Calculating guarantee fees, retention money occupation costs, and financing costs for construction projects

Guarantee (letter of guarantee) fee = guaranteed amount × rate (reference 1‰–5‰, 4‰ recommended; absent agreement the guaranteed amount may take 15% of the total contract price); retention occupation cost = retention amount × occupation time × capital cost rate; capital cost = financing cost (one-off) + capital occupation cost. Red lines: performance security ≤10% of the awarded contract amount; quality (retention) money ≤3% of the total settled project price (replaceable by a bank guarantee; where performance security has been provided, no further retention before completion); overdue interest absent agreement at 0.05‰ per day. Where a guarantee is allowed to replace cash, prefer the guarantee.

Applicable Codes

  • T/SZCA 5-2022 洁净工程项目定额 第0.3.6条
  • 建质〔2017〕138号 第5、7条
  • GB/T 50500-2024 第10.5.1条
  • HG/T 20705-2009 第16.1.1条
  • 保障中小企业款项支付条例 第15条
  • T/YJXB 0001-2023 第4.0.13、4.0.14条

Topic Positioning

The three elements of construction project capital costs — guarantee fees, retention occupation costs, and financing costs (discount fees, overdue interest): their calculation formulas and statutory caps, plus the decision logic of replacing cash retention with guarantees.

Core Conclusions

  • Guarantee fee = guaranteed amount × rate. Reference rate range 1‰–5‰, 4‰ recommended; the guaranteed amount follows the tender documents — absent agreement it may take 15% of the total price of the contracted works (this basis comes from an association standard, see Applicable Boundaries).
  • Retention occupation cost = retention amount × occupation time (years) × capital cost rate (the enterprise's internal settlement rate or weighted average financing cost) — the opportunity cost of paying retention in cash.
  • Capital cost = financing cost (one-off fees: loan handling fees, issuance fees, discount fees, etc.) + capital occupation cost (interest, dividends, and other returns).
  • Bill discount fee = face value × annual discount rate × discount period (years).
  • Overdue interest: the agreed rate must not be below the 1-year LPR at contract conclusion; absent agreement, 0.05‰ per day (≈18.25% annualized).
  • Red-line caps: performance security ≤10% of the awarded contract amount; retention money ≤3% of the total settled project price, replaceable by a bank guarantee; where the contractor has provided performance security, no further retention should be withheld before completion, and where surety bonds/insurance are used, none may be withheld.
  • Decision: a 4‰ guarantee fee is usually far below the cash occupation cost computed at the annualized capital cost — where a guarantee is allowed to replace cash, prefer the guarantee, but include the cost of occupying the credit line in the overall decision.

Applicable Boundaries

  • The 4‰ rate is the recommended value of the cleanroom engineering sector quota; other sectors follow the contract and tender documents; the 15% guaranteed amount basis is that standard's basis — the statutory 10% cap on performance security must also be satisfied.
  • The capital cost rate has no unified national rule; take the enterprise's actual financing cost — different values significantly change the conclusion.
  • The overdue interest clause applies to late payment by government agencies, public institutions, and large enterprises to SMEs.
  • Suspension scenarios additionally involve the increased financing costs of delayed payment and delayed retention return, to be included.

Further Reading

  • Guarantee rate and guaranteed amount basis: T/SZCA 5-2022, Quota for Cleanroom Engineering Projects, Clause 0.3.6
  • Retention cap and guarantee replacement: Jianzhi [2017] No. 138, Articles 5, 7; GB/T 50500-2024, Standard for Valuation of Construction Works with Bills of Quantities, Clause 10.5.1
  • Capital cost definition: HG/T 20705-2009, Code for Project Management of Petrochemical Industry Construction Projects, Clause 16.1.1
  • Overdue interest: State Council Order No. 728, Regulation on Ensuring Payment to SMEs, Article 15
  • Suspension financing costs: T/YJXB 0001-2023, Standard for Calculating Contractor's Costs upon Work Suspension of Construction Works, Clauses 4.0.13, 4.0.14