funds utilization (cash-flow) plan
- 01
Linking project cost indicators with the schedule plan: preparation binding → earned value monitoring → synchronized adjustment (GB/T 50502 7.6, GB/T 50326 11.2, GB/T 50358 2.0.8)
Three bonds link cost and schedule: ① preparation — the cost management…
GB/T 50502-2009 建筑施工组织设计规范GB/T 50326-2017 建设工程项目管理规范GB/T 50358-2017 建设项目工程总承包管理规范2026-09-25 - 02
Cost baseline system to be locked first in the project planning (early) stage: investment estimate → target cost → design quotas → investment control decomposition statement → funds utilization plan
What is locked in the planning stage is the "overall envelope + control…
DBJ/T 15-153-2019 广东省建设项目全过程造价管理规范DB11/T 1509-2018 公路工程设计导则铁基〔1987〕288号 铁道部关于限额设计试行办法2026-09-25 - 03
Preparing the construction project cash flow forecast (funds utilization plan): dual bases of contract × project execution plan, dual revenue/expenditure lines, dual-basis closure
Preparing the cash flow forecast = translating the contract payment term…
GB/T 51095-2015 第7.2.1条DBJ/T 15-153-2019 第5.11.2条GB/T 51111-2015 第6.2.3条2026-09-25