target cost
- 01
Three-layer conditions for adjusting the target cost: trigger situations, non-adjustment constraints, and the re-approval procedure
Adjusting the target cost must simultaneously satisfy the trigger, const…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50502-2009 建筑施工组织设计规范GB/T 50358-2017 建设项目工程总承包管理规范2026-09-25 - 02
Construction cost management and responsibility-centre cost overview: the six-link closed loop, cost-plan preparation and three cost bases, responsibility decomposition and assessment
Cost management is the six-link closed loop of forecasting, planning, co…
GB/T 50326-2017 建设工程项目管理规范(第2.0.21、11.2.2~11.2.4条)GB/T 50502-2009 建筑施工组织设计规范(第7.6.1、7.6.2条)GB/T 50903-2013 市政工程施工组织设计规范(第6.5.1条)2026-09-25 - 03
Preparing the subcontract control price and the subcontract target price: concept distinction, preparation bases, inversion check, and linking the two prices
The subcontract control price is the enterprise's internal maximum bid l…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50326-2017 建设工程项目管理规范T/ZBD 100.1-2022 建设工程造价数据建设通用标准2026-09-25 - 04
Cost baseline system to be locked first in the project planning (early) stage: investment estimate → target cost → design quotas → investment control decomposition statement → funds utilization plan
What is locked in the planning stage is the "overall envelope + control…
DBJ/T 15-153-2019 广东省建设项目全过程造价管理规范DB11/T 1509-2018 公路工程设计导则铁基〔1987〕288号 铁道部关于限额设计试行办法2026-09-25 - 05
Positioning, distinguishing, and linking target cost, responsibility cost, and planned cost (the GB/T 50326-2017 Clause 11.2.4 procedure)
The three form a chain of "targets passed down level by level, responsib…
GB/T 50326-2017 建设工程项目管理规范 第11.2.2、11.2.4条GB/T 50502-2009 建筑施工组织设计规范 第2.0.15、7.6.2条DBJ/T 15-153-2019 广东省建设项目全过程造价管理规范 第5.7.3条2026-09-25