Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-29

Settlement rules for the construction contract price after contract termination (four scenario rules + three material states + lump-sum contract pricing + quality threshold)

Termination ends only the unperformed part; the performed part must be settled, and conformity of the completed works is the precondition for payment (if repaired to conformity the repair cost is borne; if still nonconforming after repair, no contract price is payable). Termination by agreement is settled per the agreement; termination for force majeure pays seven categories of costs with no liquidated damages or claims; on termination for contractor breach the employer may suspend payment and verify losses, and quality warranty liability is not exempted; on termination for employer breach liquidated damages are additionally payable and the retention money refunded. On-site materials are allocated across three states. For termination of a lump-sum contract with no agreement: contractor breach — contract lump sum minus the price of the unperformed works; employer breach — the completed-work price is computed per contemporaneous pricing bases (GB/T 51262-2017 §5.10.7).

Topic Positioning

Overview of the settlement rules for the construction contract price after termination of the construction contract (by agreement / force majeure / employer breach / contractor breach).

Core Conclusions

Termination ends only the unperformed part; the performed part must be settled, and conformity is the precondition for payment. Four scenario rules: ① termination by agreement — settle per the agreement (§10.4.1); ② force majeure termination — pay seven items including the completed works, ordered-and-delivered materials, return and contract-cancellation charges, and evacuation/dismissal costs, with no liquidated damages or claims; after payment the completed works and materials belong to the employer (§10.4.2); ③ contractor-breach termination — the employer may suspend payment and verify the completed-work price + material payments + loss claims, quality warranty liability not being exempted (§10.4.3); ④ employer-breach termination — pay per §10.4.2 and refund the retention money, plus liquidated damages and losses (§10.4.4). Materials in three states: physical works belong to the employer; ordered and delivered materials belong to the employer after payment; materials neither paid for nor delivered belong to the contractor. Lump-sum contracts with no agreement upon termination (GB/T 51262-2017 §5.10.7): contractor breach — contract lump sum minus the price of the unperformed works; employer breach — the completed-work price is computed per contemporaneous pricing bases. Nonconforming quality: repaired to conformity — the repair cost is paid; still nonconforming after repair — no contract price is paid (Judicial Interpretation I on Construction Contract Disputes, Article 10).

Applicable Boundaries

Applies to settlement after termination, excluding the normal final account; attribution of responsibility is determined by the client / judicial organs; failing negotiation, Chapter 11 dispute resolution applies.

Further Reading

GB/T 50500-2024 Clauses 10.1.9, 10.4.1–10.4.4, 11.1.1; GB/T 51262-2017 Section 5.10; Civil Code Articles 566/567/806 and Article 10 of Judicial Interpretation I on Construction Contract Disputes.

Keywords

Cited By