Cost baseline system to be locked first in the project planning (early) stage: investment estimate → target cost → design quotas → investment control decomposition statement → funds utilization plan
What is locked in the planning stage is the "overall envelope + control baselines", not specific itemized costs: the investment estimate sets the total investment ceiling and controls the design budget estimate; the target cost is in principle lower than the same-stage estimate/budget estimate/construction drawing budget/maximum tender price ceiling; design quotas are issued at three levels (scheme design / preliminary design / construction drawings) and refined as design proceeds; the investment control decomposition statement splits the total investment by cost items, contract sections, and responsible departments; the funds utilization plan fixes the timing. Levels control one another (budget estimate ≤ estimate, construction drawing budget ≤ budget estimate); the total quota is rigid and must not be breached while local transfers are allowed; cost items share one framework for comparability; at the estimate stage the target cost decomposition should leave headroom.
Applicable Codes
- DBJ/T 15-153-2019 广东省建设项目全过程造价管理规范
- DB11/T 1509-2018 公路工程设计导则
- 铁基〔1987〕288号 铁道部关于限额设计试行办法
- T/ZBD 100.2-2022 建设项目投资估算编制作业指引
Topic Positioning
This card answers "which costs should be locked first in the project planning (early) stage": a five-tier system of "overall envelope + control baselines" rather than specific work-item costs — the earlier the stage, the greater the influence on cost and the harder to change later.
Core Conclusions
Lock five tiers of baselines in order: ① the investment estimate = the ceiling of total project investment, controlling the design budget estimate; ② the target cost = the cost target calculated from construction standards and techno-economic indicators, in principle lower than the same-stage investment estimate, design budget estimate, construction drawing budget, and maximum tender price ceiling; ③ design quotas = three-level quotas for scheme design, preliminary design, and construction drawing design, issued before scheme design begins and refined as design proceeds; ④ the investment control decomposition statement = splitting the total investment by cost items, contract sections, and responsible departments; ⑤ the funds utilization plan = the timing of funding availability and annual use. The levels control one another: the design budget estimate is controlled within the approved investment estimate, and the construction drawing budget within the approved budget estimate. Cost items should share one framework, from coarse to fine, keeping the stages comparable; the total quota is rigid and must not be breached, while local breaches may be balanced by transfers among individual indicators within the total quota; at the estimate stage design depth is low, so the target cost decomposition should leave reasonable headroom.
Applicable Boundaries
Applies to cost control in the early/planning stage (preparation and review of investment estimates, design budget estimates, target costs, and quota design); planned costs, responsibility cost decomposition, and assessment baselines in the construction stage are subsequent links (see related cards). The railway sector has quantitative constraints: the total preliminary-design budget estimate generally shall not exceed the approved estimate by more than 10%; "target cost lower than the same-stage cost" is a Guangdong provincial requirement — when other regions adopt it by reference, local provisions prevail.
Further Reading
See DBJ/T 15-153-2019, Guangdong Code for Whole-Process Cost Management of Construction Projects, Clauses 3.2.3, 5.1.2, 5.1.3, 5.7.6, 5.8.1, 5.8.2, 5.9.4; DB11/T 1509-2018, Guidelines for Highway Engineering Design, Clause 13.2.1; Tie Ji [1987] No. 288, Ministry of Railways Trial Measures for Quota Design; T/ZBD 100.2-2022, Working Guideline for Preparing Construction Project Investment Estimates, Clause 7.3.6.
Keywords
- 项目策划阶段
- 前期阶段成本锁定
- feasibility-stage cost estimate
- target cost
- 设计限额
- 投资控制分解书
- funds utilization (cash-flow) plan
- 全过程造价控制
- 限额设计