Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Comparing procurement payment terms: when unit prices are equal, rank options by payment present value and capital occupation cost

When material unit prices are equal and only payment terms differ, discount each option's payment schedule at the enterprise's internal monthly capital occupation rate: payment present value = Σ(payment amount ÷ (1 + monthly rate)^months); for quick estimates, capital occupation cost ≈ amount × occupied days ÷ 360 × annualized capital cost rate — the lower present value/occupation cost wins: the longer the credit and the smaller the prepayment, the better; the choice must add four corrections: the capital cost rate value, current cash flow, the hidden risks of overly long credit, and the input tax deduction timing.

Applicable Codes

  • GB/T 50430-2017 第8.2.1条、第8.2.2条
  • GB/T 50326-2017 第6.2.1条
  • GB/T 50358-2017 第6.3.3条
  • T/SCIA 002-2020 第7.3.1条
  • DB11/T 382-2017 第4.3.1条

Topic Positioning

How to rank options in procurement comparison when material unit prices are equal and only payment terms differ (prepayment ratio, credit length) — essentially comparing the time value of money; a reusable general calculation method in procurement decisions.

Core Conclusions

Three-step method: ① list each option's payments (amount × payment time) as a cash flow schedule; ② discount at the enterprise's internal monthly capital occupation rate: payment present value = Σ(payment ÷ (1 + monthly rate)^months); ③ compare present values — lower wins. Rule: the longer the credit and the smaller the prepayment, the lower the present value — with equal unit prices, a credit option beats a prepayment option. Quick estimate: capital occupation cost ≈ amount × occupied days ÷ 360 × annualized capital cost rate, directly comparable with unit price discounts and interest subsidies. Four corrections: ① the capital cost rate value is the key sensitivity — unify the internal rate per the enterprise's financial system and test multiple tiers; ② when current cash flow is tight, credit is worth more than its nominal discounted value (refer to the advance-funding peak = the lowest point of the cumulative monthly net cash flow); ③ overly long credit, or a rising market, may let the supplier claw back through quality, delivery priority, or passed-through increases — the price is not truly locked; ④ input VAT deduction follows the date the special invoice is obtained — delayed invoices must net out the deduction loss.

Applicable Boundaries

Applies only where unit prices are equal or total prices comparable; where they differ, first convert the price difference (cash discounts, interest subsidies, market-following prices) before comparing. Conclusions are highly sensitive to the capital cost rate — unify the internal basis. Do not mechanically extrapolate "longer credit is always better" — weigh supplier risk and price-locking ability; payment terms should align with the project funds utilization plan and implementation schedule.

Further Reading

Procurement plan preparation and content: GB/T 50430-2017 Clause 8.2.1, GB/T 50326-2017 Clause 6.2.1; supplier evaluation and selection: GB/T 50430-2017 Clause 8.2.2, T/SCIA 002-2020 Clause 7.3.1; EPC procurement execution plan: GB/T 50358-2017 Clause 6.3.3; supervisor review of material procurement and supply plans: DB11/T 382-2017 Clause 4.3.1.

Keywords

  • 付款条件比选
  • 付款现值
  • 资金占用成本
  • 账期
  • 折现
  • 采购方案比选
  • 资金时间价值
  • 预付比例

Cited By