracts (by reference to the agreed price of the works, including the time of payment), and the reasoning on the start after rescission cannot be applied directly.
- The SME payment-period rules (Articles 9 and 10 of the Regulation on Ensuring Payment to Small and Medium-sized Enterprises) settle only 'when payment is due' and do not change the 18-month length; that Regulation also provides that organs, public institutions and large state-owned enterprises may not compel use of audit results as the settlement basis (Article 12); that apart from the four types of security (tender, performance, works quality, migrant workers' wages) no other security may be collected and security may not be limited to cash (Article 13); and that late payment carries overdue interest (Article 17: the agreed rate shall not be lower than the 1-year LPR at contract conclusion; failing agreement, 0.05% per day).
- Time-of-effect boundary: verbatim, Article 23 of Fa Shi [2026] No. 12: 'This Interpretation takes effect on 30 June 2026. For construction contract cases of first instance newly accepted by people's courts after this Interpretation takes effect, this Interpretation applies. Where SPC judicial interpretations previously issued are inconsistent with this Interpretation, this Interpretation prevails.' First-instance cases newly accepted after 30 June 2026 therefore apply the new rules of Articles 21, 14 and 17; cases accepted earlier are still determined under Article 41 and Article 27 of Fa Shi [2020] No. 25.
Further reading
- Fa Shi [2026] No. 12, SPC Interpretation (II) on Construction Contract Disputes: Article 10 (price of the executed part after rescission of lump-sum contracts), Article 14 (retention base and start of the return period), Article 17 (stating the priority amount in the operative part; no priority for suspension and standby losses), Article 21 (two start situations), Article 23 (time of effect and old-new interface).
- Fa Shi [2020] No. 25, SPC Interpretation (I) on Construction Contract Disputes: Article 27 (three presumed situations of the time payable), Articles 38 to 40 (quality passing; unfinished works; scope of priority), Article 41 (18 months).
- Civil Code: Articles 566 and 567 (consequences of rescission; settlement and winding-up clauses), Article 806 (statutory right of rescission and payment of the price after rescission), Article 807 (substantive basis of the priority right).
- Regulation on Ensuring Payment to Small and Medium-sized Enterprises (State Council Decree No. 802, 2025 revision): Articles 8 to 15 and Article 17.
- Answers of the Jiangsu Higher People's Court on Construction Contract Dispute Cases (Su Gao Fa [2018]), Part IV, Articles 14 to 20 (the old 6-month regime, mode of exercise, effect of waiver, assignment of claims - old-regime reference only).
- Official release page (for verifying the latest judicial documents and policy updates): https://www.moj.gov.cn/pub/sfbgw/gwxw/202609/t20260908_539390.html
- Related cards: general rules on the start point of the priority right (Article 21 plus the three situations of Article 27); the rule of period-by-period start under staged payment; the start of the retention return period after rescission; the settlement rules after rescission.
Keywords
- 建设工程价款优先受偿权
- 合同解除
- 起算时间
- 十八个月
- 应当给付工程价款之日
- 法释〔2026〕12号第二十一条
- 结算和清理条款
- 承包人退场之日