Preparing the construction project cash flow forecast (funds utilization plan): dual bases of contract × project execution plan, dual revenue/expenditure lines, dual-basis closure

Preparing the cash flow forecast = translating the contract payment terms and the project execution plan's resource inputs into a monthly receipts-and-payments schedule: the revenue line (advance payment and its recovery, progress payments, final account payments, retention money recovery) and the expenditure line (labor/materials/machinery, subcontracting, site management fees, statutory levies and fees, taxes and duties, deposits and guarantees) are netted month by month; the lowest cumulative point is the maximum funding gap. The basis of preparation must match the construction contract, the approved project execution plan, and the planned schedule; the totals decomposed by cost item and by contract must close; the monthly rolling replaces forecasts with actuals.

Applicable Codes

  • GB/T 51095-2015 第7.2.1条
  • DBJ/T 15-153-2019 第5.11.2条
  • GB/T 51111-2015 第6.2.3条

Topic Positioning

How to prepare the construction project cash flow forecast table (in practice called the "funds plan / rolling cash flow forecast"): translating the payment terms of the construction contract and the resource input rhythm of the project execution plan into a monthly (weekly/quarterly) cash receipts-and-payments schedule, used to identify contractor advance financing (deferred payment) gaps, arrange financing, and manage collections.

Core Conclusions

① Three matches of the basis of preparation (GB/T 51095-2015, Clause 7.2.1): the funds utilization (cash-flow) plan must match item by item the construction contract (advance payment timing, progress payment nodes, final account nodes, retention money return), the approved project execution plan (output value and resource input intensity), and the planned schedule; the scope (whether free-issue materials (by the employer), specialist subcontracting, and permanent equipment procurement cost are included) must be agreed in the cost consulting contract in advance. ② Dual-line preparation: the revenue line = advance payment (including its recovery offsets) + monthly progress payments (completed output value × payment ratio, with the review lag usually 1–2 months) + final account payments + retention money recovery; the expenditure line = labor (migrant workers' wages paid in full monthly), materials (30–60 day credit), machinery, subcontract payments, site management fees, statutory levies and fees, taxes and duties (VAT under the current standard), deposits and guarantees. Monthly net cash flow = revenue − expenditure; the lowest point of the cumulative net cash flow is the maximum funding gap, usually appearing at 1/3–1/2 of the construction period after commencement. ③ Dual-basis closure (DBJ/T 15-153-2019, Clause 5.11.2): the totals decomposed by cost item and by contract must be identical, adjusted dynamically with progress, schedule, and the investor's funding situation. ④ Control measures (GB/T 51111-2015, Clause 6.2.3): formulate funds utilization control measures from the organizational, economic, technical, and contractual aspects; update monthly on a rolling basis, replacing forecasts with actuals.

Applicable Boundaries

Applies to funds planning and cash flow forecasting of main (general) contracting/specialist contracting projects; the key parameters (advance payment 10%–30%, progress payments 70%–90%, retention 3%, etc.) are general reference ranges — actual values must follow the contract's particular conditions; monthly is the norm, tightening to weekly when funds are tight early on. Not applicable to financing scheme design or single-point price queries.

Further Reading

See GB/T 51095-2015, Code for Construction Cost Consulting, Clause 7.2.1; DBJ/T 15-153-2019, Guangdong Code for Whole-Process Cost Management of Construction Projects, Clause 5.11.2; GB/T 51111-2015, Code for the Project Execution Plan of Open-pit Metal Mines, Clause 6.2.3; for the quantified contractor advance financing (deferred payment) measurement and the regulatory floors of progress payments/advance payments (GB/T 50500-2024 Clauses 9.1.7, 9.2.2, 10.2.4) see the related cards in this card's citation chain.