retention money
Concept Guide
Concept
In Chinese construction contracting, retention money is the amount an employer withholds from payments due to the contractor as security for the contractor's obligation to remedy defects during the defects liability period. It belongs to the same family of project securities as the performance security and the bid security, but its scope is narrower: it secures post-completion defect rectification only, not time, progress or the whole of the contract obligations.
How the mechanism works. First, withholding and cap: the employer normally deducts a percentage from each interim payment, and the applicable Chinese regulation caps the total at 3% of the settled contract price, so any agreed figure above that ceiling is not enforceable. Second, alternative form: the contractor may substitute a bank guarantee, and the employer cannot refuse it, moving the arrangement from tied-up cash to committed credit lines. Third, release and deduction: if a defect appears during the defects liability period and the contractor fails to remedy it within the agreed time, the employer may engage others and deduct the cost from the retention; once the period expires with no outstanding defects, the balance must be returned promptly.
A distinction worth keeping. The defects liability period is not the statutory warranty period. The former is the lifespan of the retention, agreed in the contract and usually relatively short; the latter follows quality regulations, sets minimum warranty terms by discipline, and runs longer but carries no retention link. Pricing and settlement disputes often arise from confusing the two, or from withholding retention and performance security at the same time.
FIDIC Mapping
Corresponding term. FIDIC (Red Book / Yellow Book, 2017) uses Retention Money: defined in Sub-Clause 1.1.69 of the Red Book (1.1.70 in the Yellow Book), withheld under Sub-Clause 14.3 and released under Sub-Clause 14.9. The correct English is retention money; a Chinese-style rendering as a separate reimbursement "fund" has no counterpart among the FIDIC payment clauses and will confuse readers.
Similarities and differences. Both systems deduct a percentage from interim payments to secure defect rectification. Differences: the percentage and the cap come from the Contract Data under FIDIC, while China imposes a statutory ceiling; release under Sub-Clause 14.9 is in two halves — half after the Taking-Over Certificate, the remainder after the latest expiry of the Defects Notification Periods — whereas Chinese practice normally releases once, at the end of the defects liability period; and FIDIC expressly contemplates retention security given by a financial institution, matching the Chinese bank guarantee option although the documentary basis differs.
Usage warning. When reading FIDIC contracts or pricing overseas work, do not carry over the domestic ceiling or the domestic defects liability period: check the Contract Data for the retention percentage and limit. Do not equate the Defects Notification Period with the Chinese warranty period; the former triggers final release of the retention, the latter sets statutory minimum warranty terms. Because Sub-Clause 14.9 releases half of the retention early, the cash-flow impact is smaller than a full withholding until the end of the period — adjust financing cost estimates accordingly.
| Chinese Term | English Term | FIDIC Term | Relation | Notes |
|---|---|---|---|---|
| 质量保证金 | retention money | Retention Money(红皮书定义 1.1.69/黄皮书 1.1.70;扣留 14.3、返还 14.9) | identical | 功能对等:均逐期扣留以担保缺陷修复。差异在比例与封顶由合同数据约定而非法定 3% 上限,且 FIDIC 两段释放保留金。 |
| 缺陷责任期 | defects liability period | Defects Notification Period (release of the second half under Sub-Clause 14.9) | adjacent | FIDIC 缺陷通知期最迟届满触发保留金后一半释放;中国缺陷责任期与保修期分离,保修期为法定最低年限,二者不可互替。 |
Updated 2026-09-13
- 01
Whether the quality retention money (3% retention) can be brought within the contractor's priority right to payment out of the construction project price, and the accounting method of back-computing, from the defects liability period plus the return-verification procedure period, whether the 18-month preclusive period has expired
Retention money is 'withheld from the works price payable' and forms par…
《民法典》第八百零七条法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第三十六条、第三十八条、第四十条、第四十一条、第四十五条法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第十四条、第十七条、第二十一条、第二十三条2026-10-31 - 02
After termination of the construction contract, the boundary of the payment defence for parts of the works the employer has actually taken over and put to use (without completion acceptance): a blanket refusal to pay on the ground of 'not accepted' is barred; refusal is allowed only 'to the corresponding extent' for undelivered parts and for foundation and main structure defects; repair costs require prior notice of repair
No blanket refusal. Termination only ends the unperformed part; for comp…
法释〔2020〕25号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)第九条、第十四条、第二十六条、第二十七条法释〔2026〕12号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)第十条、第十四条、第十六条、第二十三条(2026年6月30日施行)中华人民共和国民法典(主席令第45号)第五百二十六条、第七百九十三条、第七百九十九条、第八百零六条2026-10-29 - 03
Settlement rules for the construction contract price after contract termination (four scenario rules + three material states + lump-sum contract pricing + quality threshold)
Termination ends only the unperformed part; the performed part must be s…
2026-10-29 - 04
