Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Dual-basis attribution of project capital costs into business analysis (period expenses in financial accounting vs explicit disclosure in management analysis)

Project capital costs are handled on a dual basis: externally, the financial statements follow Article 49 of the Accounting Standards for Business Enterprises — finance costs are period expenses charged directly to current profit or loss, not into project production costs; internally, business analysis must attribute capital costs explicitly by project (one-off financing fees + capital occupation fees + deposit occupation + overdue interest received/paid), listing a separate "capital cost" line on the project income statement (after gross profit, before taxes). Attribution formula: project capital cost = Σ(month-end occupation × internal monthly occupation rate) + one-off financing fees − overdue interest recovered; month-end occupation = max(0, −cumulative net cash flow); the internal rate is set uniformly by the company's financial system; keep the three synchronizations of physical progress, output value statistics, and cost collection.

Applicable Codes

  • 企业会计准则(财政部令第5号)第四十九条
  • HG/T 20705-2009 石油和化学工业工程建设项目管理规范 第16.1.1条
  • GB/T 50326-2017 建设工程项目管理规范 第11.4.3、11.5.1条
  • 保障中小企业款项支付条例(第728号令)第十五条
  • GB/T 50500-2024 建设工程工程量清单计价标准 第9.4.12条

Topic Positioning

This card covers how construction project capital costs (interest, internal occupation fees, retention/guarantee occupation, overdue interest) are attributed into business analysis: the split between financial accounting and the management basis, the composition of capital costs, the monthly attribution formula, and the placement on the project income statement. It is the upstream attribution link of the advance-funding measurement and cash flow forecast cards.

Core Conclusions

① Dual basis: external statements follow Article 49 of the Accounting Standards for Business Enterprises — finance costs are period expenses charged directly to current profit or loss, not into project production costs; internal business analysis must attribute explicitly by project, otherwise advance-funded projects show "book profit, actual loss". ② Composition (HG/T 20705-2009, Clause 16.1.1): capital cost = financing cost (one-off fees: loan handling fees, guarantee fees, discount fees, etc.) + capital occupation cost (interest, occupation fees, dividends — including the time value and risk premium). ③ Attribution formula: project capital cost = Σ(month-end occupation × internal monthly occupation rate) + one-off financing fees − overdue interest recovered. Month-end occupation = max(0, −cumulative net cash flow), taken from the cash flow forecast; the internal rate is set uniformly by the company's financial system (e.g., LPR or the weighted financing cost) and may not be taken arbitrarily; for quick estimates use weighted occupation period × average occupation × monthly rate. ④ Presentation: list a separate "capital cost" line on the project income statement, placed after project gross profit and before taxes, separated from headquarters management fees. ⑤ Attribution keeps the three synchronizations of physical progress, output value statistics, and cost collection (GB/T 50326-2017, Clause 11.4.3), and the cost analysis bases include the cost plan, accounting records, and the three accounting data sets (Clause 11.5.1).

Applicable Boundaries

Applies to project-level management accounting/business analysis of construction enterprises; does not change the external statutory statement basis; the internal occupation rate must be unified by the system; overdue interest claimable from the employer under Article 15 of the Regulation on Ensuring Payment to SMEs may offset capital costs.

Further Reading

Accounting Standards for Business Enterprises, Article 49 (period expenses); HG/T 20705-2009 Clause 16.1.1 (definition of capital cost); GB/T 50326-2017 Clauses 11.4.3, 11.5.1; Regulation on Ensuring Payment to SMEs, Article 15 (overdue interest); GB/T 50500-2024 Clause 9.4.12 (progress payment claims). Use in conjunction with the advance-funding peak measurement and cash flow forecast preparation cards.