Calculating and judging the project financial internal rate of return (FIRR), financial net present value (FNPV), and payback period
FIRR is the discount rate at which the cumulative present value of net cash flows over the project calculation period equals zero; FIRR ≥ the benchmark rate means the project is viable; FNPV discounts each period's net cash flow at the benchmark rate and sums them — >0 is viable and larger is better; for hand calculation of IRR use trial-and-error linear interpolation (interval preferably ≤2%); the payback period comes in static and dynamic forms — the shorter it is, the stronger the risk resistance. Measurement of the return on contractor advance financing (deferred payment) must distinguish the all-investment basis from the equity/own-funds basis.
Applicable Codes
- RISN-TG 029-2017 建筑光伏系统技术导则 附录A.2.4
- 发改投资〔2006〕1325号 建设项目经济评价方法与参数 第五条、第十一条
- GB 50288-99 灌溉与排水工程设计规范 4.4.2
- T/CECA 20029-2023 城市河道水环境综合整治设计导则 13.3.5
Topic Positioning
This card covers the three core indicators of project fund profitability — the financial internal rate of return (FIRR), financial net present value (FNPV), and payback period (static/dynamic): definitions, formulas, hand-calculation methods, and viability criteria — for project economic evaluation and contractors' measurement of the return on contractor advance financing (deferred payment).
Core Conclusions
FIRR is the discount rate at which the cumulative present value of net cash flows over the project calculation period equals zero, i.e., Σ(CI−CO)ₜ·(1+FIRR)^(−t)=0, reflecting the project's actual rate of return; the project is viable when FIRR ≥ the benchmark rate. FNPV discounts each period's net cash flow at the set rate (generally the benchmark rate) and sums: FNPV > 0 is viable, larger is better. Hand-calculate IRR by trial-and-error interpolation: take r₁ < r₂ so that NPV(r₁) > 0 and NPV(r₂) < 0; IRR ≈ r₁ + NPV(r₁)/(NPV(r₁) − NPV(r₂)) × (r₂ − r₁), with the interval preferably ≤2% for accuracy. The payback period is the time for net returns to recover the investment: the static basis ignores the time value of money (when the cumulative net cash flow turns positive), the dynamic basis discounts at the benchmark rate before cumulating; the shorter the period, the stronger the risk resistance.
Applicable Boundaries
Applies to economic evaluation on the "calculation period + period net cash flows" basis; when contractors measure the return on advance-financed projects, distinguish the all-investment basis (total investment including borrowings as outflow) from the equity/own-funds basis (only own advance funding as outflow, interest as outflow — for judging the own-funds return rate). Benchmark rate: government-invested projects use state-published parameters, sector projects the sector benchmark, and self-evaluation may use the weighted average cost of capital (WACC) or the company's minimum required return. The cash flow statement must be prepared on the basis of the contract and the project execution plan (construction methodology and site organization), keeping the discounting basis and the tax-inclusive basis consistent.
Further Reading
See RISN-TG 029-2017, Technical Guideline for Building Photovoltaic Systems, Appendix A.2.4 (definitions and formulas of FIRR/FNPV/payback period); GB 50288-99, Code for Design of Irrigation and Drainage Engineering, Clause 4.4.2 (definitions and criteria of the indicators); T/CECA 20029-2023 Clause 13.3.5 (list of financial evaluation indicators); parameter determination principles per NDRC Investment [2006] No. 1325, Articles 5 and 11.
Keywords
- 财务内部收益率
- FIRR
- IRR
- 财务净现值
- FNPV
- 投资回收期
- 项目经济评价
- 盈利能力分析