Interest during construction: cost components and accounting destination - which financing charges (handling fees, management fees, commitment fees, on-lending fees, guarantee fees, credit insurance) merge in, the conversion basis for foreign-currency loans, the conditions for compound interest, and the basis for capitalising into the fixed asset original value (the depreciation base after commissioning)
Interest during construction covers not only loan interest but also financing charges - financial institution handling fees, management fees, commitment fees, on-lending fees, guarantee fees and credit insurance (SJG 86-2020 clause 4.6.1: normally computed separately and included in construction-period interest; GB/T 51095-2015 clause 4.2.20 to the same effect). Where interest during the construction period is only accrued and unpaid, or is paid out of fresh borrowings, it compounds (DB37/T 5130-2018 clause 4.2.18). It is capitalised into the value of the asset before the asset is delivered for use or, if in use, before the final account is concluded, forming the depreciation base after commissioning (Accounting Standards for Enterprises Article 30; EIT Implementation Regulation Article 37; Guo Fa [1985] No. 63 Article 11).
Applicable Codes
- GB/T 51095-2015 建设工程造价咨询规范 4.2.20
- T/ZBD 100.2-2022 建设项目投资估算编制作业指引 5.6.3
- SJG 86-2020 建筑和市政工程估算编制规程 4.6.1
- TB 10811-2024 铁路基本建设工程设计概(预)算费用定额 2.15.2
- JTG 3830-2018 公路工程建设项目概算预算编制办法 3.5.1
- DB37/T 5130-2018 建设工程造价咨询服务规范 4.2.18
- 中国人民建设银行基本建设贷款办法 第二十二条
- 企业会计准则(财政部令第5号)第三十条
- 企业所得税法实施条例(国务院令第512号)第三十七条
- 国营企业固定资产折旧试行条例(国发〔1985〕63号)第十一条
Positioning
The boundary and accounting destination of interest during construction: which financing charges merge into it, when compound interest applies, and why construction-period interest enters the fixed asset original value and becomes the depreciation base after commissioning.
Core conclusions
1. Composition: loan interest + financing charges
- GB/T 51095-2015 (cost consultancy code), clause 4.2.20: "Interest during construction shall be estimated from the funding plan and investment programme for the construction period and the corresponding rates, and shall include the financial institution's handling fees, management fees etc."
- T/ZBD 100.2-2022 (investment estimate guide), clause 5.6.3: "In computing interest on foreign loans or other financing, the annual rate shall comprehensively allow for the handling fees, management fees and commitment fees charged to the borrower under the loan agreement, and the on-lending fees, guarantee fees and management fees charged by the domestic agent to the borrower."
- SJG 86-2020 (estimating rules), clause 4.6.1: "Interest during construction shall be computed separately by funding source, construction duration and loan rate." "Financing charges arising in certain debt financing during the construction period - handling fees, commitment fees, management fees, credit insurance etc. - shall normally be computed separately and included in the construction-period interest."
- Foreign-currency loans follow the dedicated formula (TB 10811-2024 clause 2.15.2): "construction-period interest on foreign investment loans = sum over years of (cumulative principal to the first half-year + that year's loan x conversion factor) x loan rate x current exchange rate", using the construction period, rate and conversion factor fixed in the appraisal report.
- Scope (JTG 3830-2018 clause 3.5.1): "construction-period loan interest is the loan interest accrued in the construction period on the loan portion used by the project, including interest on loans from financial institutions, construction bonds and foreign-exchange loans." Equity funds put in bear no construction-period interest.
2. When compound interest applies
- DB37/T 5130-2018 clause 4.2.18, main estimating principles: "equity funds shall comply with state or industry rules; construction-period interest is computed by funding source and rate; where interest during the construction period is only accrued and unpaid, or is paid with borrowings, it compounds."
- The People's Construction Bank capital-construction loan rules, Article 22: "A new project that cannot pay interest before commissioning may pay after commissioning, with compound interest, interest settlement on 20 September each year; interest on renovation and expansion projects, and on new projects after commissioning, is in principle paid from the borrower's own funds, settled on the 20th of the last month of each quarter." "A borrowing unit with own funds that fails to pay interest on time may have it deducted from its deposit account per the loan contract. Loans enjoying fiscal interest discounts are collected first and discounted afterwards."
- Summary: interest not actually paid during construction (accrued only, or paid by borrowing) rolls into principal and compounds - next year's base includes the accrued interest; interest actually paid each period from own funds does not compound, the base being only the principal balance.
3. Capitalisation: into the original value, becoming the depreciation base
- Accounting Standards for Enterprises (MoF Decree No. 5), Article 30: "Fixed assets shall be recorded at actual cost on acquisition. Borrowing interest and related costs of fixed assets incurred before the asset is delivered for use, or delivered but before the final account is concluded, and exchange differences on foreign-currency borrowings, enter the value of the fixed asset; borrowing interest and related costs and exchange differences after that point enter current profit or loss."
- EIT Implementation Regulation (State Council Decree No. 512), Article 37: "Reasonable borrowing costs of an enterprise in production or business that need no capitalisation are deductible. Where an enterprise borrows to acquire or build a fixed asset, an intangible asset, or inventory needing over 12 months of construction to reach the intended saleable state, reasonable borrowing costs during the acquisition or construction period are capital expenditure entering the cost of the asset and are deducted under this Regulation."
- Provisional Regulations on Depreciation of Fixed Assets of State-owned Enterprises (Guo Fa [1985] No. 63), Article 11: "Depreciation is based on the original value of the fixed asset." "For fixed assets purchased or built with capital-construction appropriations or loans, the original value is the value stated in the schedule of property delivered by the construction unit."
- Full chain: construction-period interest (with financing charges) - capitalised into the original value - depreciated on that value; borrowing interest after the final account (delivery) goes to current profit or loss (expensed), never back into the original value.
Applicable boundaries
- The capitalisation cut-off is "not yet delivered for use, or in use but before the final account"; borrowing interest and exchange differences after that can only hit current profit or loss.
- MoF Decree No. 5 is the basic standard; current practice adds the dedicated standard CAS 17 Borrowing Costs on capitalisation conditions (asset expenditure incurred, borrowing costs incurred, construction started) and the capitalisation period - apply the current standards and tax rules in force for the project; this card cites the principle.
- Whether compounding applies depends on actual interest payment and the loan contract - never assume it; where the contract fixes another interest basis, the contract governs (GB/T 51095-2015 clause 4.2.20).
- Financing charges are "normally computed separately and included in construction-period interest" - avoid double-listing with other cost headings in financing-cost analysis.
- For income tax deduction, the capitalised part deducts in instalments through depreciation and the expensed part currently; no double counting.
Further reading
- DB37/T 5130-2018 clause 4.2.18; GB/T 51095-2015 clause 4.2.20; T/ZBD 100.2-2022 clause 5.6.3; SJG 86-2020 clause 4.6.1; TB 10811-2024 clauses 2.15.1-2.15.2; JTG 3830-2018 clause 3.5.1.
- Accounting Standards for Enterprises (Decree No. 5) Article 30; EIT Implementation Regulation (Decree No. 512) Article 37; Guo Fa [1985] No. 63 Article 11.
- Statutory texts verifiable on the national law database (flk.npc.gov.cn) and MoF / State Council sites; the published texts govern.
Keywords
- 建设期利息
- 融资费用
- 承诺费
- 管理费
- 复利计息
- 利息资本化
- 固定资产原值
- 折旧基数