The base for computing works retention money under a fixed lump-sum construction contract: the total settled project price (including contractually adjustable items and excluding unused provisional sums) rather than the signed contract price, capped at 3%; on rescission or void incomplete works the base shifts to the price due to the contractor or the discounted compensation due
For a fixed lump-sum contract the retention money base is 'the total set…
建质〔2017〕138号《建设工程质量保证金管理办法》第三、六、七、十、十一条GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.3.1、8.3.5、10.3.2、10.3.15、10.5.1条GF-2017-0201《建设工程施工合同(示范文本)》第15.2.1、15.3、15.3.2条(2017-10-01施行)https://www.mohurd.gov.cn/gongkai/zc/wjk/art/2017/art_17339_233757.html2026-10-29 - 05
Rules for the start point of the defects liability period (the period secured by retention money): the statutory deemed start 90 days after submission of the completion-acceptance report where the employer delays or fails to organise completion acceptance, and a comparison of the start points for normal acceptance, contractor-caused delay, premature use of the works without taking-over, and early acceptance of units or sections
Where for reasons attributable to the employer the works cannot undergo…
建质〔2017〕138号《建设工程质量保证金管理办法》(2017修订)第二条、第七条、第八条、第十一条最高人民法院法释〔2020〕25号《关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第九条、第十七条建市〔2020〕96号《建设项目工程总承包合同(示范文本)》GF-2020-0216 通用合同条件第11.2款2026-10-29 - 06
The duration cap of the defects liability period (generally 1 year, no more than 2 years, i.e. 24 months) against the start events for each situation: taking-over, taking-over delayed by the contractor or by the employer, prior taking-over of unit works, premature use with transfer of possession, extension for defect repair, and the three-way distinction from the retention money return period and the warranty period
The defects liability period is capped at 24 months (2 years): Article 2…
《建设工程质量保证金管理办法》(建质〔2017〕138号,2017修订)第二条、第三条、第七条、第八条《建设工程施工合同(示范文本)》GF-2017-0201 通用合同条款 14.4、15.1、15.2、15.3《建设项目工程总承包合同(示范文本)》GF-2020-0216 通用合同条件 11.1、11.22026-10-29 - 07
The boundary between the defects liability period (secured by retention money) and the warranty period: differences of length and start, whether funds are held, and refunding retention does not release the warranty duty
Retention money secures only the defects liability period (normally 1 ye…
建质〔2017〕138号《建设工程质量保证金管理办法》第二条、第八条、第九条、第十条、第十一条《建设工程质量管理条例》(2017修订)第四十条、第四十一条GB 55032-2022 · General Code for Construction Quality Control of Building and Municipal Engineering 第5.0.2条2026-10-18 - 08
Overview of engineering project procurement and supply chain management: the eight-step procurement procedure, six management main lines, and compliance red lines
The procurement management master line: control demand by plan, control…
GB/T 50358-2017 建设项目工程总承包管理规范GB/T 50430-2017 工程建设施工企业质量管理规范GB/T 50326-2017 建设工程项目管理规范2026-09-25 - 09
The full workflow of quality retention money retention and return (cap, retention methods, defects liability period commencement, and return procedure)
The retention money is reserved from payable amounts, capped at 3% of th…
建质〔2017〕138号 建设工程质量保证金管理办法GB/T 50500-2024 建设工程工程量清单计价标准 第10.5节GB/T 50319-2013 建设工程监理规范 第5.3.1条2026-09-25 - 10
FIDIC Defects Notification Period vs the domestic "defect liability period": same name, different regime - mechanism skeleton and the domestic habits to shed
The domestic defect liability period and FIDIC DNP are "terminological c…
FIDIC Conditions of Contract for Construction (Red Book), 2nd Edition 2017: Sub-Clause 1.1.27, Clause 11, Sub-Clause 14.9GB/T 50358-2017 建设项目工程总承包管理规范 第2.0.32条建质〔2017〕138号 建设工程质量保证金管理办法 第二条2026-09-25 - 11
Determining the progress-payment ratio and the payment sign-off procedure (GB/T 50500-2024 §9.1/§9.4 + GB/T 50319-2013 §5.3.1)
The ratio is set by three layers — "contract agreement first -> national…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50319-2013 建设工程监理规范2026-09-25 - 12
Full process of construction payment: advance payment, safety-measures fee, progress payment, interim settlement by construction stage, final account, retention money and final settlement (GB/T 50500-2024 Chapters 9-10)
Payment along the timeline in six segments: advance payment (for works w…
GB/T 50500-2024 建设工程工程量清单计价标准(第9.1~9.4、10.1~10.3、10.5节)财建〔2004〕369号 建设工程价款结算暂行办法建质〔2017〕138号 建设工程质量保证金管理办法2026-09-25 - 13
Calculating guarantee fees, retention money occupation costs, and financing costs for construction projects
Guarantee (letter of guarantee) fee = guaranteed amount × rate (referenc…
T/SZCA 5-2022 洁净工程项目定额 第0.3.6条建质〔2017〕138号 第5、7条GB/T 50500-2024 第10.5.1条2026-09-25 - 14
Setting rules and compliance red lines for the performance security and the quality retention (retention money): 10%/3% caps, mutual exclusivity before completion, and the boundary allowing coexistence at final settlement
The performance security guarantees contract performance, capped at 10%…
2026-09-25 - 15
Return of the quality retention money: timing, procedure, and the final account interface (Jian Zhi [2017] No. 138 + GB/T 50500-2024 §10.5)
The retention money is returned when the defect liability period (genera…
建质〔2017〕138号 建设工程质量保证金管理办法GB/T 50500-2024 建设工程工程量清单计价标准 第10.5节2026-09-25 - 16
The FIDIC Performance Certificate (Red Book Clauses 11.9/11.10) mapped against the domestic completion acceptance - defect liability period - final settlement system: correspondences and differences
Performance Certificate is not Performance Bond. FIDIC Red Book 11.9: th…
FIDIC 红皮书 1999 第 11.9~11.10 条FIDIC 红皮书 2017 第 2 版第 11.9~11.10 条GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 10.5.5、10.5.8 条2026-09-